Title Page
-
Name of Dignity Employee Issuing Permit to Work
-
Name of Contractor/Company
-
Contractor Name/Names
-
Contractor Name/Names
-
Contractor email address
-
Contractor contact number
-
Location/Work Site
-
Inspection Date & Start Time
-
Contractor RAMS & public liability insurance documents received
-
Dignity Employee to sign giving authorisation for the work to be carried out and has notified the relevant personnel
-
Contractor to sign to say that they understand the conditions of this permit
-
Is the work been carried in an area that contains asbestos (Check asbestos register if unsure)
-
Seek assistance from Management to issue an Asbestos Work Permit
Permit Request
-
Work Activity Title
-
What level of risk is the work?
-
Type of Work
- General
- Hot Work
- Confined Space
- Excavation
- Plant Isolation
- Work at Heights
- Live Electrical Maintenance Work
- Other
-
Start of Work
Safety Precautions (To be completed by the person responsible for carrying out the work)
-
Have you been inducted to the area where the works are taking place
-
Have you received instruction of the site safety rules
-
PPE is mandatory in work areas of Dignity Manufacturing. Do you know the requirements for the location where work is being undertaken?
-
Is the workforce qualified to carry out the task?
-
If working in a confined space have air samples been taken?
-
Is any electrical supply isolated? Working in accordance with with Electricity Work reg's
-
Is voltage detection instrument required?
-
Isolator locked off / tagged out? Work in accordance with I.E.E Wiring regs. (BS7671)
-
Are ladders or scaffolding required? If yes, are they in a safe condition and ready to use?
-
Is a license required and in place for scaffold?
-
Are you aware of Dignity's evacuation procedure?
-
Is there a risk of falling objects?
-
Are you required to work on a fragile roof? If so are details and dangers explained?
-
Are fire extinguishes associated with the task available?
-
Are people undergoing work trained in the use of fire extinguishers?
-
Have flammable liquids / materials been removed from the working area?
-
Have gas cylinders been properly secured ?
-
Is safe access and egress confirmed?
-
Are persons undertaking the work trained and supplied with breathing apparatus?
Precautions
-
Scaffolding checked and signed off
-
Ladder checked (to be tied / footed)
-
Area safe, clean and cordoned off?
-
Correct fire protection within 3m?
-
Fire guard required?
-
Area clear of combustible materials?
-
Sewers, drains, sealed within 6m?
PPE
-
Safety glasses
-
Hearing protection
-
Safety footwear
-
Hi viz
-
Gloves
-
Hard hat
-
RPE
-
Safety harness
Service to be isolated
-
Fire Alarm / Zone
-
Electrics
-
Gas? If so specify
-
Hazardous Chemicals
COSHH and Lone working
-
Has COSHH data been supplied with substances?
-
Have COSHH precautions been identified and implemented
-
Is work been carried out by a lone worker
-
If Yes is monitoring required
-
undefined
Authorization
Hand back
-
Contractor sign to certify that all work is completed and in safe condition. Upon signing the permit will be closed and any other works require a separate permit
-
Dignity employee to sign to certify that work is complete and the area is left safe and clean for operations to recommence