Information
-
Date
-
Audit Title
-
Serco
-
Contractor
-
Completed by
-
Location
-
Job Number (FFP, iTools, VS etc)
-
WAP#
-
Onsite Supervisor
-
Brief description of works at time of inspection
General
General
-
Hazard Notice Board at the site entrance(s)?
-
Personnel/visitors inducted and signed onto daily prestart?
-
Personnel wearing compliant PPE? <br>(E.g. Hard hat, safety boots, hi viz vest, safety eye wear, hearing protection, long pants, long sleeved shirt)
-
Additional PPE available for the task?<br>(E.g. full face shield/dust mask for cutting concrete)
-
Hazards identified and controlled?
Organisational
Organisational
-
Appropriate registers completed and on site? (E.g. SDS, Plant/Equipment/Ladders)
-
Documented Work Plan and drawings available and being followed?
Process
Process
-
Are relevant permits in place?<br>(E.g. Hot works permit)
-
Fit for purpose fire extinguishers in close proximity?
-
Portable electrical equipment tested and tagged?<br>(E.g. Drills and leads)
-
Ladders identified and labelled?
-
Safety equipment certified?<br>(E.g. Harness points and fall arrest equipment checked)
-
Fall arrest equipment being used if required?
Environment
Environment
-
Worksite clean and tidy - No trip hazards?<br>Good Housekeeping
-
Dust and airflow managed?
-
Environmental conditions are suitable, I.e. Lighting levels and ventilation?
-
Spill kits available where required?
-
Hazardous substances being used/stored as per SDS recommendations?
Plant / Equipment
Plant / Equipment
-
Exclusion/Protection Zone(s) set up around working area(s)?
-
Lifters being used as per OEM (original Equipment Manufacturer) recommendations; appropriate for the weight?
-
Live bars/terminals mechanically protected when exposed, I.e. Wrapped in high density foam rubber?
-
Emergency Evacuation paths clear and unobstructed?
-
Appropriate steps are in place to properly and securely store plant and equipment overnight?
-
End of day, all Fire Walls/Floor sealed with temporary Fire Bags and blankets?
Critical Safety Checks
Critical Safety Checks
-
If any of the following safety critical areas are not compliant then work at the site should be postponed until the area of concern is addressed:
-
Permits / consents of work not in place e.g. working at heights, excavation / drilling, confined space work
-
Site Hazard Board and a induction/Sign in process
-
Egress Routes Impeded
-
Breach of SOP (not following procedures)
-
Isolation Procedures as per AS/NZS3000
-
Unsafe behaviour where potential to injure a person
-
Extra worksite photo
Sign Off
-
Actions required? (State by who and by when)
-
Chorus representative:
-
Positive behaviours
-
Any other comments?