Information

  • Document No.

  • Client

  • Site

  • Principal Contractor

  • Site Manager

  • Conducted on

  • Prepared by

  • Location

Introduction

  • This inspection/audit has been undertaken by CPM safety. The purpose of the inspection/audit is to ensure the Principal Contractors compliance with the Health and Safety at Work etc. Act 1974 and any relevant subordinate legislation, including but not restricted to, the Management of Health and Safety at Work Regulations 1999, the Construction (Design & Management) Regulations 2007, the Control of Asbestos Regulations 2012 and the Working at Heights Regulations 2005.

    The report aims to identify areas where the Principal Contractor needs to improve to meet the requirements of all relevant health and safety regulations and industry best practice procedures.

    The 'corrective actions' section details the remedial actions graded as priority 'High', 'Medium' and 'Low'.

    'High' rated actions should be completed as soon as is reasonably practicable, as these could potentially lead to serious injury and would likely lead to an enforcement officer issuing a 'Prohibition' or 'Improvement' notice against the site.

    'Medium' rated actions should be completed with a reasonable timeframe (normally before the next inspection/audit)

    'Low' rated actions are not compulsory but the contractor would benefit from addressing these points for continual improvement of health and safety standards.

Conclusion

  • Documentaion

1.0 - Documentation

  • Is the project notifiable under CDM Regs 2015?

  • Is the F10 on display?

  • Is there a copy of the company's Employers Liability insurance policy on display?

  • Enter run-out date of EL insurance.

  • Is there a copy of the company's health and safety policy on site?

  • Has the policy been signed by the senior person within the company?

  • Has the policy been reviewed within the last 12 months?

  • Does the policy accurately reflect the company operations?

2.0 - Site Specific Documentation

  • Are risk assessments available for all hazards with a potential significant risk?

  • Have Method Statements/Safe Systems of Work been prepared for works with a potential significant risk?

  • Do the risk assessments and Method Statements/Safe Systems of Work adequately control the risks?

  • Has the Principal/Main Contractor identified hazardous substances in use on site?

  • Is there a register of the hazardous substances in use?

3.0 - Site Manager

  • Does the site manager hold a relevant Site Manager qualification? e.g. SMSTS

  • Is there an appointed site supervisor(s)?

  • Do site supervisors hold a relevant supervisory qualification? e.g. SSSTS

4.0 - Fire & Emergency Precautions

  • Is a fire/emergency plan available for the site?

  • Is there a suitable system in place for raising an alarm?

  • Are sufficient fire extinguishers provided, of the correct type?

  • Have fire extinguishes been inspected by a competent person within the last 12 months?

  • Is there suitable storage for gas and flammable substances?

  • Are all escape routes accessible and free of obstruction?

  • Is the fire assembly point clearly defined?

  • Fire Requirements

5.0 First Aid Provision

  • Is there a first aid kit large enough for the number of operatives on site?

  • Is the first aid kit adequately stocked?

  • Is there an eye wash facility available on site?

  • Is there an accident book on site?

  • Is there s sufficient number of qualified first aiders on site?

  • First Aid Requirements

6.0 Welfare facilities

  • Are suitable toilet facilities provided and kept in a clean and tidy state?

  • Is there a supply of fresh drinking water?

  • Are suitable rest facilities provided?

  • Is there a means of making warm drinks and heating food?

  • Are suitable hand-washing facilities provided?

  • Welfare facilities

7.0 Traffic Management

  • Has vehicular traffic including plant and delivery vehicles on site been suitably risk assessed?

  • Is there a suitable traffic management plan in place?

  • Are pedestrian and vehicle/plant movements suitably segregated?

8.0 - Operative/ContractorTraining (general)

  • Contractor Reviewed

  • Have site operatives/contractors been briefed on the findings of the risk assessments, COSHH assessments and Method Statements/Safe Systems of Work?

  • Are regular on-site toolbox talks being undertaken?

  • Enter the date of the last toolbox talk.

  • Have all operatives/contractors been safety inducted onto site, with a record held?

9.0 - Asbestos

  • Does the project involve refurbishment?

  • Has the site manager attended asbestos awareness training?

  • Has a relevant survey been completed?

10.0 - Working at Heights scaffolding

  • External scaffolding

  • Are fixed scaffolds in use on site?

  • Is there a relevant design available on site TG20 or bespoke?

  • Is a Scaff-tag displayed close to the entry point to the scaffold?

  • Has the scaffold been inspected by a competent person within the last 7 days?

  • Are all working platforms fully boarded?

  • Are double handrails provided on all working platforms?

  • Are toe boards provided on working platforms?

  • Are all access ladders in good condition?

  • Are access ladders correctly secured and extended above the stepping off point?

  • Is the scaffold adequately tied where appropriate?

  • Does the scaffold appears to be fit for purpose?

11.0 - Working at Heights

  • Are tower scaffolds in use on site?

  • Are scaffolds erected/signed-off by a competent person e.g. PASMA qualified?

  • Are double hand-rails provided on all working platforms?

