Title Page
-
Site location
-
Date
-
Prepared by
-
Gang ID number:
Daily Requirements
-
Have the RAMS been read and understood by all on site?
-
Do you have access/ have you been issued company RAMS?
-
Do you have the relevant tools/equipment to complete the task?
-
Have you got the relevant task order to do the job ?
-
Do you understand the task instructions?
-
If the task instruction is difficult to understand and you require additional assistance, please contact planning or a supervisor.
-
Is all the relevant PPE to be used in good condition?
-
Are you working on a permit?
-
All equipment safe to use?
-
Do operatives on site have the appropriate PPE?
-
Please provide photo evidence of safety equipment relevant to the scope of works.
Task Instruction
-
What type of works is being carried out?
OH Working
-
In date LOLER plate
-
FibreGlass Ladder
-
Harness, Lanyard + Working Belt with Inspection tags.
UG Working
-
GDU Calibrated and in good working order
-
Water Sampling Kit
-
Lifting Keys
-
Gate Guards
-
SLG in use?
-
Please upload photos throughout the day of works in progress. If unsure please ask your supervisor.
-
Site set up at start of works?
-
Site set up at during works?
-
Site set up at end of works?
-
Pre-work Risk Assessment : Identify HAZARDS assess the RISK rating.
- Access & Egress
- Over-head hazard
- Slips, trips and falls
- Underground services
- Leptospirosis
- Manual handling
- Weather
- Traffic/pedestrians
- Poor house-keeping
- Site Protection/TM
- Gas Test
- Task Lighting
- Water Test
- Enclosed Space Equipment
- Rescue Plan
- Communication
- Waste Plan
Lead fibre engineer
-
Add signature
Fibre engineer
-
Add signature
Visitors
-
Add signature
End of works Progress report
-
Please provide relevant information about the progress of works.