Title Page
-
Conducted on
-
Accredited contractor (company) name
-
Key personnel name
-
Development address
-
Development number (MCU/ROL/OPW)
-
Standard connection application number (WWS)
-
Standard connection category
- Water
- Sewer
-
Standard connection description
- Water service installation - same side of the road
- Water service installation - opposite side of the road with under road bore
- Water service disconnection
- Water fire hydrant installation
- Other (endorsed by Water and Waste)
-
Provide detail of 'other' endorsed connection
-
Size
- 20mm
- 25mm
- 40mm
-
Standard connection description
- Sewer house connection – junction on-lot
- Sewer house connection – junction off-lot
- Sewer house connection – disconnection on-lot
- Sewer house connection – disconnection off-lot
- Sewer house connection – manhole ‘x’ drop on-lot
- Sewer house connection – manhole ‘x’ drop off-lot
- Sewer house connection – re-lining
- Other (endorsed by Water and Waste)
-
Pipe material re-lined
-
Provide detail of 'other' endorsed connection
-
House connection size
- DN100
- DN150
-
Temporary connection
Pre-standard connection construction
Dilapidation Report
-
What is the condition of existing service provider assets in the vicinity of the standard connection works?
-
What is the condition of existing footpaths, trees, driveways, fences, verge etc in the vicinity of the standard connection works?
-
Are there any notifiable existing defects that may cause disputes in the future?
-
Provide photos of dilapidation report
Development approval
-
Link to PD online to access development approval: https://www.goldcoast.qld.gov.au/Planning-building/PD-Online
-
Are the standard connection works compliant with the development approval?
-
Has the matter been discussed, addressed and authorised with Water and Waste? Provide details by adding a note.
Sewer pre-CCTV condition report
-
Does the development approval require a CCTV assessment of the existing sewer service to reuse?
-
Provide link to pre CCTV
-
Was the existing sewer service pipe material asbestos cement?
-
Was the existing service fit to be relined?
-
Has a new sewer connection been provided?
-
Provide link to post CCTV of the completed reline
-
IPAM Compliance
-
Link to IPAM list: http://www.seqcode.com.au/products/
-
Are all fittings/fixtures/meters/pipe/joins/materials/products compliant with the IPAM?
-
Have the proposed products been approved in writing by Water and Waste?
-
Provide photos of all fittings/fixtures/meters/pipe/joins/materials/products
SEQ Code compliance
-
Link to SEQ Code: http://www.seqcode.com.au/standards/
-
Are the standard connection works compliant with the SEQ Code
-
Has the proposed design been approved in writing by Water and Waste?
Standard Connection Construction
Site safety
-
The standard connection works were carried out in accordance with all relevant safety requirements
-
The standard connection works were carried out in accordance with all relevant environmental safety requirements
-
The standard connection works were carried out in accordance with all relevant traffic/pedestrian safety requirements
-
Provide photos of site safety
Trench excavation
-
Provide photos of the excavation works including any benching/battering/shoring
WW sewer/water main
-
Provide photos of the excavated sewer and/or water main
Completed connection
-
Provide photos of the new standard connection prior to backfilling
Works area reinstatement
-
Has the area impacted by the standard connection works been reinstated to its former condition?
-
Provide photos of work area reinstatement
Post standard connection construction
New water meter/s
-
Is a new water meter being installed as part of the works?
-
Install date
-
Meter serial number
-
Meter size (mm)
-
Meter make
-
Meter reading on installation date (kL)
-
Supply type
- Water service installation - same side of the road
- Water service installation - opposite side of the road with under road bore
- Water service disconnection
- Water fire hydrant installation
- Other (endorsed by Water and Waste)
-
Location of meter
-
Upload photo of new water meter
-
Access online Water Meter Details Form on the City's website and submit - https://www.goldcoast.qld.gov.au/Services/Water-sewerage/Water-sewerage-connections/Water-meter-specifications
-
Upload photo of new water meters
Redundant water meter/s
-
Is a redundant water meter being removed?
-
Disconnection date
-
Meter serial number
-
Meter size (mm)
-
Meter reading on disconnection date (kL)
-
Supply type
- Water service installation - same side of the road
- Water service installation - opposite side of the road with under road bore
- Water service disconnection
- Water fire hydrant installation
- Other (endorsed by Water and Waste)
-
Location of meter
-
Upload photo of redundant water meter
-
Has provision been made with the Water and Waste Inspector to retrieve the redundant water meter?
-
Access online Water Meter Details Form on the City's website and submit - https://www.goldcoast.qld.gov.au/Services/Water-sewerage/Water-sewerage-connections/Water-meter-specifications
-
Upload photo of redundant water meters
-
Has provision been made with the Water and Waste Inspector to retrieve the redundant water meters?
Standard connection as-constructed information
-
Link to GIS: https://www.arcgis.com/apps/webappviewer/index.html?id=e22412158dfc4688a1deea1468aeb6a3&extent=17077737.3814,-3249378.7389,17078310.6592,-3249098.3702,102100
-
As-constructed requirements:
-
Has the standard connection as-constructed information been completed?
-
Upload a PDF copy of the as-constructed information
Licensed plumber details (if applicable)
-
All meter installations and/or disconnections must be performed by a licensed plumber
-
Licensed plumber name
-
QBCC licence number
-
QBCC licence class
-
QBCC licence conditions (if applicable)
-
QBCC licence expiry date
Sign off
-
Name & signature of key personnel
-
Once PCR complete, share inspection report link to Inspections@goldcoast.qld.gov.au