Project
-
Prepared by
-
Date
Instructions to Representative
-
This checklist is to be used by the AVE representative to ensure the electrical boxes, conduits, and framing complete and accurate per design specifications prior to being covered by drywall or other material. This checklist may be used if a subcontractor is performing the installation, or a crew from AVE. Be sure to address all items on this list.
If this inspection is performed by a visiting Owner’s Representative, the inspector is to create a punch list of any incomplete or incorrect items and leave a copy on site. Copies of the punch list should also be distributed as indicated above. When all items on punch list are completed, the Site Representative is to sign the punch list indicating that the work has been done, and then fax copies as indicated. The symbol next to a check box c indicates that a digital photo is required. Take shots from different angles (if necessary) to show the relationship of the device as it is installed. Similar devices require only one photo representative of the others. Follow all guidelines regarding the taking of photos.
Prior to the Trip
undefined
-
If the inspection visit requires travel and lodging, submit Travel Approval Request at least 4 weeks prior to ensure approval is given in time to take advantage of lower airfares and room rates.
-
Date Booked
-
Get it Booked.
-
Gather a set of AV drawings and all other documents related to this project.
-
Coordinate with the SPD Project Manger assigned to this project to determine the best time to visit and to acquire his approval.
-
If any kind of visa is required, be sure to acquire one prior to booking the trip.
-
What type is needed
-
Book travel following all travel guidelines and policies.
-
Most projects will require a hard hat, orange vest, safety glasses, and steel-toed shoes while on site. Some of these items may be provided by the contractor, check first.
-
What is required, and what will be provided on-site?
On Site
-
Review construction plan set being used by contractors, verify they are up to date and correct. If they are not, coordinate with project manager and architects to provide updated copies.
-
Verify local power standard:
-
Note Voltage:
-
Note Frequency:
-
Verify the conduit and boxes for the AV system power follow specifications.
-
If Emergency Power is specified for the project, verify that the AV equipment, Instruction Room lighting, and drapery will be on emergency power.
-
Patch Rack mounted in the correct location and at the correct heights according to the construction documents as specified
-
Take a Photo
-
Take a Photo
-
What needs to be done to mitigate the issue?
-
All HVI boxes have been flush mounted as specified in the construction documentation.
-
Take a Photo
-
Take Photos
-
What is need to make it right?
-
All AV cable is by approved manufacturers.
-
Take photos
-
Take Photos
-
What is needed to make it right?
-
All conduits are properly routed and installed as shown on the AV Riser Diagram - Sheet XE610.
-
Verify that the electrical circuits for all equipment racks will be on the same phase.
-
Verify the AV room minimum inside dimensions (11' x 7' for a 2-room temple).
undefined
-
Dimensions
-
Photo
-
Add media
-
Dimensions
-
Photo
Number of endowment rooms in the temple
-
How many rooms in the temple?
- 1
- 2
- 3
- 4
- 5
- 6
-
The room 1 projection enclosure must be ventilated (see specifications) to allow for proper projector operation and the finished inside dimensions meet specification
-
Dimensions
-
Dimensions
-
What needs to be done to mitigate the issue?
-
Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Verify that no insulation has been installed inside all projector enclosures
-
Projector enclosures have a second 4x4 box installed at rear of enclosure with conduit and wires running to the appropriate LVI panel in the AV room.
-
A 4x4 electrical box with double gang plaster ring is mounted at each Room Panel (TS) location and is positioned 60" on center, above finished floor. TS boxes should also be positioned far enough away from rough door openings to allow room for proper mounting of Room Panel after door casing and decorative moldings are in place. Boxes should be plumb and square. Boxes should be mounted such that the face of the plaster ring will be within ½" of the finished surface.
-
loudspeakers are located and wired as per design documents.
-
On the drawings, verify the screen dimensions are as specified with the base of screen area no lower than 48" above finished floor.
-
Photos
-
What needs to be done to mitigate the issue?
