Title Page

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Plans and Required Documentation

  • SSMP is available on site

  • Construction Project Hazard log is available on-site and up-dated regularly.

  • Site induction forms have been completed for all personnel on site.

  • Copies of general construction induction (White / Green card) qualifications / Certifications and a valid RIW card as specified in the network rules and network procedures certification standards are available on site.

  • Emergency procedures are available on site.

  • Site safety rules are displayed on site.

  • Site personnel contact details are displayed on site.

  • Drug and alcohol Policy are displayed on site.

  • External site signs identify Principle Contractor and emergency contact details.

  • Licences, Permits, authorities and qualifications are available at the time of inspection.<br><br>Hot Works Possession Asbestos Removal <br><br>Confined Spaces Dangerous Goods Storage Other (Describe)<br><br>Electrical Work Demolition

Public Interfaces

  • Public Areas are clean and tidy.

  • Interfaces with public areas are secured.

  • Access is restricted & appropriate signage is available to prevent entry.

  • Pedestrian access around site is well managed.

  • Temporary fencing around site is secured.

Inductions and Briefings

  • All staff have been inducted onto site.

  • A site walk has been conducted by the site supervisor / or person completing the Pre-Work briefing.

  • Pre-Work Briefing has been has been undertaken by the site supervisors.

  • Site and work tasks are adequately supervised.

SWMS

  • SWMS are provided for all high risk construction activities that are being undertaken on site.

  • SWMS have been reviewed and are site specific.

  • SWMS were developed in consultation with employees.

  • Work at the site is undertaken in accordance with the SWMS.

  • SWMS have been signed by those undertaking the works.

PPE

  • All workers on site (Including Supervisors) wear high visibility vests (Orange in rail corridor)

  • Helmets / Hardhats are being worn.

  • Steel-capped ankle high lace-up boots are being worn.

  • Australian Standards eye protection is being worn.

  • Hearing protection is being worn

  • Skin cancer protection is available

  • Respiratory protection is being worn were required.

  • Other protective equipment is being used as per SWMS.

Fire

  • A fire warden is available on site

  • A list of fire wardens is displayed on site.

  • Adequate fire Extinguisher(s) are available on site.

  • Location, accessibility and signage for fire extinguisher(s) is adequate.

Incidents

  • Incident forms are available on site.

  • Incident investigation reports are completed for any incidents that have occurred on site.

First Aid

  • A qualified first aider is available on site.

  • A list of first aiders is displayed on site.

  • First aid room or stations and first aid box are clean, tidy, labelled and adequately stocked and inspection forms are available.

Amenities

  • Adequate facilities and amenities are provided.

Work areas

  • Work areas are clean and tidy, clear of trip and slip hazards and exits are clear from obstructions.

  • Storage areas are secured, including dangerous goods and hazardous materials and have safety Data Sheets (SDS).

  • Penetrations are sign posted and guarded.

  • Hazardous material registration is available on site for demolition or refurbishment work.

  • Asbestos or lead paint removal work plans are available on site(N.B for Major Works)

  • Demarcated exclusion zones with signage is in place.

  • Correct PPE is being worn.

  • Decontamination facilities are available.

  • Arrangement for safe disposal and transport to waste facilities are in place.

  • Chemical containers are labelled and stored in bunded areas or pallets.

  • Gas bottles are stored upright and secure.

  • Flammable gas bottles are stored in ventilated areas separated from ignition sources.

Lighting

  • Adequate lighting (Walkways, Site-shed, Storage.

Worksite protection

  • Worksite protection plan is on site and current <br>NOTE<br><br>Implementing protection in the Danger Zone must be completed by a protection officer.

Traffic Management

  • Onsite traffic management plan is in place

Electrical

  • RCDs (Earth Leakage Protection) are in use for all leads.

  • All portable electrical tools, leads and equipment are in good condition and are tested and tagged

Safe Approach Distances

  • Safe approach distances / Electrical permit are maintained

  • Arrangements are in place to prevent encroachment.

  • Mobile plant operator(s) and safety observer hold 'Safe Electrical Approach for Crane and Plant' Competency.

Plant

  • Plant and equipment register (Including electrical) is available.

  • Log books and inspection records are available for all plant.

  • Plant operator has the required qualifications (E.g Current High Risk Licence).

  • Operational flashing lights, reversing siren is available and in good working order for all mobile plant.

  • Daily Pre-Start checks have been completed for all plant in use.

  • Exclusion zones are in place around mobile plant.

Hot works

  • Hot works permit is completed.

  • Work and requirements comply with permit.

  • Cylinders stored fixed working upright

  • Grinding / Welding is protected ( Face shield, Fire Extinguisher, Spark screen and correct PPE

Working & Heights

  • Fall prevention is in place with a rescue plan.

  • Fall prevention System (E.g Harnesses, Lanyard, Static line) is in place and inspected as required by legislation.

  • Areas below personnel working at heights is barricaded.

Ladders

  • Ladders are used for access only.

  • Ladder extends at least 1m above landings at an angle of 1:4 and the top and bottom are lashed.

  • Ladders are non-metallic in the rail corridor.

Excavation

  • Excavation plan has been approved and is being followed.

  • Asset owners are consulted when excavating in the vicinity of services with DYBD and areas are marked.

  • No mechanical excavation is being undertaken within 2m of known services.

  • Excavations are Benched, Battered, Shored and edge protection is in place.

Scaffolding

  • Scaffolding is certified with regular inspection and Scaff Tag in place on all entry points to the scaffold

  • Scaffold is complete with handrails, Kick-boards and internal/External Access.

  • Solid foundation under scaffolding and secured against vandalism.

  • Area around scaffold is barricaded.

  • Wheels are locked on mobile scaffold.

Demolition

  • Demolition plans are in place and qualified supervisor is on site.

Formwork

  • Engineers formwork certificate is available(As Applicable) and complies with AS3610.

  • Sole plates are in use.

  • Secure access is supplied.

  • Area barricaded during erection of formwork

Confined Space

  • Confined space permit is in place and correctly filled in.

  • All personnel hold Confined Space Certification and training.

  • Confined space watcher permit is in place with Gas reading sign on/off by all.

  • Rescue plan is in place.

Environmental

  • Noise issues are managed.

  • Dust is minimised.

  • Water run-off is controlled.

  • Sedimentation barriers are in place Spill kits are available on site and are stocked correctly.

Other Information or issues Found

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.