Title Page

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Framing and Sheathing

  • Framing per approved engineering and shop drawings?

  • Inspections passed?

  • Sheathing installed uniform/plumb and in good condition?

  • Slab edge firesafing installed?

  • Blocking, trims, accessories installed per plan?

Waterproofing (hot applied, peel-in-stick, cold applied, etc)

  • Primer installed?

  • Waterproofing installed?

  • Waterproofing uniform and plumb?

  • Confirm butt joints and the lapping correct?

  • Flashing, trims, and accessories installed?

  • Additional tape at rain screen locations for fasteners?

  • Manufacturer representative site visit?

  • Pull test for caulk?

  • Ready for water test?

  • Water test complete and passes?

EIFS/Plaster

  • Framing/substrate prepped, uniform, and complete?

  • Gold Coat Applied?

  • Mesh wrapped around openings?

  • Trims, flashing, accessories installed at openings?

  • Control and expansion joints with flashing installed?

  • Insulation foam installed?

  • Brown coat installed?

  • Finish coat installed?

  • Manufacturer representative visited/inspected the site?

  • Pull test for caulk?

  • Ready for water test?

  • Water test complete and passed?

Punched Openings

  • Framing, blocking, substrate complete?

  • Waterproofing complete through opening?

  • Frame set to waterproofed condition/substrate?

  • Aluminum frame in good condition? Any damage?

  • Primary caulk to weather barrier?

  • Glass set in opening?

  • Glass in good condition? Any damage?

  • Trims, accessories, gaskets installed?

  • Stool trim installed?

  • Finish caulking installed uniform around opening?

  • Glass manufacturer visited/inspected the installation?

  • Aluminum frame manufacturer visited/inspected the installation?

  • Pull test for caulk?

  • Ready for water test?

  • Water test complete and passed?

Curtain Wall

  • Embed clips installed per shop drawings?

  • Slab edge firesafing installed?

  • Aluminum framing installed and fully bolted

  • Aluminum frame in good condition? Any damage?

  • Glass installed per the shop drawings?

  • Glass in good condition? Any damage?

  • Gaskets, trim, and accessories installed?

  • Primary caulk installed?

  • Specialty items (i.e. Fins, lights, sunshades, etc) installed?

  • Glass manufacturer visited/inspected the installation?

  • Aluminum frame manufacturer visited/inspected the installation?

  • Pull test for caulk?

  • Ready for water test?

  • Water test complete and passed?

Rain Screen/Louvers

  • Waterproofing installed around openings/substrate?

  • Fastener locations identified and addressed with penetrations through substrate waterproofing?

  • Gaskets, trims, accessories installed?

  • Primary caulk installed?

Roofing

  • Roofing installed per plans? (I.e. Slope, drain locations, flashings, etc)

  • Roofing penetrations properly flashed?

  • Trims, blocking, flashings, accessories installed?

  • Blocking with underpayment material installed on parapets?

  • Coping and flashings at parapet installed?

  • No ponding/stagnant water seen?

  • Any visual damage to roof membrane?

  • Manufacturer representative visited/inspected the site?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.