Information
-
Audit Title
-
Client / Site
-
Date and time of arrival
-
Conducted on
-
Prepared by
-
Location
-
Document No.
-
Personnel
-
THE FOLLOWING SECTION MUST BE COMPLETED AND CONSIDERED SATISFACTORY BEFORE CONTINUING FURTHER WITH THIS AUDIT
Preliminary requirements
-
Is there a valid (i.e. in date) ASB5 notification form on site for the works to be audited?
-
Is there (or will there be) asbestos removal work or cleaning in progress within the enclosure during the audit?
-
Is there provision to observe work practices within the enclosure by means of CCTV and/or viewing panel(s)?
-
Is there a site specific Plan of Work available on site for the works?
-
Is there a copy of the company standard procedures/ generic procedures available on site?
-
Is the decontamination unit fully functional in terms of power, ventilation, and the provision of hot and cold running water for showering?
-
DO NOT PROCEED WITH THE AUDIT UNLESS EACH RESPONSE ABOVE IS AFFIRMATIVE. SHOULD ANYTHING ABOVE BE AMISS THAT CAN BE RECTIFIED IMMEDIATELY, THEN CONTINUE WITH THE AUDIT ONCE RECTIFIED.
-
SHOULD ANYTHING ABOVE BE AMISS THAT CANNOT BE RECTIFIED IMMEDIATELY, THEN INFORM THE SUPERVISOR, THAT THE AUDIT CANNOT CONTINUE
ASB5 Notification Form
-
Are details of any other licence holders recorded in section 3 of the ASB5?
-
What form of asbestos containing material is being worked upon? (Section 4 of ASB5?)
-
What is the approximate extent of the works stated in section 5 of the ASB5?
-
Are the working hours specified on the ASB5 and do they match the POW?
-
What is the maximum number of employees per shift stated in section 5 of the ASB5?
-
How many operatives (including the supervisor) are on site?
Site documentation
-
A copy of HSE Asbestos licence on site
-
Evidence of current employers liability insurance on site
-
Evidence of current public liability insurance on site
-
Is the contract supervisor the same person as specified in the plan of work?
-
Does the named supervisor match that of the ASB5?
-
Does the plan of work detail when the work is to be carried out? (Including start/finish times and weekend variations)
-
Does the plan of work detail the analytical company providing the 4 stage clearance?
-
Does the plan of work detail who the analytical company is contracted to?
-
Does the plan of work detail the type of asbestos involved? (i.e. Amosite, Chrysotile, Crocidilite)
-
Does the plan of work detail the condition of the asbestos containing material to be removed? (e.g. good, fair or poor)
-
Does the plan of work made reference to reading the standard procedures in conjuntion with the POW
-
Does the version number of the standard procedures match the reference in the POW
-
Does the plan of work (or standard procedures) detail who is authorised to amend the plan of work?
-
Does the plan of work (or standard procedures) detail the construction method for enclosures and air locks?
-
Does the plan of work (or standard procedures) detail the arrangements for smoke testing and witnessing? If Yes, please record name/title of proposed witness
-
Does the plan of work (or standard procedures) detail decontamination entry and exit procedures?
-
Does the plan of work (or standard procedures) detail the type of respirators used?
-
Does the plan of work detail the asbestos removal technique to be used?
-
Does the plan of work detail the air monitoring arrangements for the duration of the works?
-
Are welfare facilities detailed in the plan of work and are they available for use as described?
-
Is the scope of works adequately described on the plan of work, and does it match the details recorded on the ASB5?
-
Is there a site specific risk assessment available for inspection, for hazards other than asbestos? e.g. hot work, work at heights, use of hand tools, confined spaces, electricity, manual handling etc
-
Is there a copy of the contractor's current valid licence available for inspection?
-
Is there documented evidence on site confirming current insurance cover for both employers liability and public liability? e.g. Insurance schedule
-
Are daily site and plant inspection records (including DCU, enclosure, airlocks, NPU's & vacuum cleaners) available for inspection and up to date?
-
Does the NPU inspection record include manometer/ pressure gauge readings for each NPU in use (including DCU)?