  • Do all towers appear to be erected correctly?

12.0 - Working at Height-selection of work equipment

  • Are ladders, steps, hop-ups or similar in use on site?

  • Is the equipment of the correct grade?

  • Class 1 'industrial use' or EN 131 'heavy duty'

  • Does the equipment appear to be in good condition?

  • Is the equipment being used in a safe manner?

13.0 - Confined Spaces Working

  • Is there any confined spaces working on site?

  • Has an emergency plan been formulated specific to the works?

  • Is the work controlled under a permit-to-work system?

  • Have those undertaking the work received sufficient training?

  • Is there the possibility of a lack of oxygen within the space?

  • Has breathing apparatus been provided and are the operatives trained in its safe use?

  • Is there the possibility of a flammable atmosphere within the confined space?

  • Are none sparking tools and equipment in use and have all potential sources of ignition been extinguished?

14.0 - Excavations

  • Are there any excavations on site?

  • Has the excavation been inspected by a competent person within the last 7 days?

  • The excavation must not be used until signed-off as safe by a competent person!

  • Do site management undertake excavation inspections at the start of each shift?

  • Does the shoring appear to be adequate?

  • Has edge protection been provided to prevent persons or plant falling into the excavation?

  • Does the excavation appear to be in a safe and secure condition?

15.0 - Cranes & Lifting Equipment

  • Are cranes in use on site?

  • Has the crane been subject to thorough examination?

  • Are there suitably qualified people to supervise the lifting operations?

  • Are lift operations being correctly planned?

  • Has a safe system of work been put into place?

  • Is any lifting equipment being used on site?

  • Has the equipment been subject to a thorough examination?

  • Accessory for lifting: 6 monthly
    Equipment for lifting people: 6 monthly
    All other lifting equipment: 12 monthly

  • Are lifting operations being correctly planned?

16.0 - General Work Equipment

  • Has all main work equipment been added to the site equipment register?

  • Is there evidence of electrical appliance testing having been completed?

  • Do management undertake regular inspections of work equipment?

  • Does all general work equipment appear to be in good condition?

  • Is there any tool/equipment specific formal training required?

  • Has the required training been provided?

17.0 - Noise

  • Are there any operations being undertaken which expose workers to potentially high levels of noise?

  • Have the noise levels been assessed or estimated?

  • Have noise control areas been defined?

  • Are operatives wearing hearing protection?

18.0 - Vibration

  • Are any tools/equipment in use which may expose workers to high levels of vibration?

  • Have vibration levels and safe work limits been assessed or estimated?

  • Is it likely that safe working limits may be exceeded?

  • Stop the work until suitable controls are identified & implemented.

19.0 - Dust management

  • Identify any operations causing construction dust

  • Has a robust risk assessment been undertaken to manage construction dust?

  • Are FFP3 masks available and in use?

  • Does the operative hold face fit certification?

  • Is the operative clean shaven?

  • Is water suppression in use for silica based materials?

  • Is dust extraction available for specified tools in use?

  • Dust management

20.0 - Site Waste Management

  • Have suitable skips been provided for waste collection?

  • Is waste being segregated into suitable waste streams (considering possibilities for recycling)?

  • Is all hazardous waste being segregated and disposed of correctly?

  • Is waste being removed from the work areas regularly to prevent a build-up?

  • Is waste being removed from site by a licensed waste carrier?

21.0 - General Site Conditions

  • Is the site secured against unauthorised access?

  • Have suitable warning signs been posted at entry points to the site and at approx. 30 meter spacing around perimeter fencing?

  • Are access and egress routes maintained clear and unobstructed?

  • Have exclusion zones been set-up around any higher risk activities?

  • Are operatives wearing the correct PPE?

  • Are any holes or openings suitably covered when not in use?

  • Has sufficient background/task lighting been provided and being used?

Corrective Actions

  • HIGH Level Risk:

    Compliance: failure to meet legal compliance or serious safety issue which may lead to prohibition or improvement notice action being issued by a visiting enforcement officer.

    Recommendations: actions to be rectified as soon as is reasonably practicable.

  • Corrective Actions (high risk)

  • High Risk
  • Add media

  • undefined

  • MEDIUM Level Risk:

    Compliance: failure to meet with general standards expected of a competent contractor, industry best practice procedures or safety issues which may lead to minor accident or incident.

    Recommendations: actions to be rectified prior to next CDM site inspection (where external support is required e.g. Safety courses, then it is acceptable to have these planned and booked prior to next inspection).

  • Corrective Actions (medium risk)

  • Medium Risk
  • Add media

  • undefined

  • LOW Level Risk:

    Compliance: action identified by the inspector to improve contractor safety management procedures or standards but unlikely to lead to enforcement action being taken.

    Recommendations: actions may not be considered as compulsory, but would portray the company in a positive light and allow the contractor to show commitment to improving site safety management procedures and/or standards.

  • Corrective Actions ( low risk)

  • Low Risk
  • Add media

  • undefined

Sign off

  • On site representative

  • Auditor

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.