-
Check drawings verify projection screen size meets specification
-
Add media
-
What needs to be done to mitigate the issue?
-
Are Aux monitor jacks in location in the correct location with a power receptacle adjacent?
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify that the AC power to each Projector will be wired to its associated HVI panel in the AV room
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify plans show that room lighting in all ordinance rooms are on a Lutron or equivalent manufactured dimmer system with adjustable fade rates. No fluorescent lights are allowed on dimmers
-
Verify that all window drapery control is wired per riser diagram.
-
Verify that the conduits for the lighting and drapery controls are properly routed.
-
Note provider for the drapery control + Contact info
-
The room 1 projection enclosure must be ventilated (see specifications) to allow for proper projector operation and the finished inside dimensions meet specification
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 2 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
Room 1 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 2 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Verify that no insulation has been installed inside all projector enclosures
-
Projector enclosures have a second 4x4 box installed at rear of enclosure with conduit and wires running to the appropriate LVI panel in the AV room.
-
A 4x4 electrical box with double gang plaster ring is mounted at each Room Panel (TS) location and is positioned 60" on center, above finished floor. TS boxes should also be positioned far enough away from rough door openings to allow room for proper mounting of Room Panel after door casing and decorative moldings are in place. Boxes should be plumb and square. Boxes should be mounted such that the face of the plaster ring will be within ½" of the finished surface.
-
loudspeakers are located and wired as per design documents.
-
On the drawings, verify the screen dimensions are as specified with the base of screen area no lower than 48" above finished floor.
-
Photos
-
What needs to be done to mitigate the issue?
-
Check drawings verify projection screen size meets specification
-
Add media
-
What needs to be done to mitigate the issue?
-
Are Aux monitor jacks in location in the correct location with a power receptacle adjacent?
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify that the AC power to each Projector will be wired to its associated HVI panel in the AV room
- Yes
- No
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify plans show that room lighting in all ordinance rooms are on a Lutron or equivalent manufactured dimmer system with adjustable fade rates. No fluorescent lights are allowed on dimmers
-
Verify that all window drapery control is wired per riser diagram.
-
Verify that the conduits for the lighting and drapery controls are properly routed.
-
Note provider for the drapery control + Contact info
-
The room 1 projection enclosure must be ventilated (see specifications) to allow for proper projector operation and the finished inside dimensions meet specification
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 2 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 3 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
Room 1 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 2 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 3 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Verify that no insulation has been installed inside all projector enclosures
-
Projector enclosures have a second 4x4 box installed at rear of enclosure with conduit and wires running to the appropriate LVI panel in the AV room.
-
A 4x4 electrical box with double gang plaster ring is mounted at each Room Panel (TS) location and is positioned 60" on center, above finished floor. TS boxes should also be positioned far enough away from rough door openings to allow room for proper mounting of Room Panel after door casing and decorative moldings are in place. Boxes should be plumb and square. Boxes should be mounted such that the face of the plaster ring will be within ½" of the finished surface.
-
loudspeakers are located and wired as per design documents.
-
On the drawings, verify the screen dimensions are as specified with the base of screen area no lower than 48" above finished floor.
-
Photos
-
What needs to be done to mitigate the issue?
-
Check drawings verify projection screen size meets specification
-
Add media
-
What needs to be done to mitigate the issue?
-
Are Aux monitor jacks in location in the correct location with a power receptacle adjacent?
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify that the AC power to each Projector will be wired to its associated HVI panel in the AV room
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify plans show that room lighting in all ordinance rooms are on a Lutron or equivalent manufactured dimmer system with adjustable fade rates. No fluorescent lights are allowed on dimmers
-
Verify that all window drapery control is wired per riser diagram.
-
Verify that the conduits for the lighting and drapery controls are properly routed.
