Title Page

  • BSG Job No.

  • Client / Site

  • Location
  • Conducted on

Contractor

  • Completed by

  • Company

  • Contact number

Contractor Completion Certificate

CONTRACTOR COMPLETION CERTIFICATE

  • CONTRACTOR TO COMPLETE

    please complete as required

  • All signage has been installed as per documentation supplied and relevant legislation

  • All signage is installed defect free

  • No packing, old signage or rubbish remains on site. Site has been left clean & any damage to garden beds has been reinstated.

  • All access equipment has been made safe & off-hired &/or removed from site

  • Make safe & off-hire all equipment before leaving site

  • All signs are touched up & cleaned

  • All illuminated signs are tested & working

  • Photos have been taken showing illumination test

  • Reason why photos were not taken

  • Reason why sign was not tested

  • All works are completed & relevant OH&S paperwork including task specific SWMS has been filled out

  • No issues or outstanding items remain

  • Defects exist - comment below

  • Defect comments

  • CHECKLIST PRIOR TO LEAVING SITE

  • Site contact or authorised representative has viewed all signs prior to signing completion certificate

  • Reason why

  • All signs have been photographed as per Bentleigh Group photographic requirements

  • Council/engineers inspections have been completed where required

  • Inspection certificates &/or documentation will be supplied to project manager

Signature

  • Signed by lead contractor that all above information is true & correct

CONTRACTOR COMMENTS/FEEDBACK

  • Comments

VARIATIONS

  • Is there any variation to original scope of work?

  • Variation to original PO exists

  • Variation confirmation in writing from PM attached

  • Variation approved by

  • Date approved

  • Variation amount

  • Reason for variation

NOTES

  • All fields to be filled out by contractor & client sign off document completed. These documents along with high quality completion photos, a copy of SWMS & any other required documents are to be received by project manager before any invoices will be processed.

Customer Completion Certificate

CLIENT COMPLETION CERTIFICATE

  • Dear valued customer;

    Please fill out below fields to confirm you are satisfied with the completed signage works.
    Feel free to leave any comments or feedback in the space provided.

  • You are satisfied all signage has been supplied & installed as required

  • Illuminated signs have been connected to power & are working

  • Your site has been left clean & tidy

  • Do any defects exist?

  • Please detail issues

  • Do you wish to supply photos?

  • Attach photos if required

Sign-off

  • Name & signature of client or authorised representative

  • Company

  • Position

FEEDBACK / COMMENTS

  • Comments

Photos

COMPLETION PHOTOS WHERE REQUIRED

  • Photos

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.