  • 1.)Open quote file and continue with new job file this should contain sub-folders or category for E.G1.) RFI / Transmittals / Issue For Approval / Mark ups / Approval For Construction / IFC etc......

  • 2.) 001 RFI *Cads file [ver] 2005 files, in PDF Eng. & arch when Robert Razen. *Panel sequence area to draw 1st. *Lift shaft details If applicable.*

  • 3.) Panel Register located on the data server for all departments to access info if required.

  • 4.) Panel register Excel Sheet 1, Panel S/D production

  • 5.) Panel register Sheet 2, On sight info required for installations.

  • 6.) Accounts, Sheet 3, Variation / contracts

  • 7.) 1st Set of IFA-(A) S/D Print, send with Transmittal- add to panel register.

  • 8.) Mark ups returned from Engineer-A & Architect-A - forward Mark ups to the S/D add to Panel Reg

  • 9.) Mark up's - returned Approval- (B) IFC print Emil with Elevations & Plans confirm mark ups applied. Add All to panel register.

  • 10.) Checked that mark up changes were applied volume / add on any change from quote specifications *Re-check that all was applied. *send to builder with transmittal ***Acounts will need to be notified IFC has been sent.

  • 11.) When S/D are returned *Send back to S/D to apply change send back to us. *Re-check that all was applied.

  • 12.) if any S/D are incorrect return to S/D for amendment.

  • 13.) When returned to APC recheck add copy to folders,up date Panel Register.Include all sheets, 1, 2 & 3. ( I.E accounts can inv when see IFC.)<br>

  • 14.) print a copy of lay out - add to wall.

  • 15.) Panel stock requirement - check list.

  • 16.) Panel poured due date: Forman's list to set factory manufacturing prduction. list ( panel # & rev, Date , requirements thickness, PFC?.

  • 17.) Panel delivery (#1 & date) add the delivery Dates to Panel register.(I.E: Delivery- 3, Date: 2/9/12. )

  • 18.) Setting production for Manufacture of panel. Once the 1st points have been done. Check off the above as a Q/A check point. This will promote productivity, by eliminating production delays

  • 19.) Steel cages list.- add folder mamilla place in pigeon hole, cages ready to manufacture.**print off clock card date or write in on drawing made date on each

  • 20.) Truck list. P.O, Times, panel sequence, compliance certificates add all to Panel Register. "If all the above is entered into Panel register it is like a panels {blue print!}".

  • 21. ) Q / A Pre panel delivery check.

  • 22.) forms folder / mark off the wall.

  • 22.) forms folder / mark off the wall.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.