Title Page

  • Site Visit Date

  • Prepared by

  • Report Reference

  • PAS Job Reference

  • Property Address
  • Property Type

  • Number of Storeys

  • Property Build

  • Type of Floor Construction

  • Property Age

  • Project Status

Site Specific Risk Assessment - Hazards Specific to this Task

  • Do you require a Site Specific Risk Assessment for this Property?

01 of 10 - Vehicle movements / parking / access to property

  • Who could be harmed?

  • Level of Risk?

  • Controls?

02 of 10 - Restricted access / tripping hazards

  • Who could be harmed?

  • Level of Risk?

  • Controls?

03 of 10 - Falls from height – Entering / exiting loft or underfloor space

  • Who could be harmed?

  • Level of Risk?

  • Controls?

04 of 10 - Loft spaces with poor or limited lighting conditions, hidden hazards/obstacles

  • Who could be harmed?

  • Level of Risk?

  • Controls?

05 of 10 - Slips trips and falls

  • Who Could be harmed?

  • Level of Risk?

  • Controls?

06 of 10 - Abusive / Aggressive tenants

  • Who could be harmed?

  • Level of Risk?

  • Controls?

07 of 10 - Needlestick and sharp object injuries

  • Who could be harmed?

  • Level of Risk?

  • Controls?

08 of 10 - Manual handling

  • Who could be harmed?

  • Level of Risk?

  • Controls?

09 of 10 - Dust, mould or dampness

  • Who could be harmed?

  • Level of Risk?

  • Controls?

10 of 10 - Overall Level of Risk

  • With all controls in place, what is the overall level of residual risk?

  • Have you reported this back to the head office and canceled the visit?

  • Have you reported this back to the head office and canceled the visit?

  • I confirm that all controls required have been put into place and the residual level of risk is acceptable.

Property Condition - Please add photographs of All areas

  • Condition of External Walls

  • Condition of Damp Prof Course (DPC)

  • Condition of Roof - where visible from the ground

  • Condition of Windows and Doors

  • Evidence of external excessive dampness

  • Does this require rectification before the installation can continue?

  • Evidence of degraded mortar beds

  • Does this require rectifying before the install can continue?

  • Condition internal walls

  • Is there penetrative and/or rising damp present at the property?

  • Does this require remedial action before the installation can continue?

  • Why is remedial action not required?

  • Is there evidence of condensation and/or mould growth in the dwelling?

  • Is the cause of the mould / condensation known?

  • Does this require rectification before the installation can continue?

  • Why is rectification not required?

  • Are there any other defects that must be considered before the installation can progress?

  • Please provide details and photographic evidence.

Ventilation - Please add photographs of all areas

  • Are ventilation upgrades required?

  • Status of ventilation upgrades are the time of visit?

  • Has the background ventilation been assessed (pre-installation) in accordance with the IAA's guidance?

  • Is the measured Air Change Rate>1.0 ACH for the full property and if required, 1.5 ACH for each bedroom?

  • Is extract ventilation in all wet rooms?

  • Extract ventilation type?

  • Are upgrades planned to be installed?

  • Is purge ventilation available in all rooms?

  • Are upgrades planned to be installed?

  • Is background ventilation available in all rooms?

  • Are upgrades planned to be installed?

  • Are all internal doors equipped with a 10mm undercut? (20mm for uncovered floors)

  • Are upgrades planned to be installed?

Cavity Wall Insulation (CWI)

  • Is Cavity Wall Insulation being installed?

  • Does the current condition of the property suggest it was suitable for CWI to be installed?

  • What is the progress of the installation?

  • Has the cavity been extracted and refilled?

  • Has 100% of the install been completed where possible?

  • Add an explanation as to why 100% of the installation has not been achieved

  • Is the evidence of the drilling pattern on all walls appropriate for the product?

  • All injection holes filled and dyed if required?

  • Are all vents safeguarded and any redundant vents sealed?

  • Have any combustion core vents been fitted where required? (Required for open flue appliance)

  • Is there any evidence of insulation spillage into air bricks or meter boxes?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Loft Insulation (LI)

  • Is Loft Insulation being installed?

  • Does the current condition of the property suggest it was suitable for loft insulation to be installed?

  • What is the progress of the installation?

  • Is/has 100% of the installation completed where possible?

  • Add an explanation as to why 100% of the installation has not been achieved

  • Condition of loft timbers?

  • Please provide further details

  • Loft Insulation overall thickness?

  • Is the insulation thickness consistent throughout?

  • Has the insulation been cross laid?

  • Have any downlighters installed in the ceiling below been covered with loft caps?

  • Have all electric cables been lifted above insulation?

  • Is the loft hatch insulated and draught-proofed?

  • Is there evidence of unobscured loft ventilation, existing or additional?

  • Are any water pipes or water tank correctly insulated?

  • is loft ventilation ducting insulated?

  • Are there any skeilings?

  • Have the skeilings been correctly insulated?

  • Do the skeilings have unobscured ventilation - ventilation tray installed or insulation applied below the ceiling?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Underfloor Insulation (UFI)

  • Is Underfloor Insulation being installed?

