Title Page
-
Project
-
Site Address
-
Lot No.
-
Lot No.
-
Job Number
-
Audit Type
-
Site Manager
-
Conducted on
-
Concreter
Concrete pour
-
Note approximate weather conditions, rain and temperature
-
Is concrete boom / line pump set up in the correct location?
-
No water has / is being added to the mix. ( Minimal amounts ok 30 liters and under )
-
Is a Boral tester on site?
-
Vibrator in use ( photo )
-
Is concrete supply consistent?
-
Is bath box installed?
-
Other Photos
-