Information
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
PAPERWORK / ORGANISATION / GENERAL ISSUES
-
Add media
-
Reference to the PC's H&S Policy Available
-
Notes
-
The Pre-Construction Information is available On SIte
-
Notes
-
The Construction Phase Plan is On Site
-
Notes
-
The F10 Notification clearly displayed
-
Notes
-
Risk Assessments Complete and made available
-
Notes
-
COSHH Assessments have been made available to all
-
Notes
-
Site Inductions are being completed at site level
-
Notes
-
All Statutory Site Safety signage is in place
-
Notes
-
Permit to Work
-
Notes
-
Asbestos Survey on site for full reference
-
Notes
EMERGENCY PROCEDURES
-
Add media
-
Risk Assessments complete & made available
-
Notes
-
Fire Action Notices in place
-
Notes
-
Fire Marshall
-
Notes
-
Firefighting equipment available
-
Notes
-
First Aid notices clearly displayed
-
Notes
-
How to contact the emergency services displayed
-
Notes
-
The location of the first aid box
-
Notes
-
The first aid box suitably stocked
-
Notes
SCAFFOLDS
-
Add media
-
Risk Assessments complete and made available N/A Not applicable to this project
-
Notes
-
Alterations and Inspections by a competent person
-
Notes
-
Guard rails, toe boards and all work platforms installed
-
Notes
-
Guard rails, toe boards and all work platforms installed
-
Notes
-
Safe access is available to the scaffold
-
Notes
-
Standards are provided with base plates and sole plates
-
Notes
-
All ledger braces and transoms in correct position
-
Notes
-
Scaffold is secured to minimise the likelihood of collapse
-
Notes
SPEPS / LADDERS / PODIUMS / WAH
-
Add media
-
Risk Assessments complete and made available
-
Notes
-
Risk Assessments complete and made available
-
Notes
-
Ladders extend the correct distance
-
Notes
-
Ladders / steps are Industrial class rated
-
Notes
-
Brick guards / debris netting in place
-
Notes
-
Ladders are secured to prevent slippage
-
Notes
WORKING AT HEIGHT
-
Add media
-
Risk Assessments / Method Statements complete
-
Notes
-
No work to take place directly under Working At Height activities
-
Notes
EXCAVATIONS
-
Add media
-
Risk Assessments complete and made available
-
Notes
-
Designed and maintained support systems are in place
-
Notes
-
Sides of excavations are battered back
-
Notes
-
Safe secure access to the excavation is in place
-
Notes
-
Barriers are in place to prevent falls from height
-
Notes
-
Plant, materials are stored away from the excavation
-
Notes
-
The stability of adjacent structures has been considered
-
Notes
-
The excavation is inspected and the results recorded
-
Notes
MANUAL HANDLING
-
Add media
-
Risk Assessments complete and made available
-
Notes
-
The use of heavy materials is minimised
-
Notes
VEHICLES ON PROJECT / SITE
-
Add media
-
Risk Assessments complete and made available
-
Notes
-
Separate pedestrian and vehicle routes identified
-
Notes
-
Banks man are used to control vehicle movements
-
Notes
WELFARE / PPE
-
Add media
-
Risk Assessments complete and made available
-
Notes
-
Toilet facilities are provided and maintained/cleaned
-
Notes
-
Hot and cold water is provided to the washing facilities
-
Notes
-
Soap and towels are provided
-
Notes
-
Correct wet and dirty working clothing is provided
-
Notes
-
Changing and drying facilities are provided
-
Notes
-
Drinking water is provided and signed as necessary
-
Notes
-
Helmets are provided
-
Notes
-
High Visibility clothing provided
-
Notes
-
Safety Boots /Shoes provided
-
Notes
-
Safety Glasses provided
-
Notes
-
Hearing Protection provided
-
Notes
-
RPE Equipment provided
-
Notes
-
Accidents / Incidents to report
-
Notes
-
Hearing Protection provided
-
Notes
-
Risk Assessments complete and made available
-
Notes
-
Toilet facilities are provided and maintained/cleaned
-
Notes
ADDITIONAL NOTES
-
Add media
-
Add media
ATTENDANCE & SIGN OFF
-
Site Manager
-
CDM / Surveyor