Does the gate type match the order?
-
Will there be a spare parts inspection going along with is order?
-
Check cable to spring clearance.
-
Are the spring jam nuts tightened?
-
Does the gate have a "tested by" sticker signed?
-
Is their a custom firmware and border crossing sticker by the tested sticker?
-
Is the DRB loop sticker on the MGC?
-
Is the diode jumper correctly installed? (+24V and C1-3)
-
Has the standard lower jumper been moved to 24V instead of 0V?
-
Has the (KA)key switch been installed and wired Correctly? (Green to IN4, white to IN6, and brown to 0V)
-
Is the EM01 installed?
-
Is the DM02 installed?
-
Were any extra devices installed?
-
Are all of the yellow marks correct?
-
Does the gate have the correct number of springs?
-
Is the hood gasket installed?
-
Does the gate have the correct UL sticker?
-
Does the gate serial number sticker match the box label?
-
Does the controller have all of the plugs?
-
Does the color match the order?
-
Is the gate set up for articulated?
-
Does it have the correct springs?
-
Does the gate have any accessories?
-
Is the flange correct?
-
Is the Vario grey section included?
-
Are the u-rails included?
-
Is the documentation package complete?
-
Do both doors slide into the channels without binding?