Insert Date and Time
Planning for Health and Safety
-
The GC is aware of and is compliant with the Amazon Developer, Contractor and Vendor Health and Safety Performance Standards
-
The General Contractor holds formal H&S meetings between the contractors present on site?
-
The H&S plan has been updated, is current and being implemented?
-
The H&S plan indicates responsibilites for implementation.
-
Add pictures here if required
-
Insert any comments you have on this section in here.
Covid 19
-
Is there a Site-Specific COVID-19 Health and Safety Plan in place for the site
-
Is there a reporting protocol when workers are diagnosed as carrying COVID-19 or suspected/confirmed as having been exposed to COVID-19 and has this been communicated to the site operatives.
-
Is there signage on site in relation to Covid 19
-
Is there a site monitor stationed at the project entrance AND actively engaged in site work force observation to provide education and monitoring; provide verification of the COVID-19 guidelines around the site and observe workforce to identify any workers that have symptoms (cough, sneeze, runny nose temperature)
-
Is there a procedure in place that delivery drivers and visitors are not allowed on site without adherence to Site-Specific COVID-19 Health and Safety Plan and escorted around the site?
-
Is there social distancing and people seperation measures in place on site and are they being adhered to as much as reasonably practicable?
-
Is there adequate cleaning facilites in place on site and are they being used as needed?
-
Has appropriate PPE been supplied if social distancing cannot be guaranteed?
-
Do you have any further concerns regarding the GS compliance with the Amazon Covid 19 Protocol?
Contractor/Sub Contractor Requirements
-
Contractors are working to the requirements detailed in the GC H&S plan
-
The GC has defined the minimum H&S competencies required by contractor/ sub contractors supervision
-
Specific arrangements are in place for those who do not speak the country language of the project
-
Contractors carry out regular H&S training, briefings, tool box talks etc
-
Contractors have been made aware of Amazon Developer, Contractor and Vendor Health and Safety Performance Standards
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Access control and security
-
The project perimeter is secure and access by unauthorised persons is prevented
-
Access is controlled for the workforce and visitors and linked to the Induction process
-
Pedestrian and vehicle access is separated , safe and functioning.
-
Understandable H&S information is given to delivery drivers
-
Multiple access gates operate to the same access control standards.
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
H&S Induction and Training
-
The GC has prepared a project specific H&S Induction which is being delivered on the project
-
The H&S Induction specifically addresses Fatal Risks, Site Controls and focus and individual inputs required.
-
The H&S Induction is required to gain access on to the project.
-
The H&S Induction for Amazon Contractors is the same as or equal to the above.
-
It is possible to identify anyone who has been H&S Inducted out on the project.
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Risk Assessment and Method Statements
-
Arrangements are in place to obtain RAMS in advance of works , authorise and retain records
-
Proof of briefing records are available for any vetted and authorised RAMS Contractors supervisors have been involved with, have knowledge of and are supervising works as defined within vetted RAMS
-
Sub contracted elements of activities are subject to the same controls listed above
-
There are arrangements for managing H&S if the methodology is required to change
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Supervision, Competency
-
The GC has defined minimum H&S responsibilities for all supervisors on the project.
-
Records are available confirming supervisors competency checks
-
Supervisors can be easily identified out on the project
-
The role of supervisors when unsafe working, acts or conditions are identified is always considered
-
Supervisors working for Amazon cooperate with the GCs arrangements for managing H&S
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
H&S support and advice
-
The GC is supported by adequate H&S expertise.
-
All H&S appointees coordinate and work together with agreed forms of communic ation, protocols and prioritisation
-
The H&S teams are empowered to stop unsafe working if required.
-
Positive H&S performance, practices and behaviours are identified and recorded.
-
H&s performance data is produced, reviewed and visible to the project workforce.
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Non conformance and Escalation Process
-
The GC has a formally defined process for dealing with non conformances including an escalation protocol.
-
Unsafe working involving fatal risks is prioritised
-
The escalation process is used when required with evidence available
-
Unsafe working is stopped by the GC/ Contractor supervision when required
-
Near miss events are reported and acted upon
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Monitoring and Inspection
-
Effective arrangements are in place for the oversight and monitoring of H&S on the project involving the GC team, Contractors and H&S.
