Information
-
Contractor
-
Foreman
-
Conducted on
-
Location
-
Personnel
-
Prepared by
Fall Protection
-
Body Harness & Lanyards with Shock Absorbers properly inspected & in use.
-
Independant safety lines in place; installed & anchored properly.
-
100% Tie-off when working in unprotected areas above 6ft.
Scaffolding
-
Exterior Scaffolding - Platforms / Picks have Handrails & Independent Lifelines in place.
-
Suspended scaffold anchor points & rigging sufficient?
-
Interior Scaffolding/Painter's Boom in good repair.
-
Scaffold & Painter's Boom anchor points & rigging sufficient?
Housekeeping
-
Walkways & Access Points free of debris and storage.
-
Trash & Debris properly disposed of.
-
Handwashing Station on site.
-
Damaged / Defective equipment removed and tagged "Out Of Service."
Tools
-
Hand tools are in good repair. (No damaged handles, no mushroomed heads.)
-
Power tools have proper guards in place.
-
Electric cords / tools are in good condition.
-
Fire Extinguisher accessible & fully charged.
-
Ladders in good repair, have three rung clearance & secured.
Personal Protective Equipment (PPE)
-
Hard Hats
-
Safety Glasses
-
Gloves
-
Face Shields / Welding Hoods
-
Protective Clothing
-
Proper Attire
-
Respiratory Protection
Environmental
-
Environmental Hazards Observed
-
Paint Storage Area designated?
-
Mixing Area designated & ground protected from spills.
Lead
-
Is this a lead project/is there lead paint on this tank?
-
Has the Action Zone been established & Lead Hazards signs in place?
-
Has personal air monitoring been done to set Action Levels?
-
Is a proper decontamination station set up? i.e.: hand-wash station, decontamination trailer with shower, changing area.
-
Has lead waste been tested/TCLP?
-
Lead waste storage area designated?
-
Is lead waste properly stored? i.e.: dumpster lined, covered at night, ground cover, hazardous waste storage drum.
-
Are crew members decontaminating before smoking, eating and/or drinking?
-
Is there a HEPA vacuum being used before exiting containment?
Containment
-
Is a containment system set up on this site?
-
Is the air tugger/ containment hoist properly mounted?
-
Is the hoist cable properly secured?
-
Is the cable in good condition?
-
Are the anchors in good condition? i.e.: not pulling loose
-
Correct number of cable clamps installed and properly torqued?
-
Is the rigging tree properly secured?
-
Is the rigging tree loaded evenly & properly?
-
Is the bonnet tight and secure? No low hanging/entanglement hazards.
-
Are the tarps/sided properly sealed & in good condition?
General
-
Job site properly marked, including barricades & construction signs.
-
First-aid & Bloodbourne Pathogens kit fully stocked & accessable
Signatures
-
Subcontractor Foreman
-
Auditor