Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • This section of the BCI ITP covers the quality assurance record of station one for framing, insulation, plumbing and electrical.

  • The BCI Traveler BCI:QCC is the verifying document for the ITP. Testing documents are supplemental to the ITP.

  • Review drawings for module floor construction<br>USPT-WP-ADDET-2100A6-001 to A6-002<br>USPT-WP-MDLAY-2100M5-001 to M5-025<br>USPT-WP-MSEC-2100M1-001<br>USPT-WP-ESPDS-000007 (SOW Attachment E)<br>USPT-WP-EDLAY-2100ED-01A to ED-01C<br>USPT-WP-EDLAY-2100ED-01B to ED-01C<br><br>

  • Take picture of Jim

  • Enter the drawing numbers appropriate for the flooring work

TOOLBOX SAFETY MEETING OR JSA

  • Was a toolbox safety meeting conducted or a JSA for today's work?

  • Enter time and date of inspection

  • Was a roster of attendees completed to document the safety meeting or JSA?

  • Enter time and date of inspection

  • Completed by Ice Services Quality

FRAMING

  • Verify all materials are correct according to the Camp3 drawings, BCI specifications, and Approved Change Orders.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Verify the correct dimensions according to the Camp 3 drawings and BCI specifications.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Verify correct layout including, blocking, backing, chases and openings, for any plumbing or mechanical components according to the Camp 3 drawings or BCI specifications.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Verify the correct temperature for the application and curing of adhesives.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Verify the correct use of the fastening system and the required nailing detail.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Visually inspect construction for correctness and quality.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

INSULATION

  • Verify insulation materials per plan and BCI specifications

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Fiberglass insulation installed per BCI and manufacturers specifications.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Cellulose insulation installed per BCI and manufacturers specifications.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Install 2nd and 3rd floor insulation at exterior rim.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

ELECTRICAL

  • Verify all materials are correct per design drawings and BCI specifications

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Branch Circuits - verify proper location and layout per design drawings.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Branch circuits - verify properly rigid and secured.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Integrity of raceway - verify proper layout and location.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Heat trace - verify proper layout and location and installation per manufacturers specification.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Calibration and inspection of testing equipment

  • Verify all instrumentation has current calibration.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Merger testing

  • Merger leads are to be connected together and test performed to verify leads are in correct position and cords are not damaged before testing of heat trace, feeder, and branch circuits. A reading of zero is correct. The BCI- ETPM is to be completed.

  • Merger testing completed and documented on the BCI- ETPM report

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Heat tracing is to be tested to Nelson heat tracing specifications.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Heat trace testing was performed and documented on the BCI-ETHT report.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

PLUMBING

  • Underfloor waste and vents - verify plumbing layout per plans

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Underfloor waste and vents - visually inspect construction for correctness and quality.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Testing of Underfloor waste and vents - verify that all instrumentation has current calibration.

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Testing of Underfloor waste and vents - Test 1 After rough-in - a 5 psi air test for minimum of 15 minutes per BCI- PT

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Testing of Underfloor waste and vents - Test 2 All waste piping will be floe tested near final station of plant. This test may be performed at the same time as the final Domestic Water Flow Test. After completion of this test, the system will be drained down and blown out to insure no water is left in the system. See BCI-PT

  • Enter time and date of inspection

  • Completed by Ice Services Quality

  • Testing of Underfloor waste and vents - Re-test (if needed) If the floor system is cut into or has any demo done to it, the under floor waste and vent system will be re-tested according to the same procedured outlined above. See BCI-PT<br>

  • Enter time and date of inspection

  • Completed by Ice Services Quality

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.