Department of Housing and Public Works
Trade Hazard and Risk Analysis.
-
Project/Site
-
Contractor
-
Contractor Rep's Name
Review the following items/activities and the control measures and tick the check box for yes if appropriate. The control measures are defined inside the brackets.
-
Demolition (Notifiable activity (5 days prior) Refer QBuild Standards Section 9.7)
-
Personnel/Plant to work within Exclusion Zones of Overhead Electrical Service Line (Service Provider to inspect Service and issue Safety Advice. WMS to be in place. QBuild Standard Section 7.9)
-
Underground Water/Gas/Electrical/Data Services in/near work area. (Services to be located prior to excavation. QBuild Standard Section 4.1)
-
Water/Gas/Electrical/Data cables/services in walls, floors, ceilings etc. in/near work area. (Services to be located prior to commencement of work. QBuild Standard Section 4.1)
-
Work on/near unprotected electricity supply/installations (LIVE WORK) (Live Work NOT to be undertaken without WMS and approval from QBuild. QBuild Standard Section 7.10)
-
SITE ACCESS/SECURITY Public Pedestrian access required through/near the site/work area. (Barricading required. QBuild Standard Section 3.11 - 3.12, 8.6, 9.13)
-
Traffic management required around site works. (Traffic management plan, traffic controllers. QBuild Standard Section 3.13 - 3.14, 8.6)
-
Children near Work Area (eg. Schools/Housing sites) (Barricading required. QBuild Standard Section 3.13 - 3.14, 8.6)
-
Site/Building will be occupied by tenants/public during construction. (Hoarding/Barricading required. QBuild Standard Section 3.13 - 3.14, 8.6)
-
AIR/EXPLOSIVE OPERATED POWER TOOLS Air Operated Nail Guns/Explosive Power Operated Tools in use. (PPE and signage required. QBuild Standard Section 8.3,8.13)
-
Work involving Compressed Air (eg. Spray painting) (PPE and signage. QBuild Standard Section 8.13, 8.6, 9.5)
-
MANUAL/MATERIAL HANDLING Lifting or moving Heavy/Awkward Loads (Lifting/moving equipment required. QBuild Standard Section 5)
-
Materials/Equipment to be lifted to elevated areas (Mechanical equipment required. QBuild Standard Section 5)
-
WORKING AT HEIGHTS (GRAVITATIONAL) Work above 2.0m (Fall protection equipment required. QBuild Standard Section 3)
-
Working with/from cranes (Licensed Dogman required. QBuild Standard Section 8.14)
-
Work involving Elevating Work Platforms (Scissor or Boom Type) Licensed operator required. QBuild Standard Section 3.18, 3.19)
-
Work from Scaffolding (Erection by competent person required. QBuild Standard Section 3.7, 3.8)
-
Work involving Ladders (Ladders to be industrial rated. QBuild Standard Section 3.4)
-
EXCAVATIONS Excavations less than 1.5m in depth (Hoarding/Barricading required. QBuild Standard Section 4)
-
Excavations GREATER than 1.5m in depth (Shore, Bench or Batter unless certified in writing by Geotechnical Engineer. QBuild Standard Section 4)
-
HAZARDOUS SUBSTANCES/CHEMICALS Work involving use of Hazardous Chemicals, eg Paint, Poisons, Solvents, Adhesives etc. (Approved method of application/storage as per MSDS. QBuild Standard Section 6)
-
Removal, Inspection and/or working with Asbestos Products (Roof/Wall Sheeting, Lagging, Flooring) (Removal. QBuild Standard Section 9.12)
-
Removal/Treatment of Lead Based Paint (Removal. QBuild Standard Section 9.6)
-
PLANT/MACHINERY/EQUIPMENT Working with concrete pumps (Hoarding/Barricading required, work to be carried out by licensed operator. QBuild Standard Section 8.7 - 8.8)
-
Working with Earthmoving Machinery etc (Provide exclusion zones. QBuild Standard Section 8.2)
-
Working with Cranes/Material Hoists etc (Provide exclusion zones. QBuild Standard Section 8.14, 3.16 - 3.18)
-
Confined spaces (Work methods as per QBuild and Government Standards - Refer Section 9.1)
-
Work involving sewerage, pits, infectious material etc. E.g. Syringes, Blood, Faeces etc. (Work methods as per QBuild and Government Standards. Refer Sections 9.20 - 9.21)
Environmental Management
-
Does the project / specification require an Environmental Management Plan?
-
Comments / Details
-
Does the project / specification require specialist consultants to be engaged? E.g. Environmental Management Officer.
-
Comments / Details
-
Has an exemption been given for either?
-
Comments / Details for exemption
Identified controls - Select an appropriate response for each item below, if a likelihood of a risk is identified, subsequent questions will appear. The risk matrix is located at the base of this form.
-
Acid sulphate soils
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Asbestos - Transport and Disposal of Asbestos
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Dust Management - Management of dust on site
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Fire Ant Management
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
General Site Management
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Managing requests to remove or trim vegetation
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Noise & Vibration Management - Excessive noise/vibration issues
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Painting Management - Management of Lead Based Paint.
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Storm Water Erosion & Sediment Control Measurement
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Water Quality - Deposit or release the materials into the roadside system
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Waste Management - Monitoring of waste types & operational costs.
-
Consequence
-
Overall Risk
-
Is there an identified control?
-
Other - List other environmental risks that are not above. Include the likelihood, consequence, overall risk and if there is identified controls.
-
Is it a heritage listed building? (Must be confirmed prior to work commencement)
Estimator - To the best of my knowledge, I have identified potential hazards/risks for the work.
-
Signature
-
Date
Supervisor - I agree that potential hazards/risks relevant to this site have been identified by the Estimator.
-
Signature
-
Date
Site Foreperson or Site Supervisor - I accept and agree that the Estimator and Supervisor have identified the initial potential hazards/risks applicable to this site.
-
Signature
-
Date
-
Add photos etc here if required
-
Risk Analysis
-