-
Note provider for the drapery control + Contact info
-
The room 1 projection enclosure must be ventilated (see specifications) to allow for proper projector operation and the finished inside dimensions meet specification
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 2 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 3 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 4 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
Room 1 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 2 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 3 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 4 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Verify that no insulation has been installed inside all projector enclosures
-
Projector enclosures have a second 4x4 box installed at rear of enclosure with conduit and wires running to the appropriate LVI panel in the AV room.
-
A 4x4 electrical box with double gang plaster ring is mounted at each Room Panel (TS) location and is positioned 60" on center, above finished floor. TS boxes should also be positioned far enough away from rough door openings to allow room for proper mounting of Room Panel after door casing and decorative moldings are in place. Boxes should be plumb and square. Boxes should be mounted such that the face of the plaster ring will be within ½" of the finished surface.
-
loudspeakers are located and wired as per design documents.
-
On the drawings, verify the screen dimensions are as specified with the base of screen area no lower than 48" above finished floor.
-
Photos
-
What needs to be done to mitigate the issue?
-
Check drawings verify projection screen size meets specification
-
Add media
-
What needs to be done to mitigate the issue?
-
Are Aux monitor jacks in location in the correct location with a power receptacle adjacent?
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify that the AC power to each Projector will be wired to its associated HVI panel in the AV room
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify plans show that room lighting in all ordinance rooms are on a Lutron or equivalent manufactured dimmer system with adjustable fade rates. No fluorescent lights are allowed on dimmers
-
Verify that all window drapery control is wired per riser diagram.
-
Verify that the conduits for the lighting and drapery controls are properly routed.
-
Note provider for the drapery control + Contact info
-
The room 1 projection enclosure must be ventilated (see specifications) to allow for proper projector operation and the finished inside dimensions meet specification
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 2 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 3 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 4 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 5 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
Room 1 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 2 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 3 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 4 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 5 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Verify that no insulation has been installed inside all projector enclosures
-
Projector enclosures have a second 4x4 box installed at rear of enclosure with conduit and wires running to the appropriate LVI panel in the AV room.
-
A 4x4 electrical box with double gang plaster ring is mounted at each Room Panel (TS) location and is positioned 60" on center, above finished floor. TS boxes should also be positioned far enough away from rough door openings to allow room for proper mounting of Room Panel after door casing and decorative moldings are in place. Boxes should be plumb and square. Boxes should be mounted such that the face of the plaster ring will be within ½" of the finished surface.
-
loudspeakers are located and wired as per design documents.
-
On the drawings, verify the screen dimensions are as specified with the base of screen area no lower than 48" above finished floor.
-
Photos
-
What needs to be done to mitigate the issue?
-
Check drawings verify projection screen size meets specification
-
Add media
-
What needs to be done to mitigate the issue?
-
Are Aux monitor jacks in location in the correct location with a power receptacle adjacent?
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify that the AC power to each Projector will be wired to its associated HVI panel in the AV room
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify plans show that room lighting in all ordinance rooms are on a Lutron or equivalent manufactured dimmer system with adjustable fade rates. No fluorescent lights are allowed on dimmers
-
Verify that all window drapery control is wired per riser diagram.
-
Verify that the conduits for the lighting and drapery controls are properly routed.
-
Note provider for the drapery control + Contact info
-
The room 1 projection enclosure must be ventilated (see specifications) to allow for proper projector operation and the finished inside dimensions meet specification
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 2 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 3 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 4 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 5 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
The room 6 projector enclosure must be ventilated (both supply and exhaust) to allow for proper projector operation and the finished inside dimensions meet specifications
-
Dimensions
-
What needs to be done to mitigate the issue?
-
Room 1 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 2 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 3 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 4 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 5 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Room 6 Projector enclosures are fitted with a 4x4 electrical box at rear of enclosure for power with a conduit routed to the appropriate HVI panel in the AV Room as specified in construction documents. The Room ‘A’ box requires 4 outlets per the local of style power receptacles, and the Room ‘B’ box requires two outlets per the local style power receptacle.
