Information
-
Job Number:
-
Customer:
-
Address:
-
Installer name:
-
Assessor Name:
-
Conducted on:
Boiler
-
Manufacturer:
-
Model:
-
Serial Number:
-
GC Number:
1. Gas compliance
-
Boiler location and clearances correct and securely fitted?<br>
-
Flue installation correct - route/terminal/support/Fixings<br>Making good - internal minimum - external if possible<br>
-
Gas supply correctly sized?<br>
-
Gas supply sleeved and sealed (At Risk)
-
Gas supply correct - route and fixings?
-
Gas tightness test complete and correct?
-
Meter outlet working pressure correct? ( Record reading below)
-
mbar
-
Boiler inlet working pressure correct? (Record reading below)
-
mbar
-
Gas rate and volume correct? (Record reading below)
-
kw
-
m3/ph
-
Flue gas anyalyser test correct? (Record reading below)
-
CO ppm :
-
CO2 vol %:
-
CO/CO2 Ratio:
2. System Details
-
Has the compensate discharge been correctly installed?<br>
-
Has the safety discharge pipe been installed correctly?<br>
-
Has all pipe work been installed neat and tidy, are all pipes clipped and clean etc?<br>
-
System water clean and inhibition correct?<br>
-
Has the system been correctly balanced?<br>
-
System bypass fitted and/or correctly set?<br>
-
Have TRV's been fitted?
-
Have the Hot Water cylinder and assosciated paperwork correctly lagged?<br>
-
Filling loop fitted correctly, hose link removed and connections capped?
-
Does the system have an adequate and accessible drain off fitted?<br>
-
Where dust sheets used?<br>
-
Property left clean after work?
-
Waste removed from site?
-
Building work/making good carried out by:
-
Building work including all making good (internal & external) complete?
-
Customer instructed on use of new system/controls?
-
Benchmark certificate left inside and filled out correctly?
-
CP12 on site and correctly completed?
Electrical and misc
-
Have controls been fitted correctly and to specification?
-
Main and/or supplementary bonding correct?
-
All electrical work is tidy including all trucking etc?
-
Is the ECV operational and accessible?
-
Has the installation been completed in accordance with posted measures on DRC?
-
If NO please provide further information:
-
Correct access points for flue in voids ?
Summary
-
Visit outcome:
-
Has the installer been informed of any defects or corrective remedial work?
-
Feedback on assessment and any corrective action taken: