Information

  • Document No.

  • Project Name

  • Auditor

  • Location
  • Conducted on

  • Contractors

Administrative Job Site Requirements

  • Active construction area clearly demarcated and safety access signage posted?

  • Emergency contact information, egress routes and evacuation muster points posted?

  • Area urgent and emergency healthcare facilities posted?

  • Daily SPA accurately reflects work, means/ methods, and precautions?

  • Daily SPA reviewed and signed by Superintendent or representative?

  • Daily SPA readily accessible in the field?

  • Daily SPA completed and signed by contractor Competent Person and contractors performing the work?

  • Daily SPAs are closed and end of day affirmation signed?

  • JSAs readily accessible in the field?

  • Are all JSAs reviewed and approved by EHS?

  • Name of JSA(s) audited? Audit 1 JSA per active contractor.

  • Does the JSA adequately capture the scope of work?

  • Are JSAs signed by the contractors working on the job?

  • Name of JSA reviewed? Review 1 JSA per active contractor.

  • Are JSA's signed by and approved by EHS?

  • Are JSA's signed by the contractors working on the job?

  • Does the JSA adequately capture the scope of work?

  • If applicable, are required personnel OSHA 10/30 Hour trained for Foreman/Supervisors?

  • Are construction signs posted?

COVID-19 Mitigation

  • COVID-19 Management Plan for project/ site approved and current?

  • Client COVID-19 screening process implemented for contractors?

  • C2 Daily Pandemic Self-Assessment completed by all contractors and visitors?

  • COVID-19 signage posted clearly?

  • Sanitation facilities and hand washing facilities available and stocked?

  • Routine (3-4 times daily) touchpoint sanitization being conducted?

  • All workers and visitors wearing fabric or surgical mask face-covering? Bandanas and neck gaiters prohibited.

  • All workers maintaining 6' distance at all times?

  • Does workers have a COVID-19 Pre-Task Safety Planning in place for activities which are infeasible to complete while maintaining 6' of distancing at all times?

  • Break and lunch accommodations made to maintain 6' distance?

  • Tools not being shared or being sanitized between users?

Housekeeping

  • Are materials stored properly?

  • Is trash being centered piled and collected routinely throughout work day?

  • Has construction dumpster been designated and located for the project?

  • Is the dumpster appropriately sized and properly managed for pick ups?

  • Are the walking and working surfaces clear, clean, trip hazards eliminated?

PPE

  • Are hard hats, safety glasses, cut resistant gloves, vests (as required), and steel or composite toe footwear being worn by craft and management?

  • Is the work being performed exceeding 85db? Is proper hearing protection in place?

  • Is there PPE available for visitors?

  • Is there any additional PPE being worn? Has it been identified in the JSA?

  • Are all respiratory users qualified or have signed the "voluntary use" sign off sheet on job site?

Fall Protection

  • Is work being preformed greater than 6ft?

  • Has the Working at Heights Permit been completed?

  • Are flag lines, weighted base and rail, and other relevant fall restraint systems properly utilized?

  • Has the proper PFAS been identified and inspected for the work?

  • Are anchor points engineered?

Fire Safety and Emergency.

  • Are there a proper fire extinguishers available with in 50 feet of work ?

  • Are the sprinkler heads & fire protection systems unobstructed ( sprinkler heads clear by 18'' or greater)?

  • Is the Fire Extinguisher Inspection current?

  • Is there a trained fire watch on duty during Hot Work?

  • Are flammable and combustible materials stored properly? ( SDS at point of use )

  • Are stairwells clear of combustible or flammable materials?

  • Is there a First Aid Kit and eye wash station on job site?

General Safety

  • Are there any outstanding safety violations that have been identified during the audit?

  • Are there any outstanding safety successes that have been identified during the audit?

  • All containers labeled? ( HAZCOM )

  • Is temporary lighting provided as needed? <br>(29 CFR 1926.56(a) table D-3)

  • Is equipment guarding in place as per manufacturers instructions?

  • Are tools and equipment inspected and in good condition prior to use?

  • Is there a spill kit on the job site?<br>

Ladders/ Stairs/ Scaffolds.

  • Are Stairs provided where there is a change in elevation >19'' ( EU >0.5m), and secured?

  • Are Stairs greater than 4 risers all equipped with a hand rail?

  • Is scaffolding in use, built by a qualified competent erector, built correctly, secured, tagged correctly and inspected daily? ( check mudsills or locked wheels)

  • Does the scaffolding have safe access and egress for workers?

  • Are Holes/penetrations protected with secured covers labeled "HOLE" or barricaded?

  • Is the scaffolding protected for use by unauthorized persons, is there a swing gate which can be locked when no one is working?

  • Are ladders being used safely? No one working above the 2 rung? Tied off when required? Etc...

  • Are Ladders in good condition? Labels, rings, feet...

  • Are Ladders being stored correctly?

  • Are Ladders in being used as intended?

  • Are Extension Ladders being used safely with proper pitch, ladder secured and a 36 inch overhang?

  • Are platforms protected by handrail, midrail and toe board?

Welding/ Cutting / Brazing

  • Has the hot work permit been reviewed and completed?

  • Have all combustibles been removed 35ft or covered? ( flammables removed)

  • Is torch cutting being performed with proper PPE and area prepped?

  • Are compressed gas cylinders secured and capped when not in use?

  • Are Torches, hoses, gauges / regulators in good conditions and equipped with flash back preventers?

Crane Lifting / Rigging.

  • Has the lift plan and permit been completed and reviewed with all affected personnel?

  • Are there trained signal men in "line of sight" of operator or other means of communication with operator?

  • Has the qualified rigger inspected all lifting equipment prior to use?

  • Has the crane been properly barricaded?

  • Have all the areas within the swing radius been notified, with proper signage , barricaded with danger tape and evacuated?

  • Are tag lines being used to control the load?

  • Has the crane inspections been completed and documented?

Excavation/ Confined Space.

  • Verify One Call ticket.

  • Utility mark out is clear and being refreshed by the excavation contractor?

  • Is the excavation lay out in White?

  • Has the excavation permit been reviewed and completed?

  • Has utility location taken place? 8 feet outside the permiter of the excavation?<br>Verify report

  • Are the trenches/ excavations sloped properly or shored and barricaded?

  • Is trench/ excavation greater than 4ft?

  • Is body harness being worn?

  • Are there proper egress in place, ladders no more than 25ft apart?

  • Is this a HAZWOPER site and if yes is training verified?

  • Has a weather event occurred since initial evaluation from a competent person?

  • Is confined space permit required and has the been permit been reviewed and completed?

  • Has the confined space attendant properly maintained the access log?

  • On site rescue team?

  • Are the Confined space personnel properly trained?

  • Verify Confined Space training?

  • Atmospheric testing at 3 levels? <br>Example: Top Middle Bottom

Motorized Equipment. ( [PIT's, lifts)

  • Is there motorized Equipment being use?

  • Has the proper inspection been performed and documented?

  • Do the operators have the proper training for the equipment being used?

  • Are seat belts used by all operators?

  • Do the motorized vehicles have proper back up alarm?

  • Is the chain or gate closed on Scissor Lift?

  • Are flaggers in place where needed?

  • Is Scissor Lift being used safely? Feet on surface not using mid rail or toe board to stand on not leaning outside lift?

  • For boom Lift is PPE correct?

  • Is the rollover protection in place and maintained?

  • Has field modification been made without manufacturers written approval?

Electrical Safety.

  • Is there a energized electrical permit in place?

  • Has the energized permit been reviewed and completed?

  • Are all electrical tools and cords free of chemicals, flammables and water?

  • Are extension/power cords creating a trip hazard?

  • Are cords in good condition, no cuts or repairs w/ tape?

  • Is the Proper Lockout/Tagout in place where needed?

  • Is there a 3ft clear distance around electrical panel?

  • Are GFCI's being used and closest to the power source?

  • Are the required permits completed and posted?

Environmental

  • Have all proper barricades been put in place to minimize cross contamination?

  • Are the Concrete truck washout procedures being followed?

  • Is the waste handling and disposal of hazardous waste being executed properly?

  • Is secondary containment in place where needed?

  • Is Threading Machine catch box in place?

  • Are Storm sewers protected?

  • Are chemicals at the job site being stored safely and are they labeled correctly?

  • Is there proper ventilation in place for stored chemicals?

  • Are the SDS provided at job site? ( point of use )

  • Are personnel trained in the chemicals they are handling?

Corrective actions and supplemental comments.

stakeholders

  • PM or CM

  • Auditor.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.