Information

  • Document No.

  • Christeyns Engineering Project Document

  • Project initiation date

  • Job Number

  • CUK Account Manager and Regional Manager

  • Description of works to be costed

  • Are site plans available? Click the dots on the right hand side to add notes

  • Are wiring diagrams available for all machines to be connected to? Click the dots on the right hand side to give details

  • Select date

  • Have the customers equipment signals been considered for the type of CUK equipment being installed? And prodive details (FluxMulti/DF2 for example and the need for formula select boxes etc) Click the dots on the right hand side to give details

  • Select date

Initial Site Assessment (ISA) for Costing Purposes

  • ISA Conducted on

  • ISA Conducted by

  • Description of works to be costed

  • Attach photos here

  • Are site plans available? Click the dots on the right hand side to add notes

  • Attach plans if applicable

  • List customers washing equipment including weights

  • Ask customer for working hours and site access and give details

  • Has customer been informed of potential downtime of their machines? Click the dots on the right hand side to give details

  • Is access equipment required for working at height? Click the dots on the right hand side to give details

  • Is asbestos register available? Click the dots on the right hand side to give details and photos to attach below

  • Attach asbestos details

  • Are wiring diagrams available for all machines to be connected to? Click the dots on the right hand side to give details

  • Have the customers equipment signals been considered for the type of CUK equipment being installed? And provide details (FluxMulti/DF2 for example and the need for formula select boxes etc) Click the dots on the right hand side to give details

  • Inform customer of the need for services - we can price for electrical work. Give details of who was informed (Finalised once spec is agreed and job is authorised)

  • Inform customer of training to be given and the need for a list of delegates. Give details of who was informed

  • Inform customer of our job packs and H and S documentation. Give details on who was informed

  • Inform customer of site spares to be held securely and in a dry place. Give details of who was informed

  • Ask customer for any comments or requests? And give details (Paper work prior to install/car parking restrictions)

  • Costings submitted by when?

Full Site Assessment (FSA)

  • Date of FSA

  • FSA Conducted by

  • Is all information in ISA all correct or are further details required - click on the dots on right hand side to give details (New machinery/different wiring diagrams etc)

  • Has a management pack been created? - give details

  • Has the contract been signed/job authorised? Click on the dots on the right hand side to give details of a person who has authorised the job.

  • Has the job number been issued and put on the title page of this document? - if no give details

Equipment

  • Has the location of all systems been agreed with the customer? Give details of customer contact who agreed. Photos of locations can be added via the dots.

  • Has the location of the e-stops been agreed? Give details of the location and who agreed, photos and notes via the dots

  • Do the engineers have enough information from the sales team? (Pumps compartments/pack sizes/ etc.... Has relevant rep been informed)

Installation

  • Can start date be given to customer and rep? - give details if not

  • Expected duration of installation

  • List equipment/systems to be installed (and to which machines) - describe installation

  • List equipment spare kits to be available

  • Are all commissioning sheets for this job available in the job pack?

  • Has all the non stock items been ordered - give details of delivery dates

  • Are all procedures in place for all equipment to be installed? Give details of any missing

  • Are all CUK engineers experienced/qualified to carry out all tasks safely - give details (eg, Engineer 'X' will not be wiring to customer equipment without proper supervision)

  • Reiterate downtime requirements to customer - give details of who this was discussed with

  • Customer actions discussed - Give details (services/floor levelling etc)

  • Has CUK job pack and customer work permits been completed - if no, give details (2nd site survey, job not starting yet...etc)

  • Are H and S passports up to date? If no give details

  • Are all CUK tools PAT tested and in date?

  • Are all CUK ladders in date?

  • Is all CUK PPE in date and fit for purpose?

  • Are contractors involved with the installation? - give details of who (Installers/tank people/tank clean out people/etc)

  • Have all contractors completed the 'Contractor Code of Conduct' form? - give details

  • Have all contracts RAM's, insurance and training certificates been obtained - give details

  • Are all contractors equipment in date and registered? - give details (PAT/ladders/harnesses/PPE)

  • What arrangements have been made regarding equipment unloading and safe storage?

  • List requirements for working at height

  • Will there be any requirement for working at height once this job is complete? - give details (Rep access to pumps etc).

  • Give details of floor surface condition

  • Give details of on site waste disposal

  • Give details of any hazards not on generic RA

  • Will there be a requirement for pressure testing? Give details

  • Is there asbestos in the engineers work environment? Give details of register

Chemicals

  • Are all chemicals supplied by CUK? - if no, give details

  • Can all chemicals be segregated as per segregation matrix in job pack, if not, what measures are to be put in place?

  • Size of area in use chemicals - photos and notes can be added via the dots on the right hand side

  • Are there any drains in the vicinity, if so what measures are to be put in place to prevent any chemicals entering the drains?

  • Can chemicals be stored away from pedestrians or access restricted? Give details

  • Are there any temperature issues where the chemicals are to be located? Give details

  • Does the area need to be ventilated? Give details

Training

  • Do we know who needs to be trained? Give details

  • Do we know who is carrying out the training and when? Give details

  • Are training forms in the job pack?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.