-
Photos
-
What needs to be done to mitigate the issue?
-
Verify that no insulation has been installed inside all projector enclosures
-
Projector enclosures have a second 4x4 box installed at rear of enclosure with conduit and wires running to the appropriate LVI panel in the AV room.
-
A 4x4 electrical box with double gang plaster ring is mounted at each Room Panel (TS) location and is positioned 60" on center, above finished floor. TS boxes should also be positioned far enough away from rough door openings to allow room for proper mounting of Room Panel after door casing and decorative moldings are in place. Boxes should be plumb and square. Boxes should be mounted such that the face of the plaster ring will be within ½" of the finished surface.
-
loudspeakers are located and wired as per design documents.
-
On the drawings, verify the screen dimensions are as specified with the base of screen area no lower than 48" above finished floor.
-
Photos
-
What needs to be done to mitigate the issue?
-
Check drawings verify projection screen size meets specification
-
Add media
-
What needs to be done to mitigate the issue?
-
Are Aux monitor jacks in location in the correct location with a power receptacle adjacent?
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify that the AC power to each Projector will be wired to its associated HVI panel in the AV room
-
Photos
-
What needs to be done to mitigate the issue?
-
Photos
-
Verify plans show that room lighting in all ordinance rooms are on a Lutron or equivalent manufactured dimmer system with adjustable fade rates. No fluorescent lights are allowed on dimmers
-
Verify that all window drapery control is wired per riser diagram.
-
Verify that the conduits for the lighting and drapery controls are properly routed.
-
Note provider for the drapery control + Contact info
-
Verify that details of IR transmitter enclosures are correct, and the conduit is routed according to the AV Riser Diagram.
-
Photos
-
What do we DO?
-
Photos
-
Altar junction box is installed at floor level. Junction box to be 4" x 4" with 3.5" depth with a double gang plaster ring installed on top.
-
Photos
-
What do we need to do to FIX it?
-
Add media
-
Clock boxes are mounted at 66" above finished floor. Boxes should be plumb and square with double gang plaster ring on each box, flush with wall.
-
Photos
-
What do we need to do?
-
Photos
-
Hidden junction boxes or splices are not allowed. All junctions must be at clock mounting locations only
-
Conduit is routed according to the AV Riser Diagram on Sheet XE610.
-
Confirm that a qualified sub-contractor will terminate clock ends with proper RJ-45 connectors, will punch down cables at patch bay, and certify all lines to 1Gb.
-
Review cable routing and punch down schedule with contractor. Discuss CAT6 cables to be run from RBI panel to network patch bays
-
Verify electrical boxes, access holes, and cabling is properly positioned and routed.
-
Confirm electrical interconnect as shown on sheet XE510.
-
Conduit is routed according to the AV Riser Diagram on Sheet XE610.
-
All Dedication TV outlet boxes are installed in the correct locations, at the standard outlet height, and conduit and wiring installed according to the AV Riser Diagram on Sheet XE610. Note any changes to the riser for As-built documentation
-
A power outlet box should be installed within 12" of each TV outlet
-
Verify that the Electrical Contractor has ordered the TV outlet cover plates as specified in the Audiovisual Equipment Schedule on sheet XE610.
-
A suitable box should be installed in floor at table location near font for installation of a 120VAC duplex GFCI rated power outlet. Outlet should not be slaved from another GFCI outlet located elsewhere.
-
Photos
-
What do we need to do?
-
Photos
-
Verify that the conduit and boxes are installed at the correct locations according to the AV riser diagram on Sheet XE610. Verify that the electrician will use CAT6 wire.
-
Verify that the electrical contractor has ordered the RJ45 wall plates as specified in the Audiovisual Equipment Schedule on sheet XE610
-
Verify that electrical contractor understands that all AV cable is to be Belden according to specifications. Substitutions are not allowed.
Notes
-
Any notes for this project that should be noted...
-
NOTES
-
All you can do is do your best.....