Information
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Contractor on site
SECTION 1. SITE DETAILS
-
Audit Number
-
Audit Title
-
Site Address Being Audited
-
Analyst Being Audited
- Simon Mitchell
- Lisa Worley
-
Date of Audit
-
Location Air Monitoring Sampling
-
Type of Air Monitoring
- 4 Stage Clearance
- Reassurance
- Leak Test
- Background
- Personal
-
Site Job Number
SECTION 2. DOCUMENTATION CHECK
-
Has the analyst reviewed the method statement, risk assessment, COSHH on site?
-
Analysts guide HSG248 on site?
-
Analyst company in-house procedures on site?
-
Has a site specific risk assessment been carried out? (Check Analysts PDA)
SECTION 3. STAGE 1 Site Setup and Assessment
-
Does the Analyst have all necessary equipment available
-
Has the Analyst Checked Transit Route
-
Has the Analyst inspected areas surrounding the - Enclosure,Van and Skip
-
Has the Analyst inspected Enclosure,Vision Panel placement or CCTV
-
Has the Analyst checked the DCU
-
Has the Analyst inspected contractors on site decontamination equipment
-
Has Analyst taken sufficient amount of photographs?
SECTION 4. STAGE 2 Visual Inspection
-
Is the analyst wearing app appropriate PPE/RPE?
-
Does the Analyst have all the necessary equipment ( Torch,Flexible Mirror,Screwdriver,Wet Wipes and Camera)
-
Has the Analyst witnessed the Site Supervisor conduct visual inspection?
-
Has the analysts inspected enclosure and air locks for debris
-
Has the Analyst checked surfaces of remaining plant/equipment in the Enclosure? (Use of Wet Wipes or Visual)
-
Has the analyst recorded findings to wether enclosure is dry?
-
Has the analyst inspected integrity of Enclosure?
-
Did the Analyst conduct the visual inspection for the recommended length of time? (Record Time)
- Compliant
- Non-Compliant
- N/A
-
Has Analyst taken sufficient amount of photographs?
-
When the analyst left the enclosure after Stage 2 have they carried out the correct decontamination procedure?
SECTION 5. EQUIPMENT SETUP AND CHECKS
-
Is the equipment in use calibrated, labelled and in good order?
-
Has the Analyst allowed the Air Sampling pump to stabilise?
-
Has the Analyst calibrated the flow meter using the master flowmeter
-
Has the Analyst checked the Flow rate to ensure the correct amount of air is being pulled through the pump
-
Has the Analyst started the calibrated timepiece to record pump run?
SECTION 6. CALIBRATED EQUIPMENT
-
Microscope (serviced) - Ref I.D
-
In Calibration?
-
Stage Micrometer - Ref I.D
-
In Calibration?
-
NPL test slide - Ref I.D
-
In Calibration?
-
High Flow Meter - Ref I.D
-
In Calibration?
-
Low Flow Meter - Ref I.D
-
In Calibration?
-
Tally Counters - Ref I.D
-
In Calibration?
-
Barometer - Ref I.D
-
In Calibration?
-
Thermometer - Ref I.D
-
In Calibration?
-
Timer - Ref I.D
-
In Calibration?
SECTION 7. NON CALIBRATED EQUIPMENT
-
Does all relevant equipment have a valid PAT test?
-
Does the analyst have an adequate number of high flow pumps to carry out suitable air monitoring?
-
Does the analyst have a low flow (personal) pump?
-
Does the analyst have and adequate number of cowl heads to carry out suitable air monitoring?
-
Does the analyst have an acetone vaporiser?
-
Does the analyst have a calculator?
-
Does the analyst have adequate supplies of slides, cover lips and filters?
-
Does the analyst have spare equipment in case of emergencies? (Fuses 3A/13A, bulbs, mask filters?)
-
Does the analyst have sufficient acetone/triacetin?
SECTION 8. STAGE 3 Air Sampling
-
Is the analyst wearing app appropriate PPE/RPE?
-
Has the Analyst confirmed NPU is capped and switched off?
-
Has the analyst removed all non essential work items from the enclosure?
-
Has the Analyst placed the correct number of pumps in relation to the enclosure size?
-
Has a disturbance been carried out using a brush? (1.5 minutes per pump up to a max of 5 mins)
-
Has the Analyst confirmed the full run time and the flow rate has been maintained?
-
When the analyst left the enclosure after Stage 3 have they carried out the correct decontamination procedure?
SECTION 9. STAGE 4 Enclosure Dismantling
-
Has the Analyst witnessed the Dismantling of the Enclosure.
-
Has the Analyst checked the area to ensure it is free of debris after dismantling?
-
Has the Analyst checked waste routes and areas surrounding skips and vans?
-
Has the Air Test Interface been complete in full on the PDA?
-
Has the Certificate of Reoccupation been filled out correctly (Calculations and all entries need to be checked)
-
Has the analyst took sufficient amount of photographs?
SECTION 10. DCU CLEARANCE
-
Has the Analyst checked the DCU to ensure contractor has cleaned prior to Air Clearance?
-
Has the Analyst carried out the correct number of sample to the DCU (<10m2 = 1 - >10m2 = 2)
-
Has the Analyst carried out the equipment checks as section 5
Q.C.
-
Have the correct version of forms been used? (Check version on document index)
Auditor Sign Off
-
Assessment/Audit Satisfactory
-
Analyst Approved?
-
Specify date of re-assessment
-
Note: if no then document details of discussion/training that has taken place.
-
Comments
-
Any comments, Is there requirements for the analyst to be retrained in any areas?
-
Auditor Signature
-
Analyst Signature