Title Page
-
Conducted on
-
Prepared by
Concrete Pre-Pour Checklist
-
ITP #:
-
CTSC CP#:
-
Bldg/Station:
-
Location:
-
Segment #:
-
IFC Drawings #:
-
Starting Date
-
Pouring Date
1.0 Pre-Construction Documents
-
1.1 Applicable Technical Documents (IFC, RFIs, SIs, etc.)
-
1.2 Waterproofing checklist has been completed prior to start pour. (If applicable)
2.0 Formwork, False work and Surface Preparation
-
2.1 Formwork installed and secured in place as per contract documents and approved shop drawings; elevations, alignment and contract tolerances achieved, and have been inspected and verified by, signed off by P. Eng or Competent person.
-
2.2 All embedded items (Hydrophilic strips, water stops, re-injectable grout tubes etc.) and openings within this section/unit are installed as per contract documents and shop drawings.
-
2.3 Substrate materials or accepting concrete surface prepared roughened, hardener, >5'C<30'C etc.
-
2.4 work area safe access/egress and working platform in place
-
2.5 Formwork's Subcontractor completed checklist
-
2.6 Check weather conditions, Curing measures on site - Burlap - Polythene - Thermal Blankets
-
2.7 Formwork/ground clear of ice and debris and ready for concrete placement
-
2.8 Construction joint check Concrete Surface (rough, cleanness, shape), Bonding Agent, etc.
-
2.9 Expansion Joint was installed as per drawing details and supplier recommendations.
-
Subcontractor Quality Representative (Name) and SIGNATURE:
3.0 Reinforcement (Subcontractor and CTSC)
-
3.1 Re-bars are installed and secured in place as per contract documents and reviewed shop drawings.
-
3.2 Cover dimensions & splice lengths meet design & specifications, with adequate ties, chairs, & supports installed
-
3.3 All embedded materials installed in proper location & orientation; adequately secured to prevent movement during the pour
-
3.4 Surface Temp for rebar >5'C<30'C
-
3.5 Completed Rebar's Subcontractor checklist.
-
Subcontractor Quality Representative (Name) and SIGNATURE:
-
CTSC Field Representative (Name) and SIGNATURE:
4.0 Mechanical Conduits
-
4.1 Mechanical Conduits and Sleeves are installed and secured in place as per contract documents, approved ITP, and shop drawings.
-
4.2 CTSC/Subcontractor completed checklist
-
Subcontractor Quality Representative (Name) and SIGNATURE:
5.0 Pre-Pour preparation
-
5.1 Anchor Bolts, steel plate are installed (dimensions, Layout) and protected.
-
5.2 Survey layout completed. Critical dimensions and elevations checked as required.
-
Formwork Subcontractor Surveyor (name) SIGNATURE:
-
For Self-Performance Works: CTSC (Quality, Forman, Superintendent as applicable) will sign all the items above (2.0-5.0) where applicable
-
Comment:
-
*CTSC Superintendent (name) and SIGNATURE:
-
CTSC Quality Coordinator (name) and SIGNATURE:
-
* Responsible to release the completed checklist