Title Page

  • Site conducted

  • Document No. GYP 005 v1.0

  • Client / Site

  • Audit Title

  • Block/Elevation/Gridlines

  • Conducted on

  • Prepared by

  • Site Address
  • Full extent of sheathing layer required areas determined prior to installation

  • Ensure correct number and thickness of Sheathing Boards is installed as specified.

  • Correct Screw used to fix Sheathing Board on to SFS.

  • Vertical fixing centres along stud frame & horizontal fixing centres are located at every vertical stud positions.

  • The sheathing board is not fixed to the SFS head track, the top most sheathing board screws are located at least 20-25mm from bottom edge of head track flange to meet deflection requirements.

  • A gap of 3-6mm must be observed.

  • All board to board joints taped and sealed using recommended tape see adjacent .

  • When the Sheathing Board over sails the edge of slab, at least 20-25mm deflection gap maintained between the boards on levels above & below.

  • All Structural deflection gaps (20-25mm) between sheathing board layers sealed using fire rated intumescent flexible Sealant as recommended by the Board Manufacturer .

  • Vent openings are formed on sheathing board layer at correct locations and sizes as marked by the Main Contractor onsite.

  • Select date

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.