Information
-
Job Number
-
Site Address
-
Conducted on
-
Prepared by
-
Location
-
Sales Consultant
THIS SECTION TO BE COMPETED BY SUPERVISOR
-
Will delivery and work vehicles be able to drive onto the building platform in all weather conditions
-
Will a standard width and length gravel drive be adequate ?
-
Is there adequate access and storage area for building materials, rubbish cages and toilet within the boundary (Not on nature strip)
-
Are the existing footpaths, driveway and cross-over free of any cracks or damage ?
ELECTRICITY & WATER
-
ASSET NUMBER OF PILLAR / PIT / POLE:
-
Please specify if Underground or Overhead power?
-
If overhead, will the height/position of power lines pose a risk and affect deliveries and Construction activities (eg Frame delivery, Crane or Concrete Boom Pump set-up / operation) ? - if Yes, Warning Notes to be included on all Orders to Trades and Suppliers - Signs, Warning Flags and / or Tiger Tails may be required
-
If power is Underground, specify Pit or Pillar supply ?
-
Is water service easily located (location viewed from street)
-
Please lift lid and take photo of meter
-
Please lift lid and take photo of meter
RETAINING WALLS
FRONT SIDE RETAINING WALL
-
Are there any retaining walls on common boundaries or neighbouring blocks or across the building zones? Select what material are they made from
-
- Masonry
- Rock Walls
- Linkblocks
- Concrete Sleepers
- Timber Sleepers
- Blockwork
BACK SIDE RETAINING WALL
-
Are there any retaining walls on common boundaries or neighbouring blocks or across the building zones? And of what material are they made from
-
- Masonry
- Rock Walls
- Linkblocks
- Concrete Sleepers
- Timber Sleepers
- Blockwork
RIGHT SIDE RETAINING WALL
-
Are there any retaining walls on common boundaries or neighbouring blocks or across the building zones? And of what material are they made from
-
- Masonry
- Rock Walls
- Linkblocks
- Concrete Sleepers
- Timber Sleepers
- Blockwork
LEFT SIDE RETAINING WALL
-
Are there any retaining walls on common boundaries or neighbouring blocks or across the building zones? And of what material are they made from
-
- Masonry
- Rock Walls
- Linkblocks
- Concrete Sleepers
- Timber Sleepers
- Blockwork
CRANE HIRE - is a crane required for thew following ?
-
Trusses
-
Frame
-
Plaster
-
Bricks
-
Other
MISCELLANEOUS
-
Is additional edge protection required ( falls from retaining walls or work platforms ) ?
-
Will Earthworks impact on neighbouring properties? If yes please provide comments below
-
Are there any trees within the building platform
-
Are there any trees on common boundaries that may be affected by Excavation and filling?
-
Is there any visible rock onsite? Or adjoining site?
-
Is there a creek or waterway nearby ?
-
What type of waterway ? - extra Sediment controls may be required
-
Is the site within a flood affected area (AHD)
-
Must the Underslab fill delivered by rigid truck? If it is, Orders must include a note that Rigid Trucks only to deliver Underslab fill
-
Is this site redeveloped or in an older area which may require identification survey
-
Do you foresee any building problems eg steepness of site, access problems etc
-
Is there any evidence of asbestos sheeting on this site ( existing house, older area etc) - if so, an Asbestos Clearance Certificate will be required
-
Have you taken site photos please send to head office
-
Should this job proceed
SITE AND PUBLIC PROTECTION RISK ASSESSMENT
-
Is there available safe parking for trades or delivery vehicles at the site ?
-
Will split deliveries be required due to access, storage or traffic issues ?
-
Does this site require temporary 1.8m chain wire fence around building site ? (As per Risk Assessment - proximity of occupied houses, schools, child care, playgrounds, shops etc)
-
Is the access and storage area for building materials suitable .If No, consider part deliveries & include additional site cleans.
-
Are there any traffic issues with this site (speed, volume, road width, bends, crests, schools etc) that will require a Traffic Management Plan / Controllers ? Quotes to be obtained and Council Fees assessed after consultation with Construction Personnel
-
Are there issues with installing normal scaffold (site size and access restrictions) ? Will scaffold need screening due to proximity of boundaries and footpaths
-
Is a work platform for carpenters / bricklayers required due to Drop-edge-beams or retaining walls?
-
Are extra site cleans required due to site area restrictions or Council DA requirements ?
-
Do we require extra material handling payment for Trades due to block restrictions ?