-
Plant and Equipment maintenance records are available and regular inspections and checks are being done
-
Monitoring and checks for occupational health issues are being carried out
-
Supervisors are involved in monitoring and inspection checks.
-
H&S meetings include review of H&S inspections, audits and checks?
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Personal protective equipment
-
Minimum PPE requirements have been established and are being complied with on the project
-
PPE Site rules are confirmed in H&S Induction and by signage on the project.
-
Additional PPE is being worn when required as detailed in RAMS or as required by project conditions
-
Amazon Contractors are complying with site PPE rules.
-
PPE is adequate and suitable, well maintained and being worn correctly
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Emergency arrangements
-
The GC has defined arrangements for Fire, Evacuation and Medical emergencies which are implemented on the project
-
Contractors have trained first aiders within their workforce
-
Fire prevention , detection and means of sounding alarm is in place and is effective
-
Control gate staff are aware of actions to be taken in the event that external emergency services are called
-
Operatives out on the project can confirm emergency arrangements when asked
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Housekeeping and waste materials, lighting
-
Access to and throughout the project is safe as a result of good housekeeping, rubbish removal and lighting.
-
Discarded materials are removed as soon as practicable.
-
Access lighting is provided within the building(s), access to same and within compound and gate areas .
-
Building materials are stored in designated areas, are stable and secured against movement.
-
Portable Halogen lighting is not in use
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Reporting of unsafe, acts, conditions, near miss events and incidents
-
The GC has arrangements in place for reporting unsafe acts, behaviours, conditions or incidents.
-
Records are available and used for contractor performance data
-
Corrective actions are recorded and effectiveness checked to prevent reoccurences
-
Positive and negative feedback is given to the workforce following any of the above occurences
-
Training and rebriefings are carried out
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Information, signage
-
There is adequate information, signage and warning notices in place on the project.
-
Information is regulary updated giving details of current high risk activities, performance, lessons learned and themes related to hazard awareness or health risks.
-
Warning signage is in place in high risk zones.
-
Emergency action signage is in place and visible to workforce
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Plant, Equipment, Tools
-
Working arrangements are evident to ensure plant , equipment and tools are maintained and are used by trained and competent individuals.
-
On site checks are carried out for operator competence,plant certification and equipment maintenance.
-
Plant and equipment is secured against unauthorised use
-
Electrical supplies for use or charging are safe , maintained and protected
-
When working at height effective measures are in place to prevent tools falling or persons below being struck by works above.
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Amazon Contractors
-
Amazon contractors are fully engaged with the GC in maintaining H&S standards and for coordinating and controling activities to achieve the same.
-
Arrangements are in place to secure access in high risk zones under commisioning and testing
-
Authorised persons are designated and control access to electrical supplies.
-
H&S standards in early access areas match or exceed GC areas
-
Early access zones are barriered off.
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Corrective actions , Improvements and best practice
-
Corrective actions are effective, H&S standards are improving and best practice is adopted whenever possible.
-
H&S performance data is available showing KPIs , trends and overall project H&S standards
-
Best practice and suggestions for improvements are implemented with feedback given to the workforce.
-
Best practice is shared with other projects
-
Self policing actions by contractors and or individuals is recognised .
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Welfare
-
Sufficient Toilets, washing and welfare facilities are provided which are operational, maintained and safe to access.
-
Toilet facilities are provided on safe locations out on the project
-
Compliant and sufficient first aid arrangements are in place
-
Canteen facility is provided
-
Designated smoking areas are provided
Add pictures here if required
-
Add media
-
Insert any comments you have on this section in here.
Storage, containers, fuels and gases
-
Designated storage areas are in place for all materials, waste, equipment , fuels and gas supplies
-
Fuel storage arrangements and dispensing are compliant and safe.
-
Storage facilities and laydown areas are safe to access at all times.
-
Information on hazardous substances is available and being used
-
The location of gas bottles is always known