Title Page
-
Conducted on
-
Prepared by
-
Location
Heat Pump Wiring
-
Is the correct size breaker used for heat pump?
-
Is an isolation switch installed for the heat pump and mounted on a fixed structure out beside the heat pump?
-
Is the correct size power supply cable used for heat pump?
-
Is the correct communication cable installed and wired unto correct terminals?
Cylinder Wiring
-
Is the correct sized breaker used for controller on cylinder?
-
Is an isolation switch installed for controller and mounted on a fixed structure beside controller?
-
Is the correct size power supply cable used for controller on cylinder?
-
Is the correct communication cable installed and wired into correct terminals?
-
Is the flow switch switch wired back into correct terminal on control panel?
Heating Controls / Stats Wiring
-
Are all heating controls powered from controller on cylinder?
-
Are all heating controls wired & working?
Heat Pump Mounting
-
Is the unit installed the correct distance from nearest boundaries?
-
Is the unit secured correctly to antivibration mounts via rubber mounts?
-
Is the unit mounted plumb level?
-
drain caps fitted
-
Is a condensate drain kit fitted and terminating correctly
-
If the unit is mounted on wall brackets; is a drip tray installed?
Heat Pump Plumbing (Outdoor)
-
Is the correct size pipework used?
-
Are flexible antivibration hoses fitted and washers used?
-
Are heat pump isolation valves fitted out at the heat pump?
-
Is the flow and return pipework connected correctly?
-
Is the primary flow pipework insulated?
-
Are all safety valves and tundish drained through a metal pipe to an appropriate drain point?
Cylinder Plumbing (Indoor)
-
Is flow and return pipework connected the right way around?
-
is time/date set correctly
-
Is the heating expansion vessel correctly sized, secured and charged to to the correct pressure?
-
Are all pump valves and isolation valves fully open?
-
has an anti vac valve been fitted
-
Has system been completely flushed of air and charged to the correct operating pressure
Radiator / UFH Plumbing
-
Has all air been removed from emitters?
-
Have all emitters been balanced correctly?
Additional ASHP Checklist
-
Anti-freeze valves fitted or glycol installed in the system?
-
All pipework in cylinder cupboard insulated?
-
Isolation valve fitted on cold inlet?
-
Inlet control group valve fitted in incoming cold within 3m of cylinder?
-
D1 size (max 600mm away from temperature relief valve)?
-
D2 pipework minimum 300mm before the 1st bend and correct size
-
Potable expansion vessel fitted on cold feed between inlet valve and cylinder?
-
Expansion vessel on heating
-
Hot water outlet starts in 22mm pipe - can be reduced?
-
installer details filled in on cylinder
Installation Photographs / Commissioning Documentation
-
Add media
Sign Off
-
Add signature
-
Select date