Title Page
-
Conducted on
-
Prepared by
-
W/O#
-
WR#
-
Date Completed
-
Inspector
-
Date inspected
-
Project type
- CIRCUIT INSPECTION
- FAILED EQUIPMENT NO OUTAGE
- NEW CUSTOMER
- RECLOSER REPLACEMENT
- RELOCATION
- SECTIONALIZING
- SMALL WIRE REPLACEMENT OVER HEAD
- UPGRADES
-
# of Point Sheet/Pole Location
-
# of Equipment
-
# Standards to Inspect
-
All point Sheets were installed to AEP standards (if no, list point sheet # and deficiencies below)
-
Equipment was tested or visually approved
-
(Please double check that all pole sizes are correct on the Maps). All redlines were noted on the job sketch (MAPS)
-
All materials/trash removed from job site
-
Job site free of hazards
-
Notes: (List any deficiencies found)~
-
Inspected and meets AEP Standards
- Pass
- Fail
Rework inspection
-
Note: inspection must be recorded in DWMS
-
Rework inspection date
-
Rework Completed on
-
Inspected and meets AEP Standards
- Pass
- Fail
Management Review
-
Signature
-
Date Completed