Structure

  • Is the structure as handed over to SGC found to be with acceptable tolerances in accordance to the construction issue drawings?

Membranes

  • Have the membranes been installed in accordance with the construction issue drawings and manufacturers recommendations and are free from damage?

Helping Hand Brackets

  • Have the helping hand brackets been installed as per the construction issue drawings?

Pull Out Testing

  • Where through bolts or other anchors have been used have the relevant pull tests been carried out?

Carriers & Channels

  • Have carriers & channels been installed in accordance with the construction issue drawings, relevant system suppliers manual where applicable and torque settings checked?

Fire Barriers (HOLD POINT 1)

  • Siderise Product type

  • Is the Product installed in the correct direction(Siderise logo parallel to the supporting structure)?

  • Have joints been tightly abutted and sides taped using RFT on both sides?

  • Are Siderise OSCIs being used on the back of the panel and Siderise guidance been followed?

  • Has the product been installed with 10mm compression?

  • Has the product been installed with brackets at 600mm centres(1bracket if less than 300mm) with non-combustible fixings?

  • Is the product correctly secured ensuring no gaps between the barrier and supporting structure?

  • Is the vertical barrier taking priority(horizontal barriers abbuting to the side of the vertical)?

  • Has thermal insulation cut back so that the barrier is installed against the supporting structure?

  • Are facade rails and brackets tightly abutted(gaps to be packed with product and sealed with RFT or Fire & Acoustic mastic)?

  • Are there any penetrations through the barrier and are they been treated following Siderise guidance?

  • Have Siderise brackets been used correctly, at 400mm centres with non-combustible fixings and and in the correct direction?

  • Is the product correctly secured ensuring no gaps between the barrier and supporting structure?

  • Is the air gap between the intumescent face and the back of the cladding panel a maximum of 25mm including at bracket locations?

  • Have the product been installed with the purple logo tape facing up?

  • Is the vertical barrier taking priority(horizontal barriers abbuting to the side of the vertical)?

  • Has the product been installed with the intumescent strip facing the facade?

  • Are the panels flat fitted against the rails?

  • Has thermal insulation been cut back so that the barrier is installed against the structure?

  • Have joints been tightly abutted and top side taped using RFT(no tape on front face)?

  • Have corner joints been mitred?

  • Are facade rails and brackets tightly abutted(gaps to be packed with product and sealed with RFT or Fire & Acoustic mastic)?

  • Are there any penetrations through the barrier and are they been treated following Siderise guidance?

  • Have Siderise brackets been used correctly, at 400mm centres with non-combustible fixings and and in the correct direction?

  • Is the product correctly secured ensuring no gaps between the barrier and supporting structure?

  • Is the air gap between the intumescent face and the back of the cladding panel a maximum of 25mm including at bracket locations?

  • Have the product been installed with the yellow logo tape facing up?

  • Is the vertical barrier taking priority(horizontal barriers abbuting to the side of the vertical)?

  • Has the product been installed with the intumescent strip facing the facade?

  • Are the panels flat fitted against the rails?

  • Has thermal insulation been cut back so that the barrier is installed against the structure?

  • Have joints been tightly abutted and top side taped using RFT(no tape on front face)?

  • Have corner joints been mitred?

  • Are facade rails and brackets tightly abutted(gaps to be packed with product and sealed with RFT or Fire & Acoustic mastic)?

  • Are there any penetrations through the barrier and are they been treated following Siderise guidance?

Installation (HOLD POINT 2)

  • Has the insulation been installed in line with the manufacturers recommendations and guidelines?

Cladding Panels (HOLD POINT 3)

  • Have cladding panels been installed as the construction issue drawings?

Signature Page

Signature for and on behalf of Salisbury Glass Limited

  • Add signature

Signature for and on behalf of Galliard Homes

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.