Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Position of Conductor
-
Dept/Contractor
-
Location
-
Name of Person in Charge
-
Number in Team
-
Name of COSS / PC/ ES
-
Sentinel No
Immediate Observations
-
Detail of Work being undertaken
1. Health and Safety
-
Is there a Site Office?
-
Is the access of a good standard?
-
Was the Site Briefing carried out?
-
Is all Site Documentation/Task Documentation on site?
-
Has all Electricity on site been accounted for?
-
Is all Staff PPE Correct?
-
Is Welfare on site sufficient and cleaned?
-
Was the site clean and tidy, with all materials stored correctly?
-
Has the First Aid person/kit been identified?
-
Were all the necessary H&S Documentation displayed?
-
Are all Permits in place for the required work?
-
Are all Flammables stored correctly and clearly marked?
-
Is there a Fire extinguisher present, and all flammables far away from Hot Works?
-
Are all Hand Tools well maintained, inspected and used by a competent person?
-
Have all the necessary Security measures been adhered to?
-
Have all staff recieved Manual Handling training and all tasks risk assessed?
-
Have all COSHH items had the required assessment?
-
Are all materials Stored correctly and safely, clearly labelled?
-
Good practice states that polluting substances should be stored more than 10 metres from the nearest receptor, i.e. watercourses or drains. The first step is to know where receptors are.
-
Are all correct measures in place to ensure Public Safety?
-
Does the team have the required tools to Work at Height?
-
Are the necessary Traffic Management procedures in place?
-
Have the questions/concerns of the Work Force been listened to or answered?
-
Have all control measures regarding Noise been implemented?
-
Have all Hand Arm Vibrations (HAVs) related tasks been risk assessed correctly?
-
Does all Plant and Equipment have the required documentation, certification and SSOW?
-
Has all of the Lifting Equipment undergone the necessary inspections/examinations? Relevant plans?
-
With Breaking Ground/Excavations, have they been checked for Utility Plans, GPR/CAT Scanning, PTW, Safe Digging, Temporary Works, Calibration of CAT, Competency?
2. Item Inspections/ Observations
-
Have the team been briefed about the Safety Reporting Arrangements?
-
Has the Signaller been Notified?
-
Have the team been briefed about the Protection Arrangements?
-
Was the Supervision of Works sufficient?
-
Was the Safe System of Work sufficient?
-
Were all of the Sentinel Checks completed?
-
Any other concerns regarding Item Inspections/Observations?
3. Planning and Documentation
-
Have Colleagues been briefed on environmental aspects and the associated risks and opportunities on site?
-
Are Operational Control Procedures available and briefed to manage these Risks and Opportunities?
-
Have all Licenses/Permits/Consents (ecology, noise, discharge, waste) been received for the relevant site works: Are conditions being met?
-
Have Environmental actions been implemented from previous HSEQ Inspections?
-
Are Emergency Plans in place; Are Site Workers aware of incident response procedures?
4. Nuisance: Noise, Vibration, Visual
-
Are local authority/local residents informed of the works?
-
Are Section 61 noise consents in place, all plant/equipment listed, conditions followed?
-
Are Barriers and other mitigation measures (BPM) being used to limit noise and vibration?
-
Best Practicable Means: BPM are defined in Section 72 of the Control of Pollution Act 1974 and Section 79 of the Environmental Protection Act 1990 as those measures which are: “reasonably practicable having regard among other things to local conditions and circumstances, to the current state of technical knowledge and to financial implications
-
Is plant in good order, away from site boundaries and turned off when not in use? In addition, are vehicles waiting to enter the site turned off?
-
Has the site neighbour’s view of site been considered: Confirm there is no light spilling over, portable screens are being used etc?
5. Ecology
-
Are protected species/areas known, with measures (e.g. fencing) used to minimise impact?
-
Have invasive species been identified and means implemented to prevent spreading?
-
Are Tree Preservation Order (TPO) Zones Signed and fenced off?
-
Have you ensured vegetation clearance is not done during nesting season (Mar-Aug), or pre-start checks are conducted by competent person(s)?
-
Is there a procedure set for reporting unexpected finds (nesting birds/badger setts/newts); are site workers aware of the procedure? Coruson Close Called?
6. Air Quality
-
Is hard standing and road free of mud/dust? Unsurfaced damped down?
-
Are vehicle loads kept covered and wheels clean when entering and leaving site? Are vehicles wheels washed on exit and entry to site?
-
Are there signs of fumes from equipment/vehicles? (Excluding exhaust fumes)
-
Is particulate monitoring being undertaken on site in dust heavy zones?
7. Oil storage, fuel and bunding
-
Are tanks, barrels, drums, securely stored, in good state and in a bunded area?
-
Are bunds at 110% capacity of the greatest or 25% of total tank volume, and structurally sound?
-
Are drip trays/others available for plant when refuelling?
-
Are oils stored away from storm drains, ditches, watercourses, sensitive areas and no visible contamination around the storage area?
8. Emergency Response
-
Are spill kits available near potential spill areas: suitable/adequate for type/ amount of fluid used/stored?
-
Have you ensured there is no visible pollution in storms drains, ditches (dry/wet), watercourse?
-
Have protective measures, where required, been implemented for drains, ditches and water courses?
9. Waste
-
Has a SWMP been implemented and briefed on site? Is it being adhered to?
-
Is spoil handled properly (away from watercourses/covered)?
-
Is waste segregated, labelled and secured?
-
Are waste transfer notes and hazardous waste consignment notes held on site and have they been completed correctly?
-
Are waste containers/skips clear, not overfilled, and no loose trash/litter around?
-
Has the works team demonstrated the effective reuse of materials/waste, either on the project site or offsite on another project?
10. Energy, Resources and Timber
-
Is energy efficient machinery, plant and equipment being used and maintained?
-
Has the use of renewable energy been considered e.g. Solar panels, hybrid generators?
-
Is the Site utilising low carbon fuels where possible?
-
Is water use being minimised on site? Are water reuse initiatives being implemented on site?
-
Is evidence available to demonstrate that the timber being used is credibly certified to FSC/PEFC standard?
11. General Competency
-
Has the Quarantine Area been clearly Identified or process briefed out?
-
Has the work been carried out to the required standard, has all work been carried out in line with the methodology stated on site?
-
Have all of the required test and inspections relating to the works been carried out, completed and documented?
-
Have all of the relevant calibration regarding works been completed and documented?
-
Are all Certificates of Conformity accessible?
-
Do all Employees/Contractors hold the necessary competency to carry out the duties of the task they’re completing (ATW/Safety Critical Competencies/CSCS Cards)?
-
Have all Temporary Works been designed by a competent Temporary Works Professional, and is all the relevant documentation available?
-
Any additional information/issues/problems or points regarding the quality of the work being carried out?
Summary of Findings
-
Overall Comments
-
Authority to Work - Competence Criteria Observed (add observed Employee Name and Criteria)
-
Future Actions
-
Detail of Actions to be Taken
-
Actions to be Taken by Who
-
Date of Actions to be Taken
-
Please Sign Name
-
Please Print Name