-
Has the smoke test record for the enclosure been completed and do the witness details match those stated in the plan of work?
Site Supervisor and/or Operative(s)
-
Current medical certificate
-
Current training certificate?
-
Training provider
-
Face fit test certificate for RPE in use?
-
Examination record for RPE in use? (daily if in enclosure, currently monthly if not)
-
Adequate response when questioned regarding emergency procedures? (if not in enclosure)
-
Supervisor/operative(s) clean shaven?
-
If out of enclosure, or if seen before entry
-
Additional comments
-
Are all copies of certificates (above) individually authenticated by, or under the direction of, senior management, with a statement confirming their validity?
Enclosure Sketch
-
Does the sketch plan included with the plan of work match the site set up, and include the positions of the NPU, airlock, bag lock (if applicable), viewing panels/ CCTV and DCU as a minimum?
-
Does the enclosure sketch identify the outline of the enclosure
-
Does the enclosure sketch identify areas adjacent to the enclosure
-
Does the enclosure sketch identify Airlock position
-
Does the enclosure sketch identify Baglock position
-
Does the enclosure sketch identify NPU location
-
Does the enclosure sketch identify CCTV and viewing panels
-
Does the enclosure sketch identify DCU location
-
Does the enclosure sketch identify Transit Route
-
Does the enclosure sketch identify Waste Route
-
Does the enclosure sketch identify location of waste skip / van
Plant on site/ Certification
-
Are there at least 2 H-type vacuum cleaners on site?
-
Are current DOP test certificates (or copies) available and relevant to each vacuum on site?
-
Does the number and capacity of the NPUs in use correspond with that stated in the plan of work?
-
Is there a copy of the thorough test and inspection on site for the NPU (s) in the enclosure
-
The legally required airflow is demonstarted as being achieved, based on actual airflow measurements and / or a reasonable assumption of NPU performance
-
Each NPU is either located outside the working enclosure and connected directly to the enclosure wall, or is fully sheeted out if inside the enclosure
-
Where the NPU is located outside the enclosure, and connected to the enclosure via trunking, there is a suitably robust and acceptable written procedure in place to connect and disconnect the NPU and trunking with minimal potential spread of contamination
-
There is a functional non-return flap on each NPU exhaust
-
Extracted air from each NPU is vented outside
-
Is there an electrical safety certification for DCU?
-
Is there a current gas safe certification for the DCU? (LPG)
-
Is there a current DOP test certificate (or copy) available on site for the NPU within the dirty end of the DCU?
Enclosure/ Airlock
-
Works activities can be viewed via:
-
Does the viewing provision allow sufficient monitoring of all areas of the enclosure during the work activities?
-
The selection and provision of warning signs are appropriate to the works
-
Is the enclosure in sound condition and constructed so as to prevent the spread of asbestos?
-
Is each stage of the airlock at least 1m x 1m x 2m (height)?
-
Is the airlock free from visible asbestos debris?
-
Are all of the airlocks flaps weighed?
-
Do the flaps cover the airlock adequately?
-
Is a bucket and sponge (or similar) available for decontamination or respirator?
-
Does the inner stage of the airlock have a viewing panel at least 600 x 300mm?
-
Where the DCU is directly connected to the enclosure, the connection consists of at least one cube and an intervening space?
Baglock
-
Has a seperate baglock been provided?
-
Is the baglock big enough for the waste size being generated?
-
Is the baglock free from visible material appearing to be asbestos debris?
-
Are all the baglock openings / flaps suitable and weighted?
-
Does the inner stage of the baglock have a viewing panel at least 600 x 300mm?
Air extraction equipment
-
Is the extract sited in the relation to ideal air management?
-
Is the extract capable of giving a minimum of 8 air changes per hour?
-
Is the extract vented to the outside atmosphere where practical?
-
Does each NPU have a non-return flap on the exhaust side of the HEPA filter?
-
NPU - Anemometer readings
-
Daily Pressure gauge readings recorded for NPU attached to enclosure
-
Daily pressure gauge reading recorded for NPU in DCU
Observed work practices
-
Are the removal procedures observed, including the dust suppression method in use, suitable for the ACM being used
-
Does the asbestos removal technique being used match that stated in the plan of work?
