Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
1.Housekeeping
-
1.1 Walkways, corridors, stairs clear of debris?
-
1.2 Material stacked and stored properly?
-
1.3. Trash taken out?
-
1.4 Slips, trips, fall hazards?(comply, eye.)
-
1.5. Emergency egress maintained?
-
1.6 Water/Pipe/Leak mitigated
2. Ladders
-
2.1. Ladders properly used?
-
2.2. Ladders properly stored and secure?
-
2.3. Extension ladders at a 4:1 pitch?
-
2.4. Extension ladder extended 3' above landing?
-
Other?
3. Electrical.
-
3.1 GFCI in place
-
3.2. Quarterly cord inspection done if required?.
-
3.3. Cords elevated to 7' overhead?
-
3.4. Cords in good condition?
-
3.5. Is temporary lighting adequate?
-
3.6. Other?
4. Barricading
-
4.1. Barricade tape managed?
-
4.2. Signage posted on all 4 sides?
-
4.3. Signage up to date and complete?
-
4.4. Right type of barricade for work?
5. Aerial lifts (mewp's)
-
5.1. Is the operator trained?
-
5.2. Are daily inspections documented?
-
5.3. Is the green tank permit posted on lift?
-
5.4. Fall protection in use (Aerial lifts only)?
-
5.5 Is gate or chain secured?
-
5.6. Area below lift protected?
-
5.7. Other?
6. LOTO (CoHE) Lock out tag out
-
6.1. Competent person present?
-
6.2. Is the employees trained?
-
6.3. Are locked keys different?
-
6.4. Energized electrical work?
-
6.5. Is tag used and filled out completely?
-
6.6. Zero energy confirmed?
-
6.7. Other?
7. Scaffolding
-
7.1. Guard rails installed correctly?
-
7.2. Bracing and pins in place?
-
7.3. Is the scaffold fully planked?
-
7.4. Is the scalpel inspected daily And tagged?
-
7.5. Are planks in good condition?
8. Fall protection
-
81 6' Fall exposure?
-
8.2 Are workers trained and documented?
-
8.3. Is the equipment inspected?
-
8.4. Is the anchor point engineered?
-
8.5. Are Floor and wall openings protected?
-
8.6. Fall distance identified?
-
8.7 Other
9. Welding and cutting.
-
9.1. Proper PPE for welding task?
-
9.2. Is work area ventilated?
-
9.3. Are welding screens being used?
-
9.4. Is that work area free of combustibles?
-
9.5. Is the area below properly controlled?
-
9.6. Are the cylinders stored properly?
-
9.7. Welding leads and hoses in good condition?
-
9.8. Other?
10. Fire prevention.
-
10.1. Hot work permit posted?
-
10.2. Is the firewatch present?
-
10.3. Are the combustible materials removed?
-
10.4. Are the bottles upright, capped and secured?
-
10.5. Fire extinguishers present?
-
10.6. Are welding leads in good condition?
-
10.7. Other?
11. PPE
-
11.1. Hard hats used?
-
11.2. Face protection?
-
11.3. Eye protection?
-
11.4. Hand protection?
-
11.5. High vis vest or equivalent?
-
11.6. Hearing protection?
-
11.7. Proper footwear?
-
11.8. Other?
12. Excavation and trenching
-
12.1. Competent person present?
-
12.2. Protective systems <20' used?
-
12.3. Are the utilities marked?
-
12.4. Are the utilities protected and supported?
-
12.5. Trench box certification?
-
12.6. Excavation permits and daily inspections?
-
12.7. Is there access every 25 feet?
-
12.8. Is the trench sloped and shored properly?
-
12.9. 4' depth safe distance?
-
12.10. 6' fall protection?
-
12.11. Are spoils 2' from edge?
-
12.12. Are there any atmospheric hazards?
-
12.13. Public protection barricades?
-
12.14. Other?
13 Environmental Aspects
-
13.1 Machinery/equipment
14. Inspection items
-
Apollo on site Foreman
-
Apollo Safety