  • Does the current condition of the property suggest it was suitable for UFI to be installed?

  • What is the progress of the installation?

  • Are there airbricks on opposing walls to permit crossflow ventilation in the underfloor void?

  • Is there an area of the floor solid that would result in "dead zones" in the air flow in the underfloor void?

  • Is the underfloor ventilation being upgraded in accordance with Building regulations Approved Document C, 2010, Section 4.14

  • Have moisture readings been taken from the joists?

  • What are the moisture readings?

  • When insulated is the remaining clearance below the insulation greater than or equal to 150mm?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

External Wall Insulation (EWI)

  • Is External Wall Insulation being installed?

  • Does the current condition of the property suggest it was suitable for EWI to be installed?

  • What is the progress of the installation?

  • Is 100% of all elevations being insulated?

  • Are the omitted areas being insulated by hybrid insulation, CWI or IWI?

  • Will the insulation interfere with loft ventilation?

  • Are loft ventilation upgrades completed or planned?

  • Is the area below the DPC being insulated following INCA/SWIGA Guidance?

  • Are thermal bridge calculations being provided for the thermal bridge as a result of lack of insulation below the thermal bridge below the DPC?

  • Is there sufficient roof overhang on all elevations to allow for 40mm between the roof structure and installed EWI system?

  • Which sections/elevations of the roof do not have sufficient overhang?

  • Where there is insufficient overhang, is the roofline being extended?

  • Is there a canopy above any of the doors?

  • Location of canopy?

  • Is the canopy being temporarily removed for the installation?

  • Is a thermal bridge calculation being provided for the canopy?

  • Are all window and door reveals, headers and sills being insulated?

  • Is there a 40mm overhang from all window sills to the EWI system planned?

  • Is there an external electricity meter box?

  • Is this being insulated, either behind the meter box or with an insulated cover?

  • Is a thermal bridge calculation being provided for the meter box?

  • Is there an external gas meter box?

  • Is this being removed and insulation applied behind?

  • Is a thermal bridge calculation being provided for the meter box?

  • Are there any unheated structures attached to the property (e.g. porch, conservatory, garage or lean-to?

  • Is the internal heat loss wall inside the structure being insulated?

  • Are there any other potential thermal bridges created by the insulation?

  • List the areas?

  • Please detail the "Other" thermal bridge

  • Are calculations being provided for all thermal bridges listed

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Internal Wall Insulation (IWI)

  • Is Internal Wall Insulation being installed?

  • Does the current condition of the property suggest it was suitable for IWI to be installed?

  • What is the progress of the installation?

  • What type of insulation is being installed?

  • Are all window and door reveals, headers and sills being insulated

  • Are there any obstructions that may prevent insulation being installed on all heat-loss walls? e.g. cupboards, fixtures etc.

Wet rooms

  • Are 100% of the property's heat loss wall being insulated?

  • Is the limitation confined to only wet rooms?

  • Can wet rooms be equipped with continuous extract ventilation and heated to 18oC?

Internal Chimneys

  • Does the property have a chimney on the heat-loss wall?

  • Is the chimney unused, ventilated, and capped?

  • Is the chimney being insulated?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Room in Roof Insulation

  • Is Room in Roof Insulation being installed?

  • Does the current condition of the property suggest it was suitable for IWI to be installed?

  • What is the progress of the installation?

Are all elements of the rooms being insulated?

  • All slopes?

  • All stud Walls?

  • All flat Ceilings?

  • Gable Walls?

  • Party Walls?

  • Dormer windows - all areas?

  • Residual loft space?

  • Where residual areas have been insulated, has a fireproof access hatch been installed?

  • Have all window reveals, headers and sills been insulated?

  • Are there any wet rooms included in the RIRI insulation?

  • Is the room equipped with continuous extract and can be heated to 18oC?

  • Are there any chimney breasts in the treated rooms?

  • Is the chimney unused, ventilated, and capped?

  • Is the chimney being insulated?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Flat Roof Insulation

  • Is Flat Roof Insulation being installed?

  • Does the current condition of the property suggest it was suitable for Flat Roof Insulation to be installed?

  • What is the progress of the installation?

  • Is the insulation being applied creating a cold deck (insulation between rafters) or warm deck (insulation on top of roof)?

  • Does the roof have a cross-ventilated void of at least 50mm

  • Are there continuous ventilation openings along two opposite sides of not less than 25mm

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

New or Replacement Windows

  • Are New or Replacement Windows being installed?

  • What is the progress of the installation?

  • Window(s) installed at the position of the plaster line to minimise disturbance and damage to interior decoration?

  • Window(s) installation positioned to align with any insulation measures to reduce thermal bridges?

  • Are there any signs of condensation or mould post install?

  • Are all areas around the windows completely sealed (not gaps to allow air leakage)?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

New or Replacement Doors

  • Are New or Replacement Doors being installed?

  • What is the progress of the installation?

  • Door(s) installed at the position of the plaster line to minimise disturbance and damage to interior decorations?

