Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Plans and Required Documentation
-
SSMP is available on site
-
Construction Project Hazard log is available on-site and up-dated regularly.
-
Site induction forms have been completed for all personnel on site.
-
Copies of general construction induction (White / Green card) qualifications / Certifications and a valid RIW card as specified in the network rules and network procedures certification standards are available on site.
-
Emergency procedures are available on site.
-
Site safety rules are displayed on site.
-
Site personnel contact details are displayed on site.
-
Drug and alcohol Policy are displayed on site.
-
External site signs identify Principle Contractor and emergency contact details.
-
Licences, Permits, authorities and qualifications are available at the time of inspection.<br><br>Hot Works Possession Asbestos Removal <br><br>Confined Spaces Dangerous Goods Storage Other (Describe)<br><br>Electrical Work Demolition
Public Interfaces
-
Public Areas are clean and tidy.
-
Interfaces with public areas are secured.
-
Access is restricted & appropriate signage is available to prevent entry.
-
Pedestrian access around site is well managed.
-
Temporary fencing around site is secured.
Inductions and Briefings
-
All staff have been inducted onto site.
-
A site walk has been conducted by the site supervisor / or person completing the Pre-Work briefing.
-
Pre-Work Briefing has been has been undertaken by the site supervisors.
-
Site and work tasks are adequately supervised.
SWMS
-
SWMS are provided for all high risk construction activities that are being undertaken on site.
-
SWMS have been reviewed and are site specific.
-
SWMS were developed in consultation with employees.
-
Work at the site is undertaken in accordance with the SWMS.
-
SWMS have been signed by those undertaking the works.
PPE
-
All workers on site (Including Supervisors) wear high visibility vests (Orange in rail corridor)
-
Helmets / Hardhats are being worn.
-
Steel-capped ankle high lace-up boots are being worn.
-
Australian Standards eye protection is being worn.
-
Hearing protection is being worn
-
Skin cancer protection is available
-
Respiratory protection is being worn were required.
-
Other protective equipment is being used as per SWMS.
Fire
-
A fire warden is available on site
-
A list of fire wardens is displayed on site.
-
Adequate fire Extinguisher(s) are available on site.
-
Location, accessibility and signage for fire extinguisher(s) is adequate.
Incidents
-
Incident forms are available on site.
-
Incident investigation reports are completed for any incidents that have occurred on site.
First Aid
-
A qualified first aider is available on site.
-
A list of first aiders is displayed on site.
-
First aid room or stations and first aid box are clean, tidy, labelled and adequately stocked and inspection forms are available.
Amenities
-
Adequate facilities and amenities are provided.
Work areas
-
Work areas are clean and tidy, clear of trip and slip hazards and exits are clear from obstructions.
-
Storage areas are secured, including dangerous goods and hazardous materials and have safety Data Sheets (SDS).
-
Penetrations are sign posted and guarded.
-
Hazardous material registration is available on site for demolition or refurbishment work.
-
Asbestos or lead paint removal work plans are available on site(N.B for Major Works)
-
Demarcated exclusion zones with signage is in place.
-
Correct PPE is being worn.
-
Decontamination facilities are available.
-
Arrangement for safe disposal and transport to waste facilities are in place.
-
Chemical containers are labelled and stored in bunded areas or pallets.
-
Gas bottles are stored upright and secure.
-
Flammable gas bottles are stored in ventilated areas separated from ignition sources.
Lighting
-
Adequate lighting (Walkways, Site-shed, Storage.
Worksite protection
-
Worksite protection plan is on site and current <br>NOTE<br><br>Implementing protection in the Danger Zone must be completed by a protection officer.
Traffic Management
-
Onsite traffic management plan is in place
Electrical
-
RCDs (Earth Leakage Protection) are in use for all leads.
-
All portable electrical tools, leads and equipment are in good condition and are tested and tagged
Safe Approach Distances
-
Safe approach distances / Electrical permit are maintained
-
Arrangements are in place to prevent encroachment.
-
Mobile plant operator(s) and safety observer hold 'Safe Electrical Approach for Crane and Plant' Competency.
Plant
-
Plant and equipment register (Including electrical) is available.
-
Log books and inspection records are available for all plant.
-
Plant operator has the required qualifications (E.g Current High Risk Licence).
-
Operational flashing lights, reversing siren is available and in good working order for all mobile plant.
-
Daily Pre-Start checks have been completed for all plant in use.
-
Exclusion zones are in place around mobile plant.
Hot works
-
Hot works permit is completed.
-
Work and requirements comply with permit.
-
Cylinders stored fixed working upright
-
Grinding / Welding is protected ( Face shield, Fire Extinguisher, Spark screen and correct PPE
Working & Heights
-
Fall prevention is in place with a rescue plan.
-
Fall prevention System (E.g Harnesses, Lanyard, Static line) is in place and inspected as required by legislation.
-
Areas below personnel working at heights is barricaded.
Ladders
-
Ladders are used for access only.
-
Ladder extends at least 1m above landings at an angle of 1:4 and the top and bottom are lashed.
-
Ladders are non-metallic in the rail corridor.
Excavation
-
Excavation plan has been approved and is being followed.
-
Asset owners are consulted when excavating in the vicinity of services with DYBD and areas are marked.
-
No mechanical excavation is being undertaken within 2m of known services.
-
Excavations are Benched, Battered, Shored and edge protection is in place.
Scaffolding
-
Scaffolding is certified with regular inspection and Scaff Tag in place on all entry points to the scaffold
-
Scaffold is complete with handrails, Kick-boards and internal/External Access.
-
Solid foundation under scaffolding and secured against vandalism.
-
Area around scaffold is barricaded.
-
Wheels are locked on mobile scaffold.
Demolition
-
Demolition plans are in place and qualified supervisor is on site.
Formwork
-
Engineers formwork certificate is available(As Applicable) and complies with AS3610.
-
Sole plates are in use.
-
Secure access is supplied.
-
Area barricaded during erection of formwork
Confined Space
-
Confined space permit is in place and correctly filled in.
-
All personnel hold Confined Space Certification and training.
-
Confined space watcher permit is in place with Gas reading sign on/off by all.
-
Rescue plan is in place.
Environmental
-
Noise issues are managed.
-
Dust is minimised.
-
Water run-off is controlled.
-
Sedimentation barriers are in place Spill kits are available on site and are stocked correctly.