Site conducted
-
Conducted on
-
Prepared by
Small Lidder
-
Is there a full stack of card available on the cardboard feeds?
-
Why has the card not been refilled ready for the next shift?
-
Is the glue tank filled to an appropriate level and ready for the next shift?
-
Why has the glue tank not been refilled and ready for the next shift?
-
Has all rubbish been disposed of correctly?
-
What is the reason for the rubbish not being disposed of correctly?
-
Is the machine working correctly and ready to use on the next shift?
Large Lidder
-
Is there a full stack of card available on the cardboard feeds?
-
Why has the card not been refilled ready for the next shift?
-
Is the glue tank filled to an appropriate level and ready for the next shift?
-
Why has the glue tank not been refilled and ready for the next shift?
-
Has all rubbish been disposed of correctly?
-
What is the reason for the rubbish not being disposed of correctly?
-
Is the machine working correctly and ready to use on the next shift?
Large Box Erector
-
Is there a full stack of card available on the cardboard feeds?
-
Why has the card not been refilled ready for the next shift?
-
Is the glue tank filled to an appropriate level and ready for the next shift?
-
Why has the glue tank not been refilled and ready for the next shift?
-
Has all rubbish been disposed of correctly?
-
What is the reason for the rubbish not being disposed of correctly?
-
Is the machine working correctly and ready to use on the next shift?
Small Box Erector
-
Is there a full stack of card available on the cardboard feeds?
-
Why has the card not been refilled ready for the next shift?
-
Is the glue tank filled to an appropriate level and ready for the next shift?
-
Why has the glue tank not been refilled and ready for the next shift?
-
Has all rubbish been disposed of correctly?
-
What is the reason for the rubbish not being disposed of correctly?
-
Is the machine working correctly and ready to use on the next shift?
Tote Stacker
-
Have the totes been stacked on the conveyor ready for use?
-
Why have the totes not been stacked and ready for use?
-
Have you cleared any faults with the machine?
-
What are the issue that couldn't be cleared?
-
Is the area around the tote stacker clear?
-
Is the machine ready for the next shift?
-
What are the outstanding issues?
Auto Bagger
-
Have all shift issues been documented?
-
Why have the issues not been documented?
-
Is the heat seal, sealing correctly?
-
What is the issue with the heat sealer?
-
Is there enough bagging plastic on the machine ready for the next shift?
-
Why has the bagging plastic not been filled?
-
Are both conveyors working correctly?
-
What is the issue with the conveyors?
-
Is the Autobagger ready for the next shift?
-
What issues are outstanding?
Conveyor & HMI
-
Have all blockages been resolved?
-
Have all issues on the HMI been cleared?
-
What are the outstanding issues?
-
Is the conveyor system ready for the next shift?
-
What are the outstanding issues?
Sign off
-
Completed by:
-
Handover received by: