Title Page
-
Prepared by
-
Location
-
Unit Number
-
What is the purpose for the walk today?
-
Conducted on
-
What it the Purpose of the this Unit walk?
Unit Walk Sheet
-
Upon completion of this inspection it is to be exported to all involved parties and printed out to be placed in the unit for the duration of the renovations.
-
As of the Below referenced date, keys have been given to The Contractor and a pre-inspection walk has been completed with the authorized Owner's representative referenced below. The signatures on this document constitute an acceptance of the above referenced unit by The Contractor and an authorization for The Contractor to perform the optional items listed below.
-
Date of inspection
-
Unit Number
-
Unit Type
-
Photos of Unit Before work starts
Supplemental Repairs (detail below)
-
Are there any scope Items that are not being done in this unit?
-
Select Items that are not to be done in this unit from the original Bid?
- Install Countertops
- Vanity light
- Bath trim kit Replacment
-
Are there any Items outside the original contracted scope For this unit?
-
Describe additional Work Needed in the following Format:- [Item-Quantity]
Attach photos of change order items to each associated line item
Use Menu Pricing Below:
-
Change order items
-
Change order Photos
Pre-Existing Conditions (excluded from renovation)
-
Are there any Pre-Existing Conditions present that will not be addressed during renovations?
-
Describe pre-existing conditions that will not be addressed during renovations.
Attach photos of change order items to each associated line item. -
Photos of items that will not be addressed during the renovation
Signatures of representatives present for the inspection
-
Signatures required for approval of Change Order Items and Pre-Existing Conditions
-
Owner's Representative
-
A-Pro Top Representitive
Final Walk Punch List
-
Date Punch Walk
-
Unit Number
-
Unit Type
Items to be Corrected
-
ONLY the Below in-scope (and CO) items are agreed to be re-inspected upon completion signoff. Any additional work requested to be performed will be subject to approval by Construction Manager. Note that additional items discovered after the pre-walk add to the duration of the renovations.
-
Are there any punch items for this unit?
-
Punch Items to be addressed.
NOTE: Attach Photos of each item discovered to the associated line item. Audit is to be exported to all parties involved in the renovations on site at the time of inspection. -
List of punch items:
-
Photos of items to be addressed:
-
Are any of these punch items Change Orders
-
List change order items In the following format: Refer to Menu Pricing Guide Item - Measurements - Price for change order items needed
-
Add media
Certificate Of Completion
-
Completion Date
-
Unit Number
-
Unit Type
-
Have all the scope items from the origional contract been completed?
-
What Scope items are remaining from the original scope of work?
-
Photos of incomplete scope items
-
Were there additional items outside the original contracted scope preformed on this unit?
-
Describe additional items preformed.
-
Photos of additional work preformed.
-
Completion Photos For Unit
Signatures of representatives present for the inspection
-
Completion approved by
-
Title:
-
Contact Info:
-
Owner's Representative
-
A-Pro Top Representitive