Fire Extinguishers
FIRE EXTINGUISHERS
Basement
-
01 Oil Tank Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
02 Oil Thank Room Powder 6 Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
03 Transformer Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
04 Transformer Room Co2 5 Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
05 AHU Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
06 AHU Room Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
07 Heating Plant Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
08 Heating Plant Room Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
09 Gas Meter Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
10 Gas Meter Room Powder 6Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
11 LV Switch Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
12 LV Switch Room Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
13 Sub Station Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
14 Sub Station Room Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
15 Switchgear Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
16 Switchgear Room Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
17 Car Park Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
18 Car Park Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
19 Car Park Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
20 Car Park Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
21 Loading Bay Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
22 Loading Bay Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
23 Loading Bay Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
24 Loading Bay Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
25 L/Bay Dock Office Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
26 L/Bay Dock Office Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
27 Core 1 Stairs Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
28 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
29 Core 2 Stairs Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
30 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
31 Core 3 Stairs Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
32 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
Ground
-
33 Reception Front Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
34 Reception Front Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
35 Atrium Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
36 Atrium Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
37 Fire Command Centre Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
38 Fire Command Centre Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
39 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
40 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
41 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
42 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
43 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
44 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
44A Main Core Corridor Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
44B Main Core Corridor CO2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
45 East Fire Exit Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
47 West Fire Exit Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
48 West Fire Exit Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
49 Plant Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
50 Plant Room Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
1st Foor
-
51 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
52 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
53 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
54 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
55 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
56 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
2nd Floor
-
57 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
58 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
59 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
60 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
61 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
62 Core 3 Stair Foam CO2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
3rd Floor
-
63 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
64 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
65 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
66 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
67 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
68 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
4th Floor
-
69 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
70 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
71 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
72 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
73 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
74 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
5th Floor
-
75 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
76 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
77 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
78 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
79 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
80 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
6th Floor
-
81 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
82 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
83 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
84 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
85 Core 3 Stair Foam 9 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
86 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
7th Floor
-
87 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
88 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
89 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
90 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
91 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
92 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
8th Floor
-
93 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
94 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
95 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
96 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
97 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
98 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
9th Floor
-
99 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
100 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
101 Core 2 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
102 Core 2 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
103 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
104 Core 3 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
10th Floor
-
105 Core 1 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
106 Core 1 Stairs Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
107 Core 3 Stair Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
108 Core 3 Stairs Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
109 Atrium Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
110 Atrium Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
111 Artium Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
112 Atrium Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
113 Plant Room Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
114 Plant Room Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
115 Lift Lobby Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
116 Lift Lobby Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
117 Plant Room 2 Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
118 Plant Room 2 Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
119 Plant Room 3 Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
120 Plant Room 3 Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
Roof
-
121 Plant Cabinet 1 Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
122 Roof Cabinet 1 Co2 5Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
123 Roof Cabinet 2 Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
124 Roof Cabinet 2 Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
125 Roof Cabinet 3 Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
126 Roof Cabinet 3 Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
127 Roof Cabinet 4 Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
128 Roof Cabinet 4 Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
129 Roof Cabinet 5 Foam 6 Litre
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
130 Roof Cabinet 5 CO2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
131 LV Switch Room 1 Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
132 LV Switch Room 2 Co2 2Kg
-
Is the seal and pin in place?
-
Is the annual inspection in date?
-
Add signature
Fire Telephones & Emergency Call Point Check
Core 1
10th Floor Core 1
9th Floor Core 1
8th Floor Core 1
7th Floor Core 1
6th Floor Core 1
5th Floor Core 1
4th Floor Core 1
3rd Floor Core 1
2nd Floor Core 1
1st Floor Core 1
Ground Floor Core 1
Basement Floor Core 1
Core 2
10th Floor Core 2
9th Floor Core 2
8th Floor Core 2
7th Floor Core 2
6th Floor Core 2
5th Floor Core 2
4th Floor Core 2
5th Floor Core 2
4th Floor Core 2
3rd Floor Core 2
2nd Floor Core 2
1st Floor Core 2
Ground Floor Core 2
Basement Floor Core 2
Core 3
10th Floor Core 3
9th Floor Core 3
8th Floor Core 3
7th Floor Core 3
6th Floor Core 3
5th Floor Core 3
4th Floor Core 3
3d Floor Core 3
2nd Floor Core 3
1st Floor Core 3
Ground Floor Core 3
Basement Floor Core 3
-
-
Add signature
Eye Wash Sets
Basement AHU/ Pump Room
-
Eyewash 2 x 500ml, 10 x 1ml
-
-
Eye Pod Dressing x 1
-
-
Napkins x 1
Basement Water Tank Room
-
Eyewash 2 x 500ml, 10 x 1ml
-
-
Eye Pod Dressing x 1
-
-
Napkins x 1
Basement Heating Plant Room
-
Eyewash 2 x 500ml, 1
-
Basement Oil Tank Room
-
Eyewash 2 x 500ml, 10 x 1ml
-
-
Eye Pod Dressing x 1
-
-
Napkins x 1
Basement Sprinkler Tank Room
-
Eyewash 2 x 500ml, 10 x 1ml
-
-
Eye Pod Dressing x 1
-
-
Napkins x 1
Basement Car Park Rain Attenuator (Irrigation) Room
-
Eyewash 2 x 500ml, 10 x 1ml
-
-
Eye Pod Dressing x 1
-
-
Napkins x 1
Roof Core 3 Lobby outside Plant Room
-
Eyewash 2 x 500ml, 10 x 1ml
-
-
Eye Pod Dressing x 1
-
-
Napkins x 1
Roof 10th floor Main core plant room North Plant access near generator
-
Eyewash 2 x 500ml, 10 x 1ml
-
-
Eye Pod Dressing x 1
-
-
Napkins x 1
-
Add signature
Fire lift check
-
lift key 22. Drive the lift in fireman's mode to any floor. When you arrive at the floor press and hold the door button to check the doors open.