Information

  • Cabinet ID

  • ABFFP ID and Street Name

  • Audit date

  • Auditor name

  • Auditee name

Field checks

3 - Microduct and duct lay - Reference Chorus document ND0629

  • 3.1 - Ducts laid or directional drilled between 450mm and 1000mm in footway

  • 3.2 - Ducts laid or directional drilled between 600mm and 1000mm in roadway (min 1.5m on NZTA road crossings)

  • 3.3 - Duct alignment/Offsets follow good blown fibre network practice (minimizing alignment deviations where possible)

  • 3.4 - Route position correct according to plan or where deviations occur the variation is captured

  • 3.5 - Pole to boundary duct at customers boundary and pole, has cap

4 - Laterals - Reference Chorus Document ND13044

  • 4.1 - lateral boundary drop labelled correctly with ABFFP ID and Tube Number on either of the 2 specified labelling conventions

  • 4.2 - Marker post installed at Lateral position, Lateral tubes cable tied to marker post, tubes cut down just below top of post, tubes capped (where applicable)

5 - Hand holes - Reference Chorus document ND0588

  • 5.1 - Sited correctly (close to customer boundary, hard surface, foot traffic only)

  • 5.2 - Hand hole locked, with lock facing the customer boundary and openable

  • 5.3 - Starter pipe(s) installed to facilitate provisioning of NGA services

  • 5.4 - Flush with ground, no trip hazards

  • 5.5 - Lid free from concrete/ seal

  • 5.6 - Single way Ribbonet, 1 turn only, end capped/ sealed with heat shrink, labelled

  • 5.7 - Maximum of 4 single way Ribbonets installed

6 - Manhole, joint chamber and ducts (new and existing)

  • 6.1 - Manhole sited correctly to As Build plans

  • 6.2 - Manhole correctly sized, as per design plan

  • 6.3 - Manholes frames flush to ground, no trip hazard

  • 6.4 - Concrete joint chamber micro duct entry grouted, duct reamed, sits flush to wall

  • 6.5 - Non-concrete joint chamber duct entry protrudes 50mm into chamber, reamed and sealed to wall

  • 6.6 - Manhole/joint chamber lids locked, in working order and rubber bung fitted

  • 6.7 - Ducts entry positioned close to adjacent wall for easy cable management

  • 6.8 - Ducts sealed where necessary to prevent ingress of water, moisture, gas, or pests into exchanges

  • 6.9 - New ducts into existing manholes - correct hole size and location cut in manhole wall for new duct entry

  • 6.10 - Pit correctly bedded - No subsidence observed

9 - Aerial - CT's/FAT's/RAT's - Reference Chorus document ND0588

  • 9.1 - Correct terminal used

  • 9.2 - Terminal mounted and secured correctly

  • 9.3 - Terminal lid secure

  • 9.4 - Network labelling in place on lids and matches CPA's

  • 9.5 - Terminal on correct pole face

  • 9.6 - Flexi pipe secured directly below CT terminal (galv saddle on wooden pole/Bandit tape on Concrete poles)

  • 9.7 - 32mm HDPE grey duct secured to pole with saddles plastic saddles secured with clouts -600mm spacing (Wooden Poles)

  • 9.8 - 32mm HDPE grey duct secured to pole with bandit strap - spacing < 1.5m (concrete poles)

  • 9.9 - Protective cable casing installed (as required - concrete or wood)

10 - BDD terminal - Reference Chorus document ND0588

  • 10.1 - Pit lids secure/locked, with bung fitted where appropriate

  • 10.2 - Pit installed correctly

  • 10.3 - Any Microduct in BDD is capped/heatshrunk/labelled

  • 10.4 - Ensure Fixed fibre draw tape runs through BDD's

11 - Pedestal - Reference Chorus document ND0588

  • 11.1 - Pedestal vertical, firm and at correct depth

  • 11.2 - Lid secure and labelled

  • 11.3 - Starter pipe(s) installed to facilitate provisioning of NGA Services

  • 11.4 - Any Microduct in Pedestals is capped/labelled

13 - Flash 9 installation - reference Chorus Document ND0610

  • 13.1 - Microduct DB - 50mm of inner black sheath past outer green sheath

  • 13.2 - Earth wires have tape where they exit the microduct sheath, are secured to pit wall and labelled

  • 13.3 - Micro duct tubes routed correctly in pit - minimum bend radius not exceeded

  • 13.4 - Velcro ties secured to the pit wall for joint bundle

  • 13.5 - Correct micro duct connectors used to join and seal micro duct (5mm and 12mm)

  • 13.6 - Correct size gas blocks installed on 12mm micro ducts outside of closure containing optic fibre cable

  • 13.7 - All spare or unallocated 5mm and 12mm micro ducts capped with end caps in joint bundle

  • 13.11 - All 5mm micro ducts trimmed to 80mm in height from base

  • 13.12 - All 12mm micro ducts trimmed to 40mm in height from base

  • 13.18 - All microducts are labelled inside dome

  • 13.25 - Micro ducts 1 - 26 enter through 3 RH ports (viewed from swing arm)

  • 13.26 - 100mm duct capped at pole (Aerial)

14 - Aerial Cable - Refrence Chorus Document ND0623

  • 14.1 - Anchor clamp/dead end grip terminated correctly

  • 14.2 - Cable down pole secured with down-lead clamp with appropriate spacing

  • 14.3 - Fibre on lower section of pole protected with pole guard

  • 14.4 - Aerial cable within 800mm of existing low voltage envelope

  • 14.5 - Sag matches that of existing lines as best as possible

General Workmanship checks

15 - Reinstatement - Reference NCOP/Local Council

  • 15.1 - Properly damage made good

  • 15.2 - Any road markings damaged by works are restored

  • 15.3 - Surplus soil removed

  • 15.4 - Reinstatement completed to NCOP specifications and local conditions

  • 15.5 - Compaction tests supplied by civil crew

16 - Site tidy

  • 16.1 - Site tidy, no task waste - poles

  • 16.2 - Site tidy, no task waste - general

17 - Existing Infrastructure Damage

  • Is there any damage to existing Infrastructure that needs to be reported to Chorus

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.