Title Page
-
Name of Surveyor
-
Site Address
-
Tenant name
-
Customer Contact Number
-
Contract/Client
-
Installation type
- Combi boiler chg
- Upgrade from heat/system boiler to combi
- Upgrade from BBU to combi
- Full install
- Radiators only
- Pipework and rads
- Not required
-
Property type
-
Door code if void or access notes
-
Type of installation Existing
-
Old boiler, Tanks and cylinder to be removed?
-
Boiler type required
- Worcester 4000 30KW
- Worcester 4000 25KW
- Worcester system 12KW
- Worcester system 15KW
- Worcester system 18KW
- Worcester system 21KW
- Worcester system 24KW
- Worcester H/O 15KW
- Vaillant Sustain 28kw
- Vaillant Sustain 24kw
- Vaillant Ecotec pro 28kw
- Vaillant Ecotec pro 24kw
- Boiler not required
-
Please take pictures of proposed new boiler location.
-
Please take picture of Existing Flue. Inside & Externally
-
Flue type required
- Standard
- Long standard
- Vertical flue, 3 ext plus 45 bends
- Vertical flue, 2 ext plus 45 bends
- Vertical flue, 1 ext plus 45 bends
- Standard flue with plume kit
- Not required
-
Worcester simple link flue adapter
-
Flue accessorys
-
Controls pack required
-
Details of condense discharge
- Internal to sink/Basin waste up to 3 meters
- Internal to sink/Basin waste over 3 meters
- External waste to drain up to 3 meters
- External waste to drain over 3 meters
- Existing okay
- Existing okay but needs external lagging 3 meters
- Existing okay but needs external lagging 6 meters
- Existing okay but needs external lagging 9 meters
- Not required
-
Condense notes or special materials
-
Gas run in meters if required
-
Replace lead tail on gas meter
-
TRVs required
-
Lock shield valves required
-
Size of radiator valves required?
- 8mm
- 10mm
- 15mm
-
Please list sizes of any radiators that need to be replaced and which rooms they are situated in?
-
Additional materials
-
Is scaffolding required?
-
If scaffolding required please take photos of position
-
Stop tap working
-
Is electrician required day of install
-
Please select electrical parts requirements
-
Customers actions required IE empty airing cupboard...
-
Customer actions signiture
-
Additional notes
-
Recommendations of work required
- Boiler change only
- Boiler change with replacement of radiators
- Full central heating install
- Remove heat only/BBU/Wall mounted boiler and upgrade to a combi boiler
- Replace radiators only
- Remove and refit radiators to allow for kitchen/Bathroom works
- Other work please describe
- No work required
-
Any asbestos concerns ?
-
Property condition
- Very good
- Good
- Fair
- Poor
- Requires attention before an engineer can work in
-
Please log any builder work required here