Information
-
Document No.
-
Work order number
-
Location/F #
-
Project manager
-
Inspector/Buckeye Person In Charge
-
Contractor
-
Conducted on
-
Prepared by
PROGRAM ADMINISTRATION
-
Postings of possible hazards visible
-
Emergency numbers / contacts posted
-
Contractor Safety Manual - onsite and available
-
First aid kits onsite and adequately supplied
-
List all contractors
-
Emergency action plan posted / up to date
-
Verify completed HWA<br><br>Is HWA properly filled out with all applicable Information? All required signatures? Initial four gas readings taken and documented?
-
Verify completed JSA<br><br>Properly filled out and completed by contractors foreman? All tasks, Hazards and mitigations controls documented? All required signatures documented?
-
Verify completed ATW<br><br>Properly filled out with all needed Information? Required signatures are documented?
-
Verify completed LOTO/ Integrity List<br><br>Procedures followed and available? Verified correct individual lock out.
-
Verify completed CSP
-
Weekly safety meeting held and documented
-
Calabration / bump log filled out and current
PPE
-
Hard hats worn
-
Top layer of clothing Fire resistant NFPA 2112 29 CFR 1910.132(b-h)
-
Gloves being worn and adequate for the work activity
-
Face shields being used where required
-
Welding hoods being worn in conjunction with safety glasses
-
Eye protection being worn and adequate for the work activity
-
Hearing protection
-
Safety harness and lanyards utilized with adequate anchorage points
-
Respirators and masks utilized, when needed Filter correct for work activity
-
High visible clothing in use, when needed
HOUSEKEEPING
-
Work areas orderly and organized with material and tools properly stored
-
Adequate lighting
-
Job site free of slips, trips and fall hazards
-
Stairways / walkways clear
-
Trash picked up
-
Break areas orderly
ELECTRICAL / UTILITY
-
Is the voltage known
-
Minimum approach based upon voltage + 3 feet is being maintained to live lines and equipment
-
For energized work all blankets, gloves, sleeves, and live line tools have been tested appropriately, maintained, and stored correctly
-
Electrical equipment intrinsically safe
-
Insulation intact on cords and wiring
-
Temporary lighting guarded
-
Electrical panels labeled and covered
-
GFCI protection utilized
-
Lockout / tagout procedures utilized
HAND AND POWER TOOLS
-
Tools maintained in a safe and reliable condition
-
Proper tools being used for the job spark free if needed
-
All mechanical safeguards in use
MOBILE EQUIPMENT
-
Equipment grounded and bonded
-
Brakes, lights, signals, and alarms operative
-
Daily inspections filled out
-
Seat belts worn - LULLS, FORK TRUCKS, ETC.
-
Aerial lift - Harnesses and lanyards being used
-
Cranes - proper setup including distance to power lines
-
Cranes - ground conditions verified and safe for operation (underground wells, vaults, etc.)
-
Cranes- swing radius protected - level
-
Rigging equipment inspected - tag showing
BARRICADES
-
Barricades affixed with proper signage
-
Floor openings planked or barricaded
-
Wall, roof openings covered or barricaded
-
Leading edges guarded
-
Impalement hazards barricaded, protected, or eliminated
-
Open man way barricaded where needed
EXCAVATION
-
One call system in place
-
All permits and approvals completed before ground disturbance
-
Underground utilities have been located and marked
-
Daily documented inspections have been performed by a competent person
-
Adequate benching, sloping, and/or trenching in place by soil type
-
Access and egress means provided
-
Spoil pile set back at least 2 feet
-
Spotter used during excavating
-
Is the excavation more than 5ft, if so, is it adequately protected and has air monitoring been performed and documented
-
Bucket has no teeth exposed
-
Is excavation within two feet of pipe? If so is it approved with site completed site safety plan
LADDERS
-
Ladders in good condition
-
Side rails extend 36 inches above landing
-
Proper for job and secure
-
Step ladders fully open when in use
-
Placement of ladder safe
SCAFFOLDING
-
All scaffolds plumb and level
-
Are adequate sills and base plates being used
-
Are scaffold planks installed correctly
-
Are guardrails including top and mid rail in place
-
To protect from falling objects, are toe boards or area barricaded below
-
Is fall protection being used in areas where required
-
Is there a scaffold tag and has it been inspected
-
Is there a safe access ladder, steps or equivalent means for safe access to the scaffold
-
Is the scaffold rated for the proper weight capacity
FIRE PREVENTION/PROTECTION
-
Are hot work permits in order
-
Air monitoring before and during hot work
-
All flammable and/or combustible materials have been removed or protected within the area
-
Fire extinguishers immediately available and inspection tags current
-
Is a fire watch monitoring the area
-
Compressed gas cylinders secured- upright- protected from damage
-
Compressed gas cylinder stored properly
-
Flashback arrestors installed properly
-
Fire blankets and/or spark containment being utilized
-
Welding flash screens being used as required
CONFINED SPACES
-
Proper permits filled out
-
Pre-entry meeting conducted
-
Permits posted at entry
-
LOTO in place if needed and procedures followed
-
containment's in place if needed
-
Atmosphere tested and results documented 02,Co,LEL,H2S,VOC/Benzene
-
Entry Supervisor has classified confined space and authorized entry
-
Everyone has been properly trained
-
Line separation / opening vessel to atmosphere
-
Rescue on site with all appropriate equipment and permits
-
Rescue plan filled out and available
-
Draw space if needed
TRAFFIC CONTROL
-
Traffic control in place where required
-
Work zones visible from all directions on roadways
Line Separation / Opening a vessel to atmosphere
-
LOTO procedures followed
-
Facility integrity list current and on site
-
Energy shut out verified
-
Atmosphere monitoring ongoing
INDUSTRIAL HYGIENE
-
Possible oil outlets are contained to prevent spills
-
All chemical containers properly labeled and SDS available
-
All regulated areas maintained ie. asbestos, lead, arsenic, Hex Chrome, etc.
-
All sources of fugitive dust are controlled ie. concrete grinding, road dust, etc.
-
All containers of hazardous or non-hazardous waste are labeled and properly stored or disposed
COMMENTS AND NOTES
-
Notes
INSPECTOR SIGNATURE
-
I have been given a copy of this audit and instructed on the findings of this audit and will make all necessary corrections if applicable. All immediate safety issues have been corrected or stop work procedure in place.
Auditor Signature
-
Any issues found have been addressed to the correct persons and corrected