  • Door(s) installation positioned to align with any insulation measures to reduce thermal bridges?

  • Has the new frame(s) bridged the damp proof course (DPC)?

  • Has the DPC been repaired to provide a continuous layer?

  • Are all areas around the door(s) completely sealed (not gaps to allow air leakage)?

  • Are there any signs of condensation or mould post install?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Park Home Insulation

  • Is Park Home Insulation being installed? (if No - continue to next page)

  • Does the current condition of the property suggest it was suitable for the proposed insulation measures to be installed?

  • What is the progress of the installation?

External Wall Insulation (EWI)

  • EWI being installed?

  • Are 100% of heat loss walls being treated?

  • Are there any areas of the roof that will not provide 40mm overhang from the roofline to the finished EWI system?

  • Is the roofline being extended?

  • Are all wall vents being extended and left unobstructed?

Loft Insulation

  • Is loft Insulation being installed?

  • Is 100% of the loft being insulated?

  • Is the insulation being cross laid?

  • Total insulation depth installed?

  • Is the insulation being laid with consistent thickness?

Underfloor Insulation (UFI)

  • Is the underfloor area being insulated?

  • Is 100% of the floor being insulated?

  • Are all floor vents left clear of insulation?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Replacement Gas Boiler / Central Heating

  • Is Replacement Gas Boiler / Central Heating being installed? (if No - continue to next page)

  • What is the progress of the installation?

  • Boiler Make and Model

  • Boiler capacity kW

  • Is the gas supply pipe the correct size (this should be 22mm for boilers <36kW and 28mm for boilers >=36kW)?

  • Record location and photograph of boiler installation

  • Record location and photograph of Heating controls

  • Record location and photograph of boiler flue

  • Is the flue located at least 300mm from an opening window, door or property boundary

  • Is the flue discharging into another closed space, such as a garage, or into a public alley way or shared access walkway between two houses?

  • Is the external condensate pipe fully insulated to avoid freezing?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Heating Controls

  • Are heating controls being installed? (if No - continue to next page)

  • What is the progress of the installation?

  • Type of heating controls installed?

  • Make and model of heating controls

  • Location(s) heating controls installed

  • Please add photographs of location(s)

  • Are the heating controls operating correctly?

  • How is this being rectified?

  • Has the occupant been given sufficient guidance on how to operate the controls correctly?

  • Is the installer planning to provide training upon installation completion?

  • Has the occupant been left with suitable operation manuals for the controls?

  • Will these be provided upon completion of the installation

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Energy Efficient Electric Storage Heaters (ESH)

  • Are Energy Efficient Electric Storage Heaters (ESH) being installed? (if No - continue to next page)

  • What is the progress of the installation?

  • Replacement Gas Boiler / Central Heating

  • Storage heater make and model

  • Number of rooms in property

  • Number of emitters installed

  • In rooms where emitters are not being installed - is top up heating available?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Solar PV

  • Is Solar PV being installed? (if No - continue to next page)

  • What is the progress of the installation?

  • Orientation of roofs where solar panels are installed?

  • Number of panels and total rated power?

  • If panels are installed on a flat roof sections, are these mounted on a frame so that the panels are tilted to an angle of approx 35 degrees from the horizontal?

  • Are all exposed cable runs secured and tidy?

  • Has the consumer unit been upgraded?

  • Location of invertors and isolator switch?

  • Please record and photograph "other" location.

  • Does the installation include battery storage?

  • Record and photograph location of battery storage

  • Are the solar panels installed at a distance less than 200mm from the roof edge and below the ridgeline?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Air Source Heat Pump (ASHP)

  • Is an Air Source Heat Pump being installed? (if No - continue to next page)

  • What is the progress of the installation?

  • Heat pump make and model?

  • Heat pump capacity?

  • Record and photograph heat pump installation location

  • Is the pump located at least 1m from the property boundary?

  • Is there sufficient free space around the heat pump (usually 150mm minimum to rear, and 300-500mm at sides. Always 1 metre clear space in front)?

  • Is the heat pump located adjacent to sleeping areas or on floors that can transmit vibration?

  • Record and photograph water tank, expansion vessels, and ancillary equipment.

  • Have radiators or pipework been upgraded? please photograph all relevant.

  • Has customer had the operation of the heat pump explained to them?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Ground Source Heat Pump (GSHP)

  • Is a Ground Source Heat Pump being installed? (if No - continue to next page)

  • What is the progress of the installation?

  • Heat pump make and model?

  • Heat pump capacity?

  • Record and photograph heat pump installation location

  • Record and photograph water tank, expansion vessels, and ancillary equipment.

  • Have radiators or pipework been upgraded? please photograph all relevant.

  • Has customer had the operation of the heat pump explained to them?

  • Is the installation compliant with PAS2035?

  • Are there any observations from the Coordinator's perspective relevant to the installation?

Inspection Signoff

  • Do you have any further comments or observations that should be noted?

  • Please record observations along with any relevant photographic evidence

  • Report completed by (please add signature)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.