Was a design specification (Written or verbal) or drawing provided to you?
-
Has the cabling & any associated containment been installed as per the design specification or drawing?
-
Have cables been installed with fire-rated fixings that will prevent premature collapse in the event of a fire?
-
Please upload photo evidence of "fire-rated" fixings or containment throughout the cable run here
-
Has any switchgear/accessories been located within 200mm of a sink, bath, shower or hob?
-
Have all Cooker, TV and Data points been fitted with 47mm deep back boxes?
-
Have all cables/conductors been appropriately labeled or marked ( SL, Load, Feed, Etc)?
-
Has all cabling been run in permitted safe zones?
-
Have all cables been cut to appropriate length (not exceeding 2 x box width) at boxes?
-
Are all cables dressed neatly and tied/fixed horizontally and vertically at 600mm maximum spacings?<br>
Works Completion
-
Have any material purchases been assigned suitable Purchase orders (PO's) on Workflow max?
-
Has the first fix work been fully completed?
-
Has any hazardous waste been generated (fluorescent lamps, electronics etc)?
-
Have all unused materials been returned to the company store/office?
-
Has the work area been left clean and tidy, with all debris removed and disposed of appropriately?
-
Please provide images of work area before and after work activity
-
Have all staff time sheets associated with the job been submitted online?
-
What was your arrival date/time on site?
-
What will be your departure date/time from the site?