Title Page

  • Project Name

  • Inspection Start Date

  • Inspected by

  • Inspected for:

  • Site Address and Location
  • Floor nr:

Visual Inspection on Site

BG Ceiling - 1st Fix

  • Confirm MEP overhead is complete and sign off prior to ceiling framing?

  • Confirm all service holes have been made good/ firestopped through walls and floors?

  • Correct RCP Drawings used? <br>Last Revision?

  • Correct Details Drawings used?<br>Last Revision?

  • Datums given by Site Engineer?

  • Bulkhead in place at the right height where required by RCP?

  • FCL correct as per drawing

  • FEA1 Rigid angle hangers & GL12 Gypframe brackets installed correctly (1200mm centres)?

  • GAH2 Acoustic Hanger used as required by Ceiling Details Drawing?

  • MF6 and GL8 Perimeter channels fixed at 600mm centres into suitable fixing surface?

  • MF6 and GL8 Perimeter channels not fixed where CL >3400mm?

  • MF7 Primary support channel fixed to the angle hanger (every 1200mm centres) with correct fixings (13mm wafer)

  • MF5 ceiling furring channels at correct centres (450mm)

  • MF5 furring channels joints overlapping by 150mm min (if applicable)

  • MF5 ceiling furring channels engaging into MF6 correctly

  • GL1 Lining channel at correct centres (450 or 600mm)

  • MF and GL Junction detail as per specs?

  • RB1 Resilient Bar at correct centres (450mm) where required by Ceiling Details Drawing?

  • Extra support for Angled Coving at Gypframe Level where required?

  • Timber supports for Angled Coving at 600mmm centres?

  • Pattresses installed as per Ceiling Details Drawing?

  • No Gypframe clashes with services?

  • Confirm all grilles and access panels are as per plans and specs?

BG Ceiling - 2nd Fix

  • RWA45 Rockwool 50mm as required by Ceiling Details Drawing?

  • Acoustic Sealant on Ceiling perimeter as per specs?

  • Correct plasterboard used on the underside as per drawings?

  • Plasterboard installed 90 degrees to MF5?

  • Confirm that any wall surfaces have been damaged?

  • Confirm all cuts out are as per plan and specs?

  • Confirm that any above ceiling services have been damaged?

  • Work area left clean and tidy?

Sign off

Snags rectified?

  • Name

Sign Off by Subcontractor

  • Name

Report accepted by MY CONSTRUCTION:

  • Name

Report and Works Accepted by CLIENT - CRITERION:

  • Comments

  • Name

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.