Step -1-
-
Carefully read all notes on the Doka Drawings.
-
Once the concrete has reached 3,000 psf. you may prepare to jump the platform.
-
All fall protection has been inspected.
-
Inspect the platform for damaged wood or unsafe conditions.
-
Remove any loose item or secure them firmly.
Step -2-
-
Remove ties.
-
Remove all nails from openings.
-
Cut all bolts on embeds.
-
Prep upper safety hand rails.
-
Strike the formwork (strip the formwork)
-
Make sure all stripping corners are fully engaged.
-
Make sure formwork is secured.
-
Make sure the correct signage is in place ( red tape, fall protection sign, scaffold tags, ext).
Step -3-
-
Inspect all lifting points and rigging before you use it.
-
Attach the lifting chains or rigging
-
No ones is permitted to "ride" on the platform.
Step -4-
-
Reposition the unit (platform and formwork).
-
Once the platform is repositioned, before the rigging is cut loose, make sure the pawls are positioned correctly into position.
-
Release rigging.
-
Correct safety hand rail and safety net.
-
Baker Concrete, Competent Person signature.