Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Select date
Working Supervisors File
-
Are contents up to date and complete?
-
Are COSHH Assessments on site, correct and understood?
-
Is the risk assessments on site, correct and understood?
Traffic Management
-
Chapter 8 signs correct
-
Barriers in place and in good condition
-
Site tidy, materials stored correctly, safely
-
Cones correctly placed and reflective sleeves in good condition
-
Safety zones maintained
-
Pedestrian routes clear, signed and adequate
Vehicles, plant and equipment
-
Good condition and trained operatives
-
Chapter 8 marked vehicles fitted with beacons and reversing alarms
-
Security of vehicles, equipment when not working
-
Dust suppression systems in use
-
Maintenance registers correct for all plant ( weekly inspection book for jcb)
-
Lifting equipment checked in last 6 months, correct colour code
-
Towed plant and trailers lighting boards
-
Second form of braking on towed plant I.e brake chain
-
Ladders identified, checked, register, policy and permit to use or PAS 250
Training
-
Staff trained to minimum standard, CSCS, SSSTS, ETS, CPCS
-
All inducted, including sub contractors and agency
POWRA
-
Completed for site
-
Suitable and sufficient for task
PPE
-
Hard hats
-
Long sleeve, not rolled up, hi vis top and trousers
-
Flame retardant
-
Gloves
-
Hearing protection
-
Eye protection
Welfare
-
Water container, drinking water
-
Toilet available
-
Washing facilities, hot water for washing hands
-
Cabin provided, clean and adequate
-
Smoking area
First aid, fire fighting and emergency planning
-
First aider on site
-
Contact details of nearest hospital
-
First aid kit
-
Fire fighting equipment on site
-
Accident, incident, near miss procedure understood on site
Site layout and housekeeping
-
Safe, tidy and professional
Services
-
Stat plans on site
-
CAT scan completed and trial holes dug
-
Locations marked
-
212 completed and on site
-
OHC specific RAs and measures in place ( goal posts, height limiters)
-
Insulated tools, flame retardant clothing
Working at height
-
Correct access equipment selected for task
-
Fall arrest equipment worn
-
Emergency plan understood
-
TM and public protected from falling objects
Hand arm vibration
-
Activity suitably planned
-
Staff awareness of HAVS
-
Dates of last HAVS screening ( max 12 months)
Manual handling
-
Staff trained in manual handling techniques
-
Mechanical use to reduce risk, but appropriate
-
Lifting tackle correctly colour coded and inspected
Excavation management
-
Staff trained in excavations upto 1.2 m
-
1.2 to 2 m authorised person planned and approved
-
2m + approval via ground specialists
-
Specific RA available 223 completed daily
Environmental issues
-
How is waste being disposed
-
WTN completed correctly
-
Are spill kits available
-
Is fuel stored correctly
-
Controls in place for noise, dust, water pollution
-
Pre work assessment completed
-
Specific RA if working over water, approved by SHEQ Dept
Other comments or observations
-
Notes and media others