Information
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
1. Working at Heights
-
1.1. Fall risks of 6ft or more? (including voids, pits, and trenches)
-
1.2. Lack of edge protection?
2. Trenching
-
2.1 Adjacent Structures Shored
-
2.2 Cave in protection?
-
2.3 Ladders provide as needed?
3. Scaffolds
-
3.2. Unsafe or incomplete scaffold?
4. Tools
-
4.0 Tools have all parts as sent from manufacturer?
-
4.1. Unsafe or damaged tools?
-
4.2 Cords are grounded correctly?
5. Harness and Equipment
-
5.1. Unsafe or damaged harness or equipment?
-
5.2. Incompatible hooks/equipment?
-
5.3. Unlabelled or does not meet AS?
-
5.4. Unsafe or uncertified anchor points?
-
5.5. Lack of inspection protocol for equipment?
-
5.6. Lack of or inadequate formal training for operators?
6. Ladders
-
6.1. Unsafe or damaged ladders?
-
6.2. Unsafe positioning of ladders?
-
6.3. Ladder not properly secured?
-
6.4. Ladder unsuitable for job? (e.g. metal ladder used for electrical work)
-
6.5 Sufficient amount of ladders for job?
7. Gear and Panels
-
7.1. Lack of identification of hazardous equipment? (Arc Flash Identification)
-
7.2. Proper labeling of Energized equipment?
-
7.3. Panel covers or temp covers on all energized panels?
-
7.4. Lack of training in risk controls and safe lifting/ team lifting techniques?
8. Hazardous Chemical (including fuel and oil)
-
8.1. Unsafe storage location? (e.g. flammables near ignition sources, spills could enter stormwater drains, etc)
-
8.2. Incompatible chemicals stored near each other?
-
8.4. Safety Data Sheets not accessible on site?
-
8.5. Fire extinguishers charged and accessible?
-
8.6. Excessive quantities stored on site or in vehicles?
-
8.9. Unsuitable storage containers? (unlabeled or stored in food containers)
9. Emergency Response
-
9.1. Lack of, or no emergency plans for site?
-
9.3. Lack of training and rehearsal of emergency plans?
-
9.4. Lack of, or inadequate first aid kits aid equipment for site?
-
9.5. Insufficient access to formally trained First Aiders for all shifts?
-
9.6. Unsuitable or inadequate communication equipment?
11. Personal Protective Equipment (PPE)
-
11.1. Lack of, or inadequate PPE? (Face shield, gloves, or hearing protection)
-
11.3. Lack of training in safe use, clean-up and inspection of PPE?
-
11.4 Hard hats being used at all times?
-
11.5 Safety glasses worn at all times?
-
11.6 Proper footwear is being worn?
-
11.7 Hearing protection available and being used?
12. Work Environment
-
12.1. Lack of/or inadequate amenities? (toilets, wash areas, lunch rooms, etc)
-
12.2. Insufficient lighting?
-
12.3. Inadequate housekeeping?
-
12.4 Access to breaker ones clear?
-
12.5 Passage ways clear of debris or obstructions?
13. Electrical Hazards
-
13.1. Unsafe electrical leads? (damaged, out of test date or untested)
-
13.2. Lack of GFI protection?
-
13.3 GFI tested weekly?
-
13.5. Overloading outlets?
-
13.7. Electrical equipment near water?
-
13.8. Electrical equipment near flammables?
-
13.9. Electrical equipment near chemicals that could cause damage?
-
13.10. Electrical leads that may be damaged from contact with moving construction equipment or personel?
-
13.11. Electrical leads on work surfaces?
-
13.12. Lack of Lock-out/tag-out (LOTO) procedures for electrical equipment?
14. Environmental Hazards
-
14.1 Smoking laws being followed?
-
14.2. Lack of/or inadequate, dust suppression system?
15. Administrative Procedures
-
15.1. Lack of/or inadequate Site Safety Plan?
-
15.2 OSHA postings and Emergency Contact Numbers posted in G.C. Trailer?
-
15.3 MSDS book in G.C. Trailer?
-
15.4. Lack or, or inadequate, supervisory arrangements?
-
15.5. Lack of/or inadequate training, licenses, skills, experience?
-
15.6 Weekly safety meeting?
-
15.8. Lack of/or inadequate incident notification procedures?
-
15.9. Lack of, or inadequate, routine inspections, monitoring, audits?
-
15.10. Jobsite orientation
Corrective Actions
-
Enter any corrective actions that will be undertaken
Sign Off
-
On site representative
-
Auditor's signature