Title Page
-
Conducted on
-
Prepared by
-
Site
Arrive on site
-
Contact lone working buddy / WhatsApp group to inform them you have arrived
Perimeter Check
-
Walk around and inspect entire site, including grassed areas
-
Any signs of damage, vandalism, signs of rough sleeping?
-
Any signs of forced entry to the building
-
Clear rubbish to bins
Enter site via Stage Door
-
Check alarm logs. Note any errors
-
Check BMS is running, check event log. Note any issues (disregard equipment alarms for items intentionally shut down)
Fire Alarm Weekly Test
-
Date of test
-
MCP address
-
MCP triggered alarm?
-
Alarm / Voice announcement heard in foyers
-
Strobes working in bars
-
Alarm / Voice announcement heard in main auditorium
-
Strobe working in main auditorium
-
Alarm / Voice announcement heard backstage?
-
Both passenger lifts park at ground level
-
Prox doors release
-
BMS indicates fire state
-
Update Weekly Test Sheet in Fire Folder at Stage Door
-
Any notes
Building Inspection
-
Walk around entire site, note any issues
-
Any signs of forced entry?
-
Location of door
-
Can it be made safe and secure?
-
Any further work needed?
-
Any flooding, or signs of water dripping from radiators etc
-
Location of issue
-
Can it be isolated / made safe?
-
Is further work needed? Clean up required?
Plant Inspection
Roof Plant Area
-
Any signs of leaks, flooding, issues?
-
Location of issue
-
Can it be isolated / made safe?
-
Is further work needed? Clean up required
Follow Spot Box Plant Room
-
Any signs of leaks, flooding, issues?
-
Location of issue
-
Can it be isolated / made safe?
-
Is further work needed? Clean up required
Boiler Room
-
Any signs of leaks, flooding, issues?
-
Location of issue
-
Can it be isolated / made safe?
-
Is further work needed? Clean up required
-
All equipment dormant (unless in timed period of activity)?
-
Temp / pressure gauges on closed systems within ranges (for dormancy)?
Access Control System
-
WinPak PC running ok?
-
Check error log. Note any issues
Dormant Equipment
-
Run FoH lift from LF to Mezz (do not ride in lift)
-
Run BoH lift from LF to UF (do not ride in lift)
-
Any hydraulic leaks in platform lift cabinets?
Run 2x split air-conditioning units on heat & cool. Note locations.
-
Unit 1
-
Location
-
Unit 2
-
Location
Freezers - check running and contents still frozen
-
Ice Cream Parlour
-
Cloak Room
-
Main Kitchen (walk in fridge / freezer)
-
Cafe freezer
CCTV
-
Check NVR is running, check error log, check playback
-
All cameras connected?
-
Remote link to app working?
Meter Readings
-
Date of readings
Electricity - in LV Switch Room
-
Elec Rate 1
-
Elec Rate 2
-
Elec Import
-
Elec Cust Reg 1
-
Elec Cust Reg 2
-
Elec Total
Gas - Intake room, on large meter tank
-
Gas
Water - Intake room, meter next to isolation valve
-
Water sub meter
Finish work, exit site
-
Complete Lone Working Checklist. Scan and send to PS
-
Return all plant to dormant / timed state. Return all keys. Turn off all lighting. Lock all internal doors.
-
Set alarm, lock Stage Door
-
Update Lone Working WhatsApp group to say you are leaving site