Information

  • Do the Combined Services Layout Radiator positions correspond with the Solid Eight Module Setting out Layout Radiator positions?

  • Do the Builders Work Holes correspond with the Drainage Plans?

  • Does the Kitchen Layout work with the run out route from the stack?

  • Is there sufficient space for the Washing Machine and Acoustic Boxing to Soil Pipe where applicable?

Builders Work

  • AGD Builders Work Holes in Slab correspond with Layout Drawing?

  • Shuttering removed from sides and cover loose?

First Fix Drylining

  • 1st Side Board Complete to allow Domestic Drops to be fitted

  • HIU Cupboard fully boarded?

  • HIU Cupboard Taped and Jointed: Walls, Corners and Ceiling Joint?

  • Sheer Wall Dot and Dabbed

  • Corners of Walls behind RWP'S Boarded

  • Where applicable, has the Elevation been boarded in line with the Column to allow Bath and Shower Valve to fitted.

Pattresses

  • AGD Pattress

  • Rainwater Pattress

  • HIU Pattress

  • UF Heating Manifold Pattress

  • Radiator Patresses

  • Shower Patresses

Dry Lining related Builders Work

  • Letter Box for MCWS

  • Letter Box or Open Front for HIU Access

Housekeeping

  • All Rooms Clear or Extraneous Material and Debris

  • Acceptance

Sign Off and Acceptance

  • Imtech Representative

  • Shepherd Construction Representative (Block Manager)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.