Title Page
-
Fava and Axor Lines No longer need heat
-
SOP # 221
-
Department
-
Conducted on
-
Prepared by
SOP 221 Procedures
Purpose
-
The purpose of SOP 221 is to prevent damage to Boilers and Heat Exchangers from Thermal Shock. It also ensures the chemistry of the water systems remain consistent.
Scope
-
This SOP is intended to assist Operators and Non Maintenance Personnel on how to safely and securely place the Boiler Room in a Stand Bye condition for a normal process shutdown.
Procedures
-
Lower the Setpoint on South Boiler to 150 F
-
Turn the VFD control on the Hot Water Pumps to 30 HZ
-
Ensure North Boiler is in the Off Position
-
Ensure Cold Water Pumps are Running
-
Ensure Chiller Breaker is ON
-
Ensure Fin Fan Breaker is ON
-
Perform a visual inspection of room and look for any leaks or tripping hazards.
-
Turn off the Lights in the Boiler Room
Completion
-
Full Name and Signature of Employee