-
Has the waste been appropriately bagged? (e.g. immediately, and single bagged if still in the enclosure)
-
Does the RPE (including filter) being use match that stated in the plan of work?
-
Are colours of coveralls as stated in the plan of work or standard procedure
-
Are all operatives clean shaven?
-
Are all items of necessary PPE being worn properly? (e.g. overall hood over head straps, overalls not tucked in to working footwear etc.)
-
Are all components of the full face RPE uniquely identifiable? (e.g. mask, blower and battery identified/marked/tagged with name or item/serial number
-
Is the pre filter (or roving head) the only part of the NPU that is exposed to the working area? (i.e NPU sheeted out if inside the enclosure)
Air Management
-
The enclosure design allows for ideal air movement
-
There is sufficient airlock flap detection to indicate adequate airflow through the airlock
-
Additional air inlets are suitably positioned and in use
Hygiene Facility
-
Is the unit positioned in relation to the work area as stated in the plan of works
-
If the unit is not directly connected to the enclosure, would it of been reasonably practicable to do so
-
Is the transit route as short as possible and away from occupied areas
-
In addition to item 1.6 above, is the unit fully functional/ in working order? (Heating, lighting, water filter, drains etc)
-
Are the internal doors and external door to the dirty end self-closing?
-
Are there an adequate number of shower heads for operatives? i.e. at least 1 for every 4 operatives)
-
Is there a nail brush provided in the shower area?
-
Is the unit in good condition and clean so far as reasonably practicable?
-
Is there a clearance test certificate, from the previous job, for the dirty and shower compartments of the hygiene unit?
-
Are the clean and dirty end doors marked (including prohibited entry and mandatory PPE signage, where required)?
-
Are towels provided?
-
Is waste water filtered and discharged either directly or via containers to drain
Waste
-
Are the waste disposal arrangements as described in the plan of work? ( including named skip company or named transfer station)
-
Is there an established transit route displaying appropriate signage and of minimum distance?
-
Is the waste transit route free from residual or split waste?
-
Is the waste route free from stored or unattended waste?
-
Where applicable, is there sufficient means to separate waste from equipment/ supplies within the company vehicle?
-
Is the containment of waste suitable, secure and sound
Miscellaneous
-
Are disposable working coveralls and transits coveralls category 3, type 5/6
-
Are contractors vans reasonably tidy and with minimal risk of the spread of asbestos?
-
Have any required changes to the POW / site diagram been made
-
A smoke test record has been completed
-
Background / leak tests and / or personal monitoring have been planned for this job according to the plan of work
-
Personal monitoring records provide a clear description of activities being undertaken during monitoring
-
There is evidence of management involvement on site since the commencement of works
First Aid and Emergency
-
Are suitable emergency arrangements in place
-
Are employee sufficiently aware of emergency arrangements
-
Is there a suitably stocked First Aid Kit available for use on the site
-
Is there a trained and designated first Aider on site
Non- Asbestos Risks
-
Work At height
-
Live Services
-
Manual Handling
-
Noise
-
Hand Arm Vibration
-
Site Vehicle Movement
-
Other contractor's activities
-
Thermal Issues
-
Hazardous substances existing on site
-
Hazardous substances brought to site
-
Other significant risks on site
Scaffolding
-
Are the asbestos removal contractors using scaffolding on site?
-
Was a sub-contractor used to erect the scaffolding
-
Was the scaffolding liable to disturb asbestos while being erected?
Welfare
-
Welfare Provision consists of
-
There is adequate and suitable welfare provision on site, which is available for use
-
Site arrangements and behavious are in accordance with current COVID-19 guidance
-
undefined
-
COMPLETE A SITE AUDIT SUMMARY OF OBSERVATIONS AND/OR RECOMMENDED ACTIONS. IF NO FURTHER ACTIONS ARE REQUIRED, COMPLETE A SUMMARY SHEET WITH A STATEMENT TO THAT EFFECT
-
Add signature