Information
-
Document No.
-
PROJECT NAME
-
PROJECT NUMBER
-
Conducted on
-
Prepared by
-
Location
-
Personnel on worksite
AHB SUPERINTENDENT
PERSONAL PROTECTIVE EQUIPMENT
-
Hard hats (with bills forward)
-
Safety glasses appropriate for conditions (tinted or clear)
-
Hard toe work boots
-
Reflective vests
-
Gloves
-
Hearing protection if required
-
Face shields for cutting or grinding
HOUSEKEEPING
-
General site storage and housekeeping
-
Trash cans in work area
-
Storage / Dog House orderly
-
Safe walkways or passages
-
Spill Kits Available
TEMPORARY BARRICADES
-
Proper tape used (red for danger, yellow for caution)
-
All sides of work area barricaded and labeled (if required)
LADDERS AND ELEVATED WORK
-
Ladders tied off
-
Ladder extended 3'
-
Ladders Inspected
-
Damaged ladders tagged Out-of-Service
-
Handrails and/or barricades in place
-
Employees tied off when working over 6 feet
FALL PROTECTION
-
Harness and lanyards used correctly
-
Harness and lanyards inspected prior to use
-
Hole protection used during working hours
-
Proper hole protection used after hours
MOBILE EQUIPMENT
-
Inspected prior to each shift
-
Seatbelts used
-
Workers trained
-
Backup alarms working
-
Spotters used when needed
-
Equipment maintained without leaks
-
Safety guards and covers in place
-
Whip-checks used on pressurized lines
HOISTING AND RIGGING EQUIPMENT
-
Annual inspection placard in place
-
Daily crane inspection performed and documented
-
Operators manual in cab
-
Rigging inspected prior to each use
-
Proper rigging and techniques used
-
Rigging properly stored
-
Qualified rigger/signal person being used
-
Safety latch on hooks
-
Workers staying clear of suspended loads
-
Knowledge of crane signals
-
Proper use of tag lines
-
Swing radius protection in place
EXCAVATION
-
Means of exiting in place for excavations deeper than 4 feet
-
Cave-In protection in place for excavations deeper that 5 feet
-
Shaft stability measures properly used (casing, fluid level maintained, etc)
-
Spin off area maintained
-
Equipment staged a safe distance away overnight
COMPRESSES GAS CYLINDERS
-
Stored upright and succored
-
Stored at least 20 feet apart
-
Separated by a 1 hour rated fire wall while in use
-
Hard caps in place when not in use
REBAR PLACEMENT
-
Lifting properly planned, communicated and managed
-
Cage properly prepared with #9 wire and/or clamps
-
Cage properly rigged for lifting
-
Cage lifted and secured in shaft safely
CONCRETE OPERATIONS
-
Concrete pump and hoses used properly
-
Slick lines and hoses properly clamped with safety wire
-
Concrete washed from skin contact
PREWORK
-
Weekly Toolbox Talks are relevant to the project, and documented
-
Safe Work Plan communicated to all employees
-
SDS for all chemicals on the project are available upon request
-
Supervisors are aware of local first-aid and hospital facilities
-
All required jobsite work permits, hot work permits, excavation permits, obtained
-
Underground locates are in place and current
-
First Aid Kit is on site in a sanitary condition and available to all employees
-
Employee training records are available for work being performed
REPRIMANDS OR WARNINGS
-
We're any reprimands issued?
-
We're any verbals warnings or directives given?
-
Was any Stop Work order issued?
COMMENTS
-
Add media
INSPECTION PERFORMED BY:
-
Add signature