Information

The purpose of the 'black start' test is to ensure The Royal Melbourne Hospital city campus automatically changes-over to emergency power and maintains the essential hospital load on emergency generators, whilst the cogeneration operators start (both turbines) and switch the campus to 'island mode' (main grid isolation) powered by cogeneration. Note the cogeneration plant only covers buildings powered from substation A, B, D, & E. Substation C - WEHI / PMC / CSB / Anatomical Path are not covered

  • Sequence:

    * Citipower > disconnects incomer No1 & No2 - (UPS areas are unaffected)
    * Emergency generators > start & pick up the essential load
    * Cogeneration plant > start turbine No1 ring-main one closed on load > start turbine No2 ring-main two close on load > 'island mode' > synchronize with grid
    * Emergency generators > shutdown into standby mode
    * Cogeneration plant > steam pressure returns to 850Kpa
    * Engineering > reset any tripped plant / equipment

  • Site

  • Prepared on

  • Approval to and date established with cogeneration operator & Citipower operator

  • Works notification to be sent to all city campus staff & partner groups - 1 week prior & the day before the test date

  • Prepared by

Key Contact Information - Name & Contact number

  • Facilities Manager - Control

  • Engineering Manager - Control

  • Plant Engineer

  • Gencare Operator

  • Cogeneration plant operator

  • RWH Facility Operator

  • Information Technology

  • RMH Bed Manager.

  • RWH Bed Manager.

TEST CANNOT COMMENCE UNTIL APPROVAL IS GIVEN FROM RMH BED MANAGER & RWH AFTER-HOURS COORDINATOR

  • Date & Time of test

Sequence of events

  • Approval to proceed - RMH

  • Approval to proceed - RWH

  • Switchboard > Public Address announcement - 'Planned code yellow site power test commencing'

Operation of UPS & emergency generators

  • Citipower > Disconnect incomer No1 & No2

  • Engineering > UPS functioning (ED / ICU / Theatre / Cardiology - 2W & 2B / Infectious diseases - 9E)

  • Engineering > Generators Start - No1, No2, No3, & No4?

  • Emergency generators start?

  • All loads transferred automatically?

  • Emergency generators - Holding load

  • Confirm hospital operations on emergency power - RMH?

  • Confirm hospital operations on emergency power - RWH?

Operation of cogeneration plant

  • Transfield > Turbine No1 - Start sequence commence

  • Transfield > Turbine No1 - Online & maintaining load?

  • Start up sequence successful?

  • Engineering > Confirm HV ring No1 holding load & auto BUS TIE rings

  • Transfield > Turbine No2 - Start sequence commence

  • Transfield > Turbine No2 - Online & maintaining load?

  • Start up sequence successful?

  • Engineering > Confirm HV ring No2 holding load & generators on cool down off load

  • Citipower > Close mains incomers No1 & No2 back on to the mains grid supply

  • RMH > Confirm hospital status on mains power?

  • RWH > Confirm hospital status on mains power?

  • Switchboard > Public Address announcement - 'Planned code yellow site power test completed'

  • Transfield > Confirm steam pressure at operating level 850Kpa

Plant Notes

  • Successful start of emergency generators?

  • Number of unsuccessful attempts to start?

  • Successful loading of essential equipment?

  • Emergency power capacity adequate for critical service delivery?

  • Successful start of cogeneration?

  • Number of unsuccessful attempts to start?

  • Successful transfer to island mode achieved?

  • Successful 'black start' test (test completed within one hour)?

  • All plant automatically reset?

  • NOTES

Contingency Plans

  • Essential services were maintained?

  • clinical services operated without impact?

  • BCMP checked as valid?

Signatures

  • Facilties Manager Signature

  • Engineering Operations Manager Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.