Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Project Documentation
-
Q1. Is the message from the Whiteboard being communicated to all workers? - Please ask workers at random if supervisors have communicated the message from the whiteboard.
-
Q2. Previous audit items closed out
-
Q3. Are site teams using the correct meeting templates as per template folder in 4projects
-
Q4. Procurement Schedules - Nominated/Domestic Available- Included in contractors report (PM)
-
Q5. Handover File Progress Report Available and up to date (Within a month)
-
Q6. BCAR Report up to date (monthly basis)
-
Q7. Are requests for inspection & testing being notified to the design team as per the preliminary inspection plan hold points
-
Q8. Submittals Register Available and up to date
-
Q9. Are site teams utilising 4projects to track request for information ( RFI)
-
Q10. Are all drawing registers up to date and do the drawing racks and 4projects mirror the master register
-
Q 11. Are superseded drawings being disposed of once available through 4projects electronically, no hardcopy superseded drawings are required to be kept
-
Q12. Pre-appointment meeting held for each subcontractor onsite, is the PM attending? If this is not in place please email rreilly, dlee, dhennessey, Project QS, Project PM, Project CM to advise PM must attend pre-appointment meetings with QS prior to Sub contractor mobilising to site.
-
Q13. Are weekly quality check sheets being completed for each element of works carried out
-
Q14. NCR's raised and closed out
-
Q15. Have any OFI’s been raised in the past 30 days
-
Q16. Are calibration certificates available for each piece of equipment
-
Q17. Preliminary Inspection Plan printed A1 and displayed in office/meeting room
-
Q18. Company Policies - ISO 9001, 14001,45001, Safe T Cert, H&S Policy, Quality Policy & Environmental/Sustainability Policy are displayed in meeting room and up to date
Concrete Cube Control & Validation
-
Q19. Cube register available and up to date
-
Q20. Have all cube test passed since the last audit
-
Q 21. Is the CCL‐Q‐PR‐016 Concrete Cube Testing Procedure being followed correctly
Q 22. Is there a clean concrete testing tank available at 20 degrees as per above procedure
-
Q 23. Is the concrete curing room organised and tidy
Housekeeping
-
Q24. Are external roadway clean and free of debris
-
Q25. Is the site compound clean and well organised
-
Q26. Is the construction area clean and well organised,
-
Q27. Are temporary waste collection points clearly identified and managed
-
Q28. Are site offices clean and well organised
Quality Onsite - Choose one or more main subcontractor's onsite for this section
-
Q29. Is the quality of workmanship onsite up to standard
-
Q30. Are subcontractors using the materials specified
-
Q31. Are Subcontractors working off of the correct revisions of drawings - Do a sample check and cross check against the Master Register
-
Q32. Are Subcontractors shop drawings approved for use prior to installation onsite
-
Q33. Can site demonstrate where above works have gone through submittal approval process with Design Team <br>
-
Q. 34 Are QA inspections complete for this element of works?
-
Q 35. Ladies toilets have the following;<br>1. Sanitary bin<br><br>2. Bathroom cabinet<br>2. Mirror<br>3. Soap <br>4. Paper hand-towels / hand dryer<br>5. Waste bin<br>6. Hot water<br>
Submittals
-
Q 36. Have project management team members raising submittals been trained in CCL-Q-PR-012 Submittals Procedure?
-
Q.37 Are submittals being raised in accordance with CCL-Q-PR-012 Submittals Procedure?<br>Naming Convention<br>Closing of submittals
-
Quality Auditor
-
Project Manager/ Collen Site Management Team Representative