Safety Checklist for 110KV Underground Cable Project
-
Project Name:
-
Contract No.
-
Location:
- Al Maather
- Al Hazem
- Al Waha
- Al Marjhan
- Hindawiah
- Khuzam
- Murjan
- Taima
- Hail
- Madinah
-
Circuit Route:
-
Inspection Report:
-
Inspection Date:
DESCRIPTION OF CHECKS
-
1. Baladiya/Municipality valid permission
-
2. Maroor/Traffic valid permission
-
3. Other concern authorities/parties valid permission (STC, telecoms, water departments and etc.)
-
4. Traffic route diversion required
-
5. Test pit/underground utilities surveillance done
-
6. Approved Safety Officer designated
-
7. Working area completely isolated
-
8. Conrete barrier aligned and placed 0.5 meters apart
-
9. Oranged colored safety plastic mesh installed
-
10. Rotating/beacon lights in every trench corner and entry installed
-
11. Lighting bulbs and LED lights installed
-
12. Project information board in both ends of the whole trench installed.
-
13. Warning and information signs installed.
-
14. Access ladders and egress installed.
-
15. Pedestrian temporary access bridges installed.
-
16. All equipment's has valid 3rd party inspection certificate.
-
17. Dump trucks/vehicles used has valid government registration.
-
18. All operators and drivers has valid traffic and 3rd party illegibility/competency certification/licence.
-
19. Fire extinguishers provided in motorized equipments.
-
20. First aid kits provided adequately.
-
21. All project personnel has complete PPE (shoes, helmet, vest)
-
22. Toolbox meeting conducted.
-
23. Removal of excavated materials from the site and disposed in an approved area.
-
24. Proper housekeeping implemented.
-
25. Proper shoring/slope protection installed.
-
26. Subcontactor approved from National Grid.
-
Prepared by:
-
Signature
-
Approved by Safety Consultant:
-
Signature of Safety Consultant: