Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
site information
-
Job & Dept.
-
Title of person who does job:
-
Dept. Supervisor
-
date
check applicable anticipated or potential hazards
-
Exposure to chemicals?
-
Activities in or near high traffic areas
-
Powered Industrial Truck equipment activity (Forklifts, Pallet Jacks, Reach trucks, Die Carts, Walk-Behinds)
-
Work affecting integrity of critical controls
-
Welding, cutting, grinding
-
Arch flash hazards
-
pressure testing
-
Other (specify) :
critical procedures: where work involves any of the following hazards must be incorporated into JSA
-
Work at heights above 1.5m
-
Confined space entry (includes tank cleaning)
-
Electrical/Mechanical lockout (live, isolation, lock out / tag out
-
Heavy equiptment lifting (cranes, boom trucks, excavators)
-
Hot work (in potentially explosive atmosphere)
ensure all hazards identified are addressed in JSA below
-
1. sequence of basic job Step in order
-
1.potential hazards. (Ex. underground services, hazard zone etc.)
-
1.safety controls to reduce or eliminate hazard
-
2. sequence of basic job Step in order
-
2. potential hazards. (Ex. underground services, hazard zone etc.)
-
2. safety controls to reduce or eliminate hazard
-
3. sequence of basic job Step in order
-
3. potential hazards. (Ex. underground services, hazard zone etc.)
-
3.safety controls to reduce or eliminate hazard
-
4. sequence of basic job Step in order
-
4. potential hazards. (Ex. underground services, hazard zone etc.)
-
4.safety controls to reduce or eliminate hazard
-
5. sequence of basic job Step in order
-
5. potential hazards. (Ex. underground services, hazard zone etc.)
-
5.safety controls to reduce or eliminate hazard
-
6. sequence of basic job Step in order
-
6. potential hazards. (Ex. underground services, hazard zone etc.)
-
6.safety controls to reduce or eliminate hazard
-
7. sequence of basic job Step in order
-
7. potential hazards. (Ex. underground services, hazard zone etc.)
-
7.safety controls to reduce or eliminate hazard
-
8. Sequences of basic job Step in order
-
8. potential hazards. (Ex. underground services, hazard zone etc.)
-
8.safety controls to reduce or eliminate hazard
-
9. Sequences of basic job Step in order
-
9. potential hazards. (Ex. underground services, hazard zone etc.)
-
9 . safety controls to reduce or eliminate hazard
tools / Equipment ( list of tools and equipment and their storage on site, if relevant to safety
-
List
additional PPE ( minimum requirement: safety boots, hard hat, visi-vest, glasses, gloves)
-
Eye protection
-
Hearing protection
-
Fall protection
-
Cotton gloves
-
Chemical resistant gloves
-
Splash goggles
-
Chemical resistant apron
-
Hard hat
-
Dust respirator (N95)
-
Full face respirator
-
Face shield
-
Vapor respirator
-
Chemical resistant boots
-
Chemical resistant body suit
-
Leather gloves
-
Portable gas monitor
-
Other (fire retardant coveralls, breathing apparatus, etc) specify :
site supervisor
-
Approved by:
-
date