Information

  • Job Number

  • Site Address

  • Conducted on

  • Prepared by

  • Location
  • Sales Consultant

THIS SECTION TO BE COMPETED BY SUPERVISOR

  • Will delivery and work vehicles be able to drive onto the building platform in all weather conditions

  • Will a standard width and length gravel drive be adequate ?

  • Is there adequate access and storage area for building materials, rubbish cages and toilet within the boundary (Not on nature strip)

  • Are the existing footpaths, driveway and cross-over free of any cracks or damage ?

ELECTRICITY & WATER

  • ASSET NUMBER OF PILLAR / PIT / POLE:

  • Please specify if Underground or Overhead power?

  • If overhead, will the height/position of power lines pose a risk and affect deliveries and Construction activities (eg Frame delivery, Crane or Concrete Boom Pump set-up / operation) ? - if Yes, Warning Notes to be included on all Orders to Trades and Suppliers - Signs, Warning Flags and / or Tiger Tails may be required

  • If power is Underground, specify Pit or Pillar supply ?

  • Is water service easily located (location viewed from street)

  • Please lift lid and take photo of meter

  • Please lift lid and take photo of meter

RETAINING WALLS

FRONT SIDE RETAINING WALL

  • Are there any retaining walls on common boundaries or neighbouring blocks or across the building zones? Select what material are they made from

BACK SIDE RETAINING WALL

  • Are there any retaining walls on common boundaries or neighbouring blocks or across the building zones? And of what material are they made from

RIGHT SIDE RETAINING WALL

  • Are there any retaining walls on common boundaries or neighbouring blocks or across the building zones? And of what material are they made from

LEFT SIDE RETAINING WALL

  • Are there any retaining walls on common boundaries or neighbouring blocks or across the building zones? And of what material are they made from

CRANE HIRE - is a crane required for thew following ?

  • Trusses

  • Frame

  • Plaster

  • Bricks

  • Other

MISCELLANEOUS

  • Is additional edge protection required ( falls from retaining walls or work platforms ) ?

  • Will Earthworks impact on neighbouring properties? If yes please provide comments below

  • Are there any trees within the building platform

  • Are there any trees on common boundaries that may be affected by Excavation and filling?

  • Is there any visible rock onsite? Or adjoining site?

  • Is there a creek or waterway nearby ?

  • What type of waterway ? - extra Sediment controls may be required

  • Is the site within a flood affected area (AHD)

  • Must the Underslab fill delivered by rigid truck? If it is, Orders must include a note that Rigid Trucks only to deliver Underslab fill

  • Is this site redeveloped or in an older area which may require identification survey

  • Do you foresee any building problems eg steepness of site, access problems etc

  • Is there any evidence of asbestos sheeting on this site ( existing house, older area etc) - if so, an Asbestos Clearance Certificate will be required

  • Have you taken site photos please send to head office

  • Should this job proceed

SITE AND PUBLIC PROTECTION RISK ASSESSMENT

  • Is there available safe parking for trades or delivery vehicles at the site ?

  • Will split deliveries be required due to access, storage or traffic issues ?

  • Does this site require temporary 1.8m chain wire fence around building site ? (As per Risk Assessment - proximity of occupied houses, schools, child care, playgrounds, shops etc)

  • Is the access and storage area for building materials suitable .If No, consider part deliveries & include additional site cleans.

  • Are there any traffic issues with this site (speed, volume, road width, bends, crests, schools etc) that will require a Traffic Management Plan / Controllers ? Quotes to be obtained and Council Fees assessed after consultation with Construction Personnel

  • Are there issues with installing normal scaffold (site size and access restrictions) ? Will scaffold need screening due to proximity of boundaries and footpaths

  • Is a work platform for carpenters / bricklayers required due to Drop-edge-beams or retaining walls?

  • Are extra site cleans required due to site area restrictions or Council DA requirements ?

  • Do we require extra material handling payment for Trades due to block